New Year Sale - Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 65percent

Welcome To DumpsPedia

CDT Sample Questions Answers

Questions 4

Which team member is actively involved and interested in all phases of the project?

Options:

A.

Contractors

B.

Owners

C.

Architects/engineers

D.

Manufacturers/suppliers

Buy Now
Questions 5

Which document directly modifies the requirements of the general conditions?

Options:

A.

Division 01, General Requirements

B.

Supplementary Conditions

C.

Agreement

D.

Instructions to Bidders

Buy Now
Questions 6

If the contractor discovers that a part of the contract documents is in violation of the building code, what should the contractor do?

Options:

A.

Notify the architect/engineer in writing

B.

Proceed with the work in accordance with the contract documents

C.

Request a variance from the building authority

D.

Stop all work until the issue is resolved

Buy Now
Questions 7

Under a single prime contract, shop drawings should be routed to the architect/engineer from whom?

Options:

A.

Contractor

B.

Material supplier

C.

Owner

D.

Subcontractor

Buy Now
Questions 8

For a large transportation project, 53 borings were made and only one boring showed some contamination. Due to financial constraints, the owner is unable to provide additional funding to the design team for further investigation. Which of the following is the best course of action for the design team?

Options:

A.

Withhold the information from the bid package because the full extent remains unknown. Ask bidders to provide a unit cost for remediation.

B.

Provide a disclaimer on the contract documents about potential contaminants onsite and suggest the owner make the geotechnical report available to all bidders.

C.

Insist the owner undertake additional investigation to determine the full extent prior to putting the project out for bid.

D.

Proceed with design as is without any modifications since the results are statistically insignificant (i.e., well within expected deviations).

Buy Now
Questions 9

What is a fundamental principle required to provide fairness in a competitive bidding process?

Options:

A.

Bid securities provide protection to all bidders for unfair practices of others.

B.

The bid shopping process provides the most beneficial pricing to the owner.

C.

All bids are prepared based on identical conditions, information, and time constraints.

D.

A minimum of three bids are required to assure sufficient competition.

Buy Now
Questions 10

Which of the following is NOT included in Divisions 02–49 of a project manual?

Options:

A.

General requirements

B.

Finishes

C.

Concrete

D.

Utilities

Buy Now
Questions 11

Where are the limits of the work of each alternate defined?

Options:

A.

Agreement

B.

Bid Form

C.

Division 01

D.

Sections in Divisions 02–49

Buy Now
Questions 12

When innovative or unusual design techniques are proposed, it is advised to have what type of review?

Options:

A.

Sustainability

B.

Budget

C.

Constructability

D.

Design

Buy Now
Questions 13

When preparing their bid, a contractor organizes their costs into different categories. The following items are examples of which type of cost?

    Permits and inspections

    Mobilization and startup

    Jobsite safety and security procedures, including personnel

    Administrative costs attributable to the work

Options:

A.

Construction

B.

Contingency

C.

Overhead

D.

Insurance

Buy Now
Questions 14

During the project closeout phase, what is an appropriate task for the facility manager?

Options:

A.

To ensure they have received the required spare parts, extra stock materials, and any necessary training needed in order to maintain the facility in the first year

B.

To coordinate with the architect a final clean-up and site restoration

C.

To hire a new security company to ensure maintenance and ground management

D.

To draft the final changes on the as-built documents

Buy Now
Questions 15

The general principle to which architects and engineers have a duty to clients and society at large to practice is defined as "taking the same course of action as another reasonable and prudent architect or engineer in the same geographic area would have taken under the same circumstances" is known by what term?

Options:

A.

Professional standard of care

B.

Due diligence

C.

Performance based requirement

D.

Spearin doctrine

Buy Now
Questions 16

What determines the responsibilities of the participants on the project team?

Options:

A.

Size of the project

B.

Nature of the project

C.

Cost of construction

D.

Project delivery type

Buy Now
Questions 17

Which party has the ultimate authority to approve a change order?

Options:

A.

Architect/engineer

B.

Contractor

C.

Owner

D.

Construction manager

Buy Now
Questions 18

Which of the following elements should be included in Supplementary Conditions?

Options:

A.

Requirements for a schedule of values

B.

Claims and dispute resolution requirements

C.

Equal employment opportunity requirements

D.

Termination of the work by owner or contractor

Buy Now
Questions 19

Where should the contractor maintain record documents?

Options:

A.

Contractor's office

B.

Contractor's office with a copy sent to the owner

C.

Owner's office

D.

The jobsite

Buy Now
Questions 20

Peer reviews or internal reviews of completed documents are examples of what?

Options:

A.

Quality control

B.

Commissioning

C.

Quality assurance

D.

Construction administration

Buy Now
Questions 21

Which of the following participants is involved in the Integrated Project Delivery (IPD) method?

Options:

A.

Authority having jurisdiction

B.

Commissioning agent

C.

Contractor

D.

Inspector

Buy Now
Questions 22

A drawing set arranged in the following order is an example of what type of drawing organization?

Cover Sheet, Sheet Index, Life Safety, Demolition, Civil, Landscaping, Architectural, Interiors, Structural, Mechanical, Electrical, Plumbing, Fire Protection

Options:

A.

Traditional drawing set organization

B.

Uniform Drawing System

C.

AIA CAD Layer Guidelines

D.

BIM Implementation

Buy Now
Questions 23

Modifications to the contract documents after execution of the owner–contractor agreement include which of the following?

Options:

A.

Change order, construction change directive, and field order

B.

Field order, construction change directive, and request for information

C.

Addendum, change order, and request for information

D.

Supplemental instructions, work change directive, and addendum

Buy Now
Questions 24

Which of the following statements best describes stakeholder and participant interest in a project?

Options:

A.

Participants have direct interest in the project while stakeholders have indirect interest

B.

Stakeholders have direct interest in the project while participants have indirect interest

C.

Both stakeholders and participants have direct interest in the project

D.

Both stakeholders and participants have indirect interest in the project

Buy Now
Questions 25

What is a primary disadvantage in using the design-bid-build method?

Options:

A.

It attracts too many bidders

B.

All of the bids may exceed the owner's budget

C.

It requires a higher level of bid document quality

D.

It reduces the owner's control over the project during the construction phase

Buy Now
Questions 26

Within the context of the construction industry, what does BIM stand for?

Options:

A.

Building Information Modeling

B.

Business Information Manual

C.

Building Interior Maintenance

D.

Building Inspection Manual

Buy Now
Questions 27

Which of the following is a format that standardizes the way text is arranged in specification pages so that it is best suited for easy reading and rapid reference?

Options:

A.

SectionFormat®

B.

PageFormat

C.

MasterFormat®

D.

UniFormat®

Buy Now
Questions 28

In what project stage does the architect/engineer obtain and document the owner's decisions about specific products and systems?

Options:

A.

Construction documentation

B.

Design

C.

Project conception

D.

Programming

Buy Now
Questions 29

Which bid form component ensures equal consideration, transparency, and flexibility while awarding a contract, but also manages cost during execution for undefined and unforeseen construction conditions?

Options:

A.

Bid security and substitution

B.

Add and deduct alternatives

C.

Allowances and unit prices

D.

Liquidated damages and combined bids

Buy Now
Questions 30

The owner's budget may not be adequate to pay for the entire project. What method is used to allow flexibility in the event that the budget is exceeded by the bids?

Options:

A.

Cash allowance

B.

Quantity allowance

C.

Unit pricing

D.

Alternates

Buy Now
Questions 31

Which of the following is a component of project design team coordination during the construction documents phase?

Options:

A.

Duplication of important information by each discipline

B.

Ensuring drawing note terminology is differentiated from specification terminology

C.

Requiring the owner to hire a third-party to write the Division 01 specifications independently

D.

Quality assurance tasks shared between design and consulting teams

Buy Now
Questions 32

Which of the following is a scaled view?

Options:

A.

Perspective

B.

Foundation plan

C.

Riser diagram

D.

Isometric

Buy Now
Questions 33

You are working on a project that is subject to regulatory reviews both at the city and at the state level. Both agencies have acknowledged receiving the construction documents. This project has already been awarded to a general contractor, and you are representing the owner who wants to start construction immediately. How would you advise the owner?

Options:

A.

Construction may begin immediately as long as a safety manager is present, and the contractor avoids all excavation work until after the permits are issued.

B.

Since the state approval is more critical than the city approval, construction may proceed immediately after the state permits are issued.

C.

Since the city approval is more critical than the state approval, construction may proceed immediately after the city permits are issued.

D.

Construction may begin only after both city and state permits have been issued.

Buy Now
Questions 34

The three types of commissioning include systems and equipment commissioning, building envelope commissioning, and what other process?

Options:

A.

Mechanical commissioning

B.

Facility commissioning

C.

Process commissioning

D.

Total project commissioning

Buy Now
Questions 35

To obtain progress payments, the contractor must submit an application for payment itemized in accordance with what?

Options:

A.

The construction schedule

B.

The subcontractor’s invoices

C.

The schedule of values

D.

The percentage of completion

Buy Now
Questions 36

What activity helps the owner assess the viability of a project, evaluate financial resources, and understand the project's potential impact on the community?

Options:

A.

Schematic programming

B.

Site selection

C.

Due diligence investigation

D.

Master planning

Buy Now
Exam Code: CDT
Exam Name: Construction Documents Technologist
Last Update: Jan 13, 2026
Questions: 120
$57.75  $164.99
$43.75  $124.99
$36.75  $104.99
buy now CDT