What is the name of the statistical method that helps identify which factors may influence specific variables of a product or process under development or in production?
Which type of chart is a graphic representation of a process showing the relationships among process steps?
Which process documents the business needs of a project and the new product, service, or other result that is intended to satisfy those requirements?
A change log for communications can be used to communicate to the appropriate stakeholders that there are changes:
What cost control technique is used to compare actual project performance to planned or expected performance?
Which component of the human resource management plan describes when and how project team members are acquired and how long they will be needed?
Identifying major deliverables, deciding if adequate cost estimates can be developed, and identifying tangible components of each deliverable are all part of which of the following?
Project or phase closure guidelines or requirements, historical information, and the lessons learned knowledge base are examples of which input to the Close Project or Phase process?
Which of the following consists of the detailed project scope statement and its associatedWBSand WBS dictionary?
Which process develops options and actions to enhance opportunities and reduce threats to project objectives?
What is the schedule performance index (SPI) if the planned value (PV) is $100, the actual cost (AC) is $150, and the earned value (EV) is $50?
Which input to the Manage Stakeholder Engagement process provides guidance on how stakeholders can best be involved in a project?
Which risk management strategy seeks to eliminate the uncertainty associated with a particular upside risk by ensuring that the opportunity is realized?
Which process identifies whether the needs of a project can best be met by acquiring products, services, or results outside of the organization?
Which process involves subdividing project deliverables and project work into smaller, more manageable portions?
A project manager is appointed full-time to a project and is given full-time administrative staff and full-time project team members. This situation describes which type of organizational structure?
A project manager should document the escalation path for unresolved project risks in the:
Which earned value management (EVM) metric is a measure of the cost efficiency of budgeted resources expressed as a ratio of earned value (EV) to actual cost (AC) and is considered a critical EVM metric?
An effective technique for resolving conflict that incorporates multiple viewpoints from differing perspectives to achieve consensus and commitment is:
Which process is responsible for monitoring the status of the project and product scope and managing changes to the scope baseline?
Which type of contract is a hybrid of both a cost-reimbursable and a fixed-price contract?
The process of identifying specific actions to be performed to produce project deliverables is:
The project budget is set at $150,000. The project duration is planned to be one year. At the completion of Week 16 of the project, the following information is collected: Actual cost = $50,000, Plan cost = $45,000, Earned value = $40,000. What is the cost performance index?
The application of knowledge, skills, tools, and techniques to project activities to meet project requirements describes management of which of the following?
Which type of dependency is contractually required or inherent in the nature of the work?
How should a stakeholder who is classified as high power and low interest be grouped in a power/interest grid during stakeholder analysis?
A project manager at a publishing company decides to initiate the editing phase of the project as soon as each chapter is written. Which type of Sequence Activities tool and technique is involved, considering that there was a start-to-start relationship with a 15-day delay?
Which type of analysis systemically gathers and analyzes qualitative and quantitative information to determine which interests should be taken into account throughout the project?
The most commonly used type of precedence relationship in the precedence diagramming method (PDM) is:
Which Process Group's purpose is to track, review, and regulate the progress and performance of the project; identify any areas in which changes to the plan are required; and initiate the corresponding changes?
The integrative nature of project management requires which Process Group to interact with the other Process Groups?
A work package has been scheduled to cost $1,000 to complete and was to be finished today. As of today, the actual expenditure is $1,200 and approximately half of the work has been completed. What is the cost variance?
If the most likely duration of an activity is five weeks, the best-case duration is two weeks, and the worst-case duration is 14 weeks, how many weeks is the expected duration of the activity?
Which process involves the creation of a document that provides the project manager with the authority to apply resources to a project?
A risk that arises as a direct result of implementing a risk response is called a:
Project deliverables that have been completed and checked for correctness through the Control Quality process are known as:
The following is a network diagram for a project.
The total float for the project is how many days?
The process of monitoring the status of the project and product scope as well as managing the changes to the scope baseline is known as:
Which output of Project Cost Management consists of quantitative assessments of the probable costs required to complete project work?
Which of the Perform Quality Assurance tools and techniques may enhance the creation of the work breakdown structure (VVBS) to give structure to the decomposition of the scope?
A project team attempts to produce a deliverable and finds that they have neither the expertise nor the time to complete the deliverable in a timely manner. This issue could have been avoided if they had created and followed a:
The following is a network diagram for a project.
The free float for Activity H is how many days?
Funding limit reconciliation is a tool and technique of which Project Cost Management process?
Which basic quality tool explains a change in the dependent variable in relationship to a change observed in the corresponding independent variable?
The project manager needs to review the templates in use. The templates are part of the:
What is the responsibility of the project manager and the functional manager respectively?
Control charts, flowcharting, histograms, Pareto charts, and scatter diagrams are tools and techniques of which process?
Who provides the inputs for the original estimates of activity durations for tasks on the project plan?
Which of the following tools and techniques is used in the Verify Scope process?
A given schedule activity is most likely to last four weeks. In a best-case scenario, the schedule activity is estimated to last two weeks. In a worst-case scenario, the schedule activity is estimated to last 12 weeks. Given these three estimates, what is the expected duration of the activity?
What is a deliverable-oriented, hierarchical decomposition of the work to be executed to accomplish the project objectives and create the required deliverables?
Which of the following terms indicates a deliverable-oriented hierarchical decomposition of the project work?
Which of the following is an output of the Perform Integrated Change Control process?
Which type of estimating is used to improve the accuracy of an activity's duration?
Prioritizing risks for further analysis or action by assessing and combining their probability of occurrence and impact takes place in which process?