Winter Special Sale - Limited Time 60% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 575363r9

Welcome To DumpsPedia

CDT Sample Questions Answers

Questions 4

What is the procedure for guarding against defects and deficiencies before and during the execution of the work?

Options:

A.

Quality assurance

B.

Quality control

C.

Quality management

D.

Quality monitoring

Buy Now
Questions 5

A drawing set arranged in the following order is an example of what type of drawing organization?

Cover Sheet, Sheet Index, Life Safety, Demolition, Civil, Landscaping, Architectural, Interiors, Structural, Mechanical, Electrical, Plumbing, Fire Protection

Options:

A.

Traditional drawing set organization

B.

Uniform Drawing System

C.

AIA CAD Layer Guidelines

D.

BIM Implementation

Buy Now
Questions 6

What project scheduling technique involves setting the target date of building occupancy and then working backwards to establish preceding milestone dates?

Options:

A.

Methods technique

B.

Critical path method

C.

Front end loading

D.

Schedule of values

Buy Now
Questions 7

During the bid period, what does the architect issue if it is necessary to modify the procurement documents?

Options:

A.

Addenda

B.

Construction change directives

C.

Change order

D.

RFI response

Buy Now
Questions 8

Under SectionFormat®, where would the Article "Manufacturers" be found?

Options:

A.

Either Part 1 or Part 2

B.

Part 1 only

C.

Part 2 only

D.

Part 3 only

Buy Now
Questions 9

Which of the following is a format that standardizes the way text is arranged in specification pages so that it is best suited for easy reading and rapid reference?

Options:

A.

SectionFormat®

B.

PageFormat

C.

MasterFormat®

D.

UniFormat®

Buy Now
Questions 10

Peer reviews or internal reviews of completed documents are examples of what?

Options:

A.

Quality control

B.

Commissioning

C.

Quality assurance

D.

Construction administration

Buy Now
Questions 11

Cost classification, data organization, and specifications use which written formats?

Options:

A.

OmniClass and UniFormat

B.

UniFormat and MasterFormat

C.

OmniClass and MasterFormat

D.

SectionFormat® and MasterFormat

Buy Now
Questions 12

What activity helps the owner assess the viability of a project, evaluate financial resources, and understand the project's potential impact on the community?

Options:

A.

Schematic programming

B.

Site selection

C.

Due diligence investigation

D.

Master planning

Buy Now
Questions 13

Which term or word is appropriate to use in specification text?

Options:

A.

Any

B.

As per

C.

As required

D.

Work

Buy Now
Questions 14

Which document obligates the architect/engineer to review submittals during construction administration?

Options:

A.

AIA Document A201, General Conditions of the Contract for Construction

B.

AIA Document B101, Standard Form of Agreement Between Owner and Architect

C.

AIA Document D200, Project Checklist

D.

AIA Document G612, Owners Instructions to the Architect

Buy Now
Questions 15

You are working on a project that is subject to regulatory reviews both at the city and at the state level. Both agencies have acknowledged receiving the construction documents. This project has already been awarded to a general contractor, and you are representing the owner who wants to start construction immediately. How would you advise the owner?

Options:

A.

Construction may begin immediately as long as a safety manager is present, and the contractor avoids all excavation work until after the permits are issued.

B.

Since the state approval is more critical than the city approval, construction may proceed immediately after the state permits are issued.

C.

Since the city approval is more critical than the state approval, construction may proceed immediately after the city permits are issued.

D.

Construction may begin only after both city and state permits have been issued.

Buy Now
Questions 16

Which of the following terms describes the process of allocating resources for the continued performance of a building's intended function?

Options:

A.

Budgeting

B.

Commissioning

C.

Facility management

D.

Project closeout

Buy Now
Questions 17

Which bid form component ensures equal consideration, transparency, and flexibility while awarding a contract, but also manages cost during execution for undefined and unforeseen construction conditions?

Options:

A.

Bid security and substitution

B.

Add and deduct alternatives

C.

Allowances and unit prices

D.

Liquidated damages and combined bids

Buy Now
Questions 18

What four considerations are included in site selection programming?

Options:

A.

Use, space, funds, date

B.

Function, form, economy, time

C.

Purpose, shape, cost, schedule

D.

Goal, condition, budget, calendar

Buy Now
Questions 19

Which documents are commonly included as procurement documents?

Options:

A.

Project record documents

B.

Contract documents

C.

Consensus documents

D.

Bidding documents

Buy Now
Questions 20

Who has the right to stop the work if hazardous materials are encountered during the construction?

Options:

A.

Architect/engineer

B.

Contractor

C.

Stakeholders

D.

Facility manager

Buy Now
Questions 21

Which of the following participants is involved in the Integrated Project Delivery (IPD) method?

Options:

A.

Authority having jurisdiction

B.

Commissioning agent

C.

Contractor

D.

Inspector

Buy Now
Questions 22

What does the Integrated Project Delivery (IPD) process involve?

Options:

A.

A collaborative, integrated, and productive team composed of key project participants

B.

Traditional delivery methods and team relationships for improving project performance by understanding the qualifications and attributes of team members

C.

Responsibility silos for greater efficiencies, leading to project success

D.

Segregated knowledge gathered as needed with paper-based communications to team members

Buy Now
Questions 23

In construction documents, what does the agreement refer to?

Options:

A.

The agreement between the owner and the architect/engineer

B.

The general conditions of the contract for construction

C.

The agreement between the owner and the contractor

D.

The agreement between the contractor and the subcontractor

Buy Now
Questions 24

During the project closeout phase, what is an appropriate task for the facility manager?

Options:

A.

To ensure they have received the required spare parts, extra stock materials, and any necessary training needed in order to maintain the facility in the first year

B.

To coordinate with the architect a final clean-up and site restoration

C.

To hire a new security company to ensure maintenance and ground management

D.

To draft the final changes on the as-built documents

Buy Now
Questions 25

Under SectionFormat®, where would warranty requirements be specified?

Options:

A.

Division 01

B.

Part 1

C.

Part 2

D.

Part 3

Buy Now
Questions 26

To obtain progress payments, the contractor must submit an application for payment itemized in accordance with what?

Options:

A.

The construction schedule

B.

The subcontractor's invoices

C.

The schedule of values

D.

The percentage of completion

Buy Now
Questions 27

Where are the limits of the work of each alternate defined?

Options:

A.

Agreement

B.

Bid Form

C.

Division 01

D.

Sections in Divisions 02-49

Buy Now
Questions 28

Which of the following elements should be included in supplementary conditions?

Options:

A.

Requirements for a schedule of values

B.

Claims and dispute resolution requirements

C.

Equal employment opportunity requirements

D.

Termination of the work by owner or contractor

Buy Now
Questions 29

Which of the following is a component of the contract documents?

Options:

A.

Procurement requirements

B.

Resource drawings

C.

Shop drawings

D.

Addenda

Buy Now
Questions 30

Which of the following is NOT included in Divisions 02-49 of a project manual?

Options:

A.

General requirements

B.

Finishes

C.

Concrete

D.

Utilities

Buy Now
Questions 31

What is MasterFormat® keyword index used for?

Options:

A.

Identifying Level 4 sections

B.

Identifying specification format

C.

Locating subject titles and numbers

D.

Specifying correct word usage

Buy Now
Questions 32

When does a project reach substantial completion?

Options:

A.

When the project is sufficiently complete to allow its intended use

B.

When the project receives final inspections from the authorities having jurisdiction

C.

When the contractor's final application for payment is approved

D.

When all of the close-out documents have been reviewed and approved

Buy Now
Questions 33

What is Leadership in Energy and Environmental Design® (LEED®)?

Options:

A.

A set of sustainable standards with measurable recognized categories for a project

B.

A formula for determining a sustainable classification

C.

A system of prioritizing sustainable projects

D.

Standardized structure for organizing sustainable information

Buy Now
Questions 34

When innovative or unusual design techniques are proposed, it is advised to have what type of review?

Options:

A.

Sustainability

B.

Budget

C.

Constructability

D.

Design

Buy Now
Questions 35

How long after bid opening is a bidder required to honor their bid price for a project?

Options:

A.

It should be no less than the time period acknowledged on the bid form.

B.

The time period is thirty days for a private project and indefinitely for a public project.

C.

The time period should conform to requirements set by the Associated General Contractors of America.

D.

The time period as established by the contract for construction.

Buy Now
Questions 36

An architect/engineer (a/e) is reviewing a claim from a contractor asking for more money and time on the project. The a/e plans to reject this claim based on documentation supplied by the contractor indicating what reason?

Options:

A.

There was active interference by the owner.

B.

There were conditions beyond the control of the contractor or owner.

C.

The a/e modified the contract documents.

D.

There is defective work needing repair.

Buy Now
Exam Code: CDT
Exam Name: Construction Documents Technologist
Last Update: Nov 18, 2025
Questions: 120
$66  $164.99
$50  $124.99
$42  $104.99
buy now CDT