ASD01 Sample Questions Answers

Questions 4

A process definition document has been produced for a process that interfaces with two applications: FirstApp and Customer Information (CI). The process requirement is to perform data extractionfrom FirstApp before performing a number of steps in the CI application.

It is estimated that to perform the daily case volume within SLA’s will require 10 robots. Average case time is approximately 10 minutes, with the FirstApp steps requiring only 1 minute to perform.

The client has a limited number of licenses for the FirstApp application and is reluctant to use 10 of these licenses to automate the process.

Which of the below is a valid design option for the project?

Options:

A.

Automate the end to end processusing two Blue Prism processes. Process 1 will perform the FirstApp tasks, Process 2 will perform the CI tasks. Data will be passed from Process 1 to Process 2 via a Blue Prism Work Queue. Process 1 will run on a single robot, with Process 2 running on 9robots.

B.

Automate the end to end process using two Blue Prism processes. Process 1 will perform the FirstApp tasks, Process 2 will perform the CI tasks. Data will be passed from Process 1 to Process 2 via a spreadsheet. Process 1 will run on a single robot, with Process 2 running on 9 robots.

C.

Automate the end to end process using single Blue Prism process which will only be run on a single robot.

D.

Automate the end to end process using single Blue Prism process which will be run on 10 robots.

Buy Now
Questions 5

The following Object Design has been created for a mainframe banking application.

Which of the following statements about the Object design above are correct? (Choose two.)

Options:

A.

The Add Note action in the “BankHost – Notepad” business object does not require an input for Type as the process definition document states that ‘Information’ will always be selected for this process.

B.

The object design facilitates a scalable design that will reduce the impact of change when the object layer needs altering.

C.

The object design should be simplified by storing all BankHost actions in the same object.

D.

There is no need for attach actions to be replicated across all the objects.

E.

The design complies with Blue Prism design best practice.

Buy Now
Questions 6

A process is required for a client in the banking sector that involves using an application to transfer funds between accounts. A strong security model is in place to prevent any malicious activity but the client is nervous about the risk of external problems, like a power cut leaving a case in an incomplete state or a fault in thesource data causing a case to be duplicated or an excessively large transfer to be made.

What should be included in the solution design? (Choose three.)

Options:

A.

A different queue for each major processing step.

B.

A different process for each majorprocessing step.

C.

A single queue that is cleared of all worked items at the start of each day.

D.

Rules to limit transaction values.

E.

A key value that will uniquely identify queue items.

F.

A requirement that the solution is never run on more than onemachine.

G.

An exception handling procedure to track manual referrals.

Buy Now
Questions 7

The status of a Work Queue can be used as a method of recording that work has been done so far on a Work Queue item.

Please consider the following statements:

1. For MI, to easily see how far an item has beenworked.

2. To aid manual working of exceptions, providing the Item Status can inform staff what work is still outstanding on an item that needs manually.

3. To enable Work Queue items to be safely retried, a process can use the item status to know which updates have already been performed so that they are not repeated.

4. To record the Customer’s Surname

Options:

A.

2 only

B.

2 and 3 only

C.

1, 2 and 3 only

D.

1, 2, 3 and 4

Buy Now
Questions 8

When designing business objects which of the following statements is true? (Choose three.)

Options:

A.

It’s best practice to keep application logic in onebusiness object so that there is a single point of reference.

B.

It’s good practice to split application logic into multiple objects so that the process is more efficient.

C.

It’s good practice to keep application logic in one business object so that developers know where to find.

D.

It’s good practice to keep application logic in one business object to minimize the process dependencies.

E.

It’s a good practice to split application logic into multiple objects to minimize the process dependencies.

F.

It’s agood practice to split application logic into multiple objects to minimize the effect of change.

G.

It’s a good practice to keep application logic in one business object so that the process is more efficient.

Buy Now
Exam Code: ASD01
Exam Name: Designing Blue Prism Process Solutions
Last Update: May 2, 2024
Questions: 27
$64  $159.99
$48  $119.99
$40  $99.99