Summer Sale - Limited Time 55% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 5763r953

Welcome To DumpsPedia

C_S4PPM_1909 Sample Questions Answers

Questions 4

What is a prerequisite for using role charts in project management?

Options:

A.

The demand of a role must have been updated according to tasks

B.

A graphic profile is assigned to the role type

C.

A graphic profile is assigned to the project type

D.

The demand of a role must be distributed over a number of periods

Buy Now
Questions 5

Where can you create a status for a what-if scenario in portfolio management/

Options:

A.

In the what-if scenario classification

B.

In the review

C.

In the what-if scenario type

D.

In customizing for the portfolio type

Buy Now
Questions 6

Which of the following are consequence of releasing a phase?

NOTE: There are 2correct answers to this question

Options:

A.

Predecessor phases are assigned the status locked

B.

Lower-level tasks and checklist are release

C.

Additional tasks cannot be added to the phase

D.

The phase type is set to read-only

Buy Now
Questions 7

You want to control the execution of subsequence phases in project management.

Which indicators must you activate in the phase type in customizing?

NOTE: There are 2correct answers to this question

Options:

A.

The Release Success phase only after Approval indicator

B.

The approval phase indicator

C.

The completion required indicator

D.

The complete phase when Granting Approval indicator

Buy Now
Questions 8

Which of the following multi-currency scenario are supported?

NOTE: There are 2correct answers to this question

Options:

A.

Multiple planning currencies can be used in one bucket

B.

Item currency can be inherited from the assigned bucket

C.

Bucket in a portfolio can use different currencies

D.

Items In a bucket an only use bucket currencies

Buy Now
Questions 9

You are in portfolio management and create a project system (PS) project from an item.

Which parts you add afterwards directly in PS?

NOTE: There are 3 correct answers to this question

Options:

A.

Network activities

B.

PS texts

C.

Documents

D.

Network components

E.

WBS elements

Buy Now
Questions 10

You have defined a financial view for portfolio bucket so that financial values are rolled up.

Which of the following are possible sources for the rollup?

NOTE: There are 3 correct answers to this question

Options:

A.

Project system project

B.

Project management projects

C.

Standalone items

D.

Initiatives

Buy Now
Questions 11

What is the priority field in the project definition of a project management project used for?

Options:

A.

To determine the scheduled dates for the project

B.

To determine the approval authorizations required

C.

To support the evaluation of projects

D.

To restrict the selection of project types

Buy Now
Questions 12

Where can you use stakeholders in portfolio management?

Options:

A.

Bucket

B.

Item

C.

Initiative

D.

Review

Buy Now
Exam Code: C_S4PPM_1909
Exam Name: SAP Certified Application Associate - SAP S/4HANA Portfolio and Project Management
Last Update: Apr 17, 2024
Questions: 80
$72  $159.99
$54  $119.99
$45  $99.99
buy now C_S4PPM_1909