Answer the following questions about the DSDM Lifecycle.
Decide if each observation is an appropriate application of Agile Project Management for
this project and select the option that supports your decision.
When the project was in the Feasibility phase it was initially proposed by the Finance
Manager that it was a fixed price for a fixed specification ' project. The Project Manager
has decided that the best way to tackle it would be to leave the development of the least
valuable features of the product until last.
Is this an appropriate application of the DSDM lifecycle?
Resources are limited. The Sales Manager has two marketing assistants who
may be able to give a few hours a week between them to the project.
What action should the Project Manager take?
Column 1 is a list of individuals from within the Xan Insurance Company
and their key responsibility within the Web project.
For each individual in Column 1, select from Column 2 the Agile Project
Management team role they are fulfilling. Each selection from Column 2 can
be used once, more than once or not at all.
Column 1
Manager of Web & Digital
Media - will oversee and report
progress on the delivery of the
overall system.
Finance Director - has
budgetary control and will
release finance for the project
subject to expected benefits.
Sales Manager - will formulate
design options for new
business processes that do not
adversely affect business as
usual.
Operations Manager - oversees
the design and integrity of the
technical aspects of the
solution.
Column 2
Business Sponsor
Business Analyst
Business Ambassador
Business Advisor
Solution Developer
Technical Coordinator
DSDM Coach
Project Manager

Which is the BEST reason to remind learners of related knowledge or skill they already possess?
When receiving instruction on practical skills, which approach is MOST valuable to the learner?
Which Facilities stakeholder is MOST likely to be placed within the ‘external’ segment for the relocation work of the Operational delivery processes workstream?
Which participant characteristic is likely to be the MOST appropriate to the success of a workshop to design a process?
Answer the following question about the agile change practices that are being
used by the Change Manager.
Column 1 lists statements made by the change team. For each statement in
Column 1, select from Column 2 the relevant agile change practice being
used.
Each selection from Column 2 can be used once, more than once or not at all.
Column 1
A new company logo, which
maintains features of the
existing UniCo logo, but also
represents expertise in
innovative solutions and mobile
applications, is needed as a
high priority for the rebranding
of UniCo.
Next time we work with the
Sales Team we will need to
schedule the fast-track training
of the Sales staff more carefully
as taking a member of staff
away from the sales work
caused operational issues.
3. Gaining access rights to make
amendments to UniCo ' s new
finance system is currently
causing issues and holding up
the updates to enable the
system to work with the new
processes.
The company procedures for
delivering large-scale computer
systems will need to be revised
to reflect the new processes for
mobile applications, taking an
estimated 60 days of effort.


To ensure that the UniCo change programme is successful, the Chief Executive Officer (CEO) knows that correctly assigning the key change roles will be essential.
Which 2 Sales Team Leaders (TL) are likely to be the line leaders MOST engaged in implementing change, based on the actions that have occurred to date?
Using the information provided in the additional information, answer the following question on building a change analytics strategy.
Do the measures to be monitored by the CEO represent appropriate ‘leading’, result-oriented measures for the effectiveness of the change interventions?
Answer the following questions about applying the principles for building
engagement to the Change Programme, defined by Hodges.
Which 2 actions demonstrate inclusivity?
The Change Manager is discussing the relocation of the Selco staff to the UniCo office with the Operations Director. They are using the SCARF framework of people ' s social experience to guide management actions. Answer the following questions about the use of David Rock ' s SCARF framework to increase the motivation for change.
On seeing plans for the office move, the Selco staff are worried that some desk allocations do not have access to natural light. The relocation leadership team held a workshop as soon as the issue was raised and has allocated these desks to be ‘hot-desks,’ not used by staff permanently based in the office.
Is this an appropriate approach to reward the brain in the need for ‘certainty,’ and why?
As Project Increment 4 progresses, the project team must choose the MOST effective communication methods for internal and external stakeholders. The Power/Interest Grid, created in the Foundations phase, is updated as needed when stakeholder influence or interest changes.

For each scenario in Column 1, select the MOST effective communication method from Column 2 to ensure successful
outcomes and minimize risk of failure. Each selection in Column 2 can either be used once only or not at all.

Time is running short and the Must Have requirements for the data entry screen
of the web page, as recorded in the Prioritised Requirements List, are not going
to be completed on time.
What action should the Project Manager take?
(During the Foundations phase, Brinda Vyas organized a workshop that Hira facilitated. It was attended by Sukra Aroon, Mira, Lee Tan, and Developers from the two Delivery Teams. The goal was to define and align on what would be available for guests at the end of Project Increment 4.
Considering the workshop attendees, which of the following observations aligns with AgilePM?)
During the Foundations phase for Project Increment 4, Sukra Aroon held a meeting with Hira, Mira Bachar, andWanida Anong, to ensure alignment and compliance with EPR company policies, local regulations, and international standards. The meeting also clarified how financial and investment decisions would be made for Project Increment 4, ensuring alignment with EPR business priorities, and how this information will be tracked,
controlled and evidenced.
Wanida Anong, who works across multiple sites worldwide, attended the meeting in person but has limited availability throughout the Project Increment.

(On receiving the meeting invitation, Hira responded suggesting that Brinda Vyas should also be invited to the meeting. Based on AgilePM guidance, which of the following does NOT present an appropriate justification for Brinda Vyas ' attendance?)
Using the additional information provided for this question in the
Scenario Booklet, answer the following question about using Kotter ' s
eight-processes cyclical model. This model is being used for planning
and leading the change required to rebrand and reposition UniCo in the
market place.
Lines 1 to 4 in the table below consist of an assertion statement and a reason
statement. For each line identify the appropriate option, from options A to E,
that applies. Each option can be used once, more than once or not at all.



Which 2 actions should the Team Leader take to implement the new Must
Have requirement?
Which 2 actions should the Business Visionary take to implement the new
Must Have requirement?
Using the information provided in the additional information, answer the following question on building a change analytics strategy.
Are the measures and source data to be monitored by the Human Resources and Facilities Manager likely to have any of the limitations of data analytics?
Which ' event ' BEST offers the opportunity to connect learning to the wider change initiative?
The Change Manager has mapped stakeholders onto a Power-Interest
Matrix, with the aim of identifying suitable actions for managing these
stakeholders.
The mapping below shows the current assessment made by the Change Manager.
The ' Interest in your change ' axis indicates a combination of the
stakeholders ' levels of active engagement and their buy-in for the Change
Programme.

Using the Scenario and the additional information provided for this question in the Scenario Booklet, answer the
following question about Stakeholder mapping and strategy.
Lines 1 to 4 in the table below consist of an assertion statement and a reason statement. For each line identify the
appropriate option, from options A to E, that applies. Each option can be used once, more than once or not at all.



Using the project timeline given in the Project Scenario, answer the following question about application of Timeboxing on the Hoy Hall project.
Lines 1 to 5 in the table below consist of an assertion statement and a reason statement. For each line identify the appropriate option, from options A to E, that applies.
Each option can be used once, more than once or not at all.

Assertion :
1. All internal works to be assigned to Timber Tigers throughout the project should be consolidated into one Structured Timebox.
BECAUSE
The Investigation step within each Structured Timebox requires everyone working within the team to jointly agree how the requirements of the Timebox will be met.
2. Acceptance criteria for the front rooms to be developed in Timebox A should be described in detail and agreed during the Timebox Kick-Off
BECAUSE
The aim of the Investigation step within each Timebox is to complete as much of
the development work as possible.
3. It is appropriate that both the Evolutionary Development phase and Deployment phase are shown in the first Project Increment.
BECAUSE
Each Timebox should comprise an Evolutionary Development phase and
Deployment phase.
4. It is appropriate that the outputs of Timebox C are scheduled for deployment at the end of the first Project Increment.
BECAUSE
A typical Timebox Plan should provide a schedule of high-level activities for the
imminent Project Increment.
5. It is appropriate that Earth Excavations create a detailed plan of activities they will complete during Timebox C.
Reason
BECAUSE
The Solution Development Team is responsible for planning the detail of all the
work of each Timebox.


Which 2 actions should the Workshop Facilitator take when preparing for the workshop?
Using the Project Scenario and the additional information provided for
this question in the Scenario Booklet, answer the following questions
about Feasibility.
Remember to limit your answers to the number of selections requested in each
question.
Which 2 statements describe the appropriate application of Agile Project
Management when developing the Delivery Plan?
Column 1 is a list of actions taken within the project. For each action in Column 1, select from Column 2 the iterative development activity that the action represents. Each selection from Column 2 can be used once, more than once or not at all.
Column 1:
1. The Solution Development Team cleared and prepared the area, ready for the bar infrastructure to be installed.
2. The Gardener decided the order in which the flowers would be planted in the borders and jotted it down in a notebook.
3. Before the Solution Development Team built the infrastructure for the bar area, the Architect pointed out what was required.
4. The Architect checked with the decorators that tasks had been completed to a satisfactory standard, and agreed a list of items that needed further coats of paint or cleaning up.
5. The Gardener began planting the borders and has placed an order for further bulbs to complete this task.
Column 2:
A) Thought
B) Action
C) Conversation

Using the Project Scenario and the additional information provided for this question in the Scenario Booklet, answer the following questions about Feasibility.
Remember to limit your answers to the number of selections requested in each question.
Which 2 statements describe the appropriate application of Agile Project Management when developing the Solution Architecture Definition (SAD)?
Using the Project Scenario and the additional information provided for this question in the Scenario Booklet, answer the following question about the
responsibilities of the roles in the Agile team.
Lines 1 to 5 in the table below consist of an assertion statement and a reason statement. For each line identify the appropriate option, from options A to E, that applies.
Each option can be used once, more than once or not at all.

Assertion
The Marketing Director, in the role of Business Visionary, is empowered to overrule cost restrictions advised by the Chief Accountant, who is appointed as Business Ambassador.
BECAUSE
The Project-level roles are responsible for directing, managing and co-
ordinating the project.
The Procurement Manager is an appropriate representative of the end user of the solution.
BECAUSE
The Business Ambassador should be empowered to make decisions within
the boundaries of their role, without referral to higher authorities outside
the Solution Development Team.
The other specialist gardening team members from Earth Excavations would be suitable as Solution Developers, assigned alongside the Head Landscape Gardener.
BECAUSE
Extra Solution Developers can provide a supporting role for a Lead
Developer.
The ' Hoy for Hoy Hall ' Action Group members should be assigned as Business Ambassadors.
BECAUSE
The Business Ambassador is responsible for ensuring that business needs
are properly analysed.
The Project Manager should plan the communication needed between the Marketing Director, in the role of Business Visionary, and the ' Hoy for Hoy Hall ' Action Group.
BECAUSE
The Business Visionary is responsible for promoting the business vision to
all interested parties.

Using the Project Scenario, answer the following question about the activities in the Agile project lifecycle.
Lines 1 to 5 in the table below consist of an assertion statement and a reason statement. For each line identify the appropriate option, from options A to E, that applies. Each option can be used once, more than once or not at all.

Assertion:-
1. The rooms and facilities must be deployed into live use at the end of each Timebox.
BECAUSE
Reason:
Evolutionary Development and Deployment must be combined in a Timebox where the integration of several teams is required.
2. The tasks associated with each Solution Development Timebox should be included
in the Delivery Plan.
BECAUSE
Reason:
A typical Delivery Plan will provide a schedule of Timeboxes and any other high level activities for the imminent Project Increment.
3. The development approach should have been agreed during Foundations.
BECAUSE
Reason:
The Development Approach Definition must be created before Evolutionary
Development can commence.
4. The resources from Timber Tigers and Earth Excavations should have been engaged
before the start of Evolutionary Development.
BECAUSE
Reason:
Commitment to delivery is based on pre-agreed resource levels at the project level.
5. A final Deployment phase should be held after Timebox C has completed.
BECAUSE
Reason:
The Deployed Solution is assessed post-project to confirm whether the expected benefits have been
achieved.


Using the Project Scenario and the additional information provided for
this question in the Scenario Booklet, answer the following questions
about Feasibility.
Remember to limit your answers to the number of selections requested in each
question.
Which 2 statements describe the appropriate application of Agile Project Management when producing an Outline Business Case to support the Feasibility Assessment?
Answer the following questions about the tracking and control activities carried out within the project.
Decide whether each activity has been applied appropriately and select the response that supports your decision.
During Foundations, the key stakeholders had very different views about the content and prioritisation for the high-level requirements. As a result, the Project Manager
organized a Facilitated Workshop with the project team to discuss and agree the requirements.
Is this an appropriate application of Agile Project Management for this project?
Find out who is responsible for challenging the priority of requirements and deal with them accordingly.
Who is responsible for approving that the change in priority of the requirement for a secondary exit from the upstairs of the building accurately reflects the scope of the
project in the Prioritised Requirements List?
Once the change of priority has been approved, who is then responsible for including the requirement for a secondary exit from the upstairs of the building to the Timebox
Plan for Timebox B?
There are several tests planned throughout the project to ensure the solution is fit for purpose and to validate the business solution as
it evolves.
Column 1 is a list of tests. For each test in Column 1, select from Column 2 the testing concept that it represents. Each selection from Column 2
can be used once, more than once or not at all.
Column 1
1) In order to get an objective
view, the financial transaction
function is to be tested by
someone from Finance who
has had no involvement in its
development.
2) Before the developer works on
the printing function for the
policy documents, the Sales
Manager will review a prototype
of the online application form
for the new coffee shop
insurance product with the
solution tester.
3) Security test scripts have been
provided by the company ' s
bank. These scripts will be used
to test the link from the
company ' s website to the
banking system, which is to be
developed specifically to achieve these tests
4.
The addition of the new coffee
shop insurance product may
threaten the stability of the
existing website. As a primary
route to market this is
unacceptable. The website ' s
capacity to run additional pages
is to be verified before any
other tests are performed.
5.
The Must Have and Should
Have requirements are to be
tested before the Could Have
requirements.
Column 2
Collaborative Testing
Repeatable Testing
Independent Testing
Prioritised Testing
Test-Driven Development

Midway through Project Increment 4, a joint Sprint Retrospective is held with Developers from both Delivery Teams.
Some members from Marketing and IT, based in India, join via video conferencing.
Issues raised:
. Dependency management challenges
· Concerns about AgilePM principle ' Demonstrate Control '
To address this, Mira Bachar and the Developers invite Hira and Sukra Aroon to help Delivery Teams understand the
issues, assess the consequences, and collaborate on solutions that align with AgilePM and Scrum.
In addition to the Developers, the teams include:

(Developers in the Infrastructure Team report integration issues between climate control and lighting systems, leading to an excessive energy demand beyond the capacity of the solar panels.
Which 2 of the following actions align with the AgilePM guidance on addressing risk?)
(Which 2 statements describe appropriate team behaviour for effective risk management?)
(Wanida Anong, working on some compliance issue in India, has limited availability to work with the Southeast Asia Delivery Teams.
Which 2 statements describe how this risk should be handled within the AgilePM framework?)
(Hira discovers that material costs are exceeding initial supplier estimates, leading to a 5–10% budget overspend.)
As Sprint 5 comes to an end, the Infrastructure Delivery Team is facing delays due to:
. Heavy rainfall affecting the Wellness Garden.
. Local supplier issues causing material delivery delays.
· Dependency on external contractors for hydrotherapy equipment.
The Operations Delivery Team is unable to finalize details of the hydrotherapy treatments without testing them in the
context of the facilities being constructed. The marketing materials cannot be generated until this work is complete.
In addition to the Developers, the teams include:

(Hira decides to update the Delivery Plan to prioritize the delivery of the hydrotherapy facilities first for early testing.
Is this action appropriate?)
(To keep Business Sponsor, Sarah, informed, Hira has set up a real-time dashboard displaying project progress, risks, and actions from planning events.
Will this meet Sarah ' s needs?)
Several of the web developers working on the project have no Agile
experience. When answering the questions in the Project Approach
Questionnaire (PAQ), the Project Manager could not agree with the statement
' all members of the project understand and accept the DSDM approach ' .
What action should the Project Manager take?
Answer the following questions about actions to be taken by different
roles.
The Business Sponsor has decided that the new coffee shop insurance
product website pages will include the financial transaction functionality to
support the end-to-end sales process. The Business Sponsor views this as a
valuable sales tool, enabling customers to pay for insurance policies online. If
successful, this new financial transaction functionality is to be made available
across all other insurance products. This is a new Must Have requirement.
All parties are to be invited to a workshop to discuss the additional work
required to deliver the required solution including the new Must Have
requirement. The areas to be discussed include specialist skills required and
possible legal, financial and technical standards to be adhered to.
Remember to limit your answers to the number of selections requested in
each question.
Which 2 actions should the Business Sponsor take to implement the new Must
Have requirement?
Xan Insurance Company operates from one location - a large, open-plan
office in the centre of a city. Those employees that will be working within the
Solution Development Team are all based in this office but work at different
ends of the office in separate departments.
What action should the Project Manager suggest to ensure the most effective
collaboration of the Solution Development Team?
An external web developer is to be contracted to create the new coffee bar
insurance area on the existing web site. The chosen web developer will only
agree to work on a ' fixed price for a fixed specification ' contract.
What action should the Project Manager take?
Answer the following questions about the contents of the DSDM
products.
Each of the following questions includes true statements about the project
but only two statements are appropriate entries for the DSDM product
identified.
Remember to limit your answers to the number of selections requested in
each question.
Which 2 statements represent appropriate entries for the Business Case?
(During the Foundations phase, Lee Tan raised concerns about the lack of detailed upfront requirements for the Eco-spa, fearing confusion, constant changes, uncertainty and inefficiency.)
Brinda Vyas and Mira Bachar have agreed to use content from a marketing brochure to describe guest-centric Product Goals for the Eco-Spa. These goals describe specific treatments that the Spa might offer and will be used to identify prioritizable Product Backlog items that could contribute to that treatment. One such Product Goal is described as:
Hydrotherapy in Mineral-Rich Spring Pools
Immerse yourself in mineral-rich hydrotherapy pools designed to soothe muscies, improve circulation, and promote
deep relaxation. Experience the gentle power of temperature-controlled waters and therapeutic massage jets in a lush
and tranquil tropical garden setting and let nature ' s healing embrace rejuvenate both your body and your mind.
In addition to the Developers, the teams include:

(Which one of the following statements does NOT align with AgilePM ' s MoSCoW prioritization?)
Towards the end of the Foundations phase of Project Increment 4, with the high-level requirements agreed, Hira, has asked the Developers to estimate the work required to deliver the Eco spa solution.

(What should the Developers do to ensure their estimates align with AgilePM guidance?)
Towards the end of the Foundations phase of Project Increment 4, with the high-level requirements agreed, Hira, has asked the Developers to estimate the work required to deliver the Eco spa solution.

(Which of the following describes AgilePM ' s approach to estimation?)