The building requires sprinklers and is equipped with a wet-pipe system. What action should you recommend for the computer room?
The humidity in the computer room has increased from about 60% up to 85% Relative Humidity (RH). What potential risk does this pose to your equipment?
You want to make cooling more effective by setting cold aisle temperature to 4 °C (39 °F). Is this acceptable?
You want to manage temperature and humidity only at the facility level in your data center. All servers use front-to-rear airflow. Which location for measurement should you recommend?
An MCB needs to be installed in the PDU of an ICT rack. Which breaking curve should you select?
A data center is in an area where utility power is highly available—only a few outages per year, typically <1 hour per event and <50 hours/year not available. What type of generators should be installed?
ICT rack consumes 3 kW with ΔT ~11 °C (20 °F). Calculate required airflow (CFM).
The 'maximum exposed area' of the fire-rated glass is defined by the supplier as 3 sqm/32 sqft. The window area is 4 sqm/43 sqft.
What would be the best option?
What should you consider when using raised floor tiles with air deflectors or louvers?
The noise levels in the data center are approximately 91 dB (A).
Do employers need to take precautions?
Given: A = attenuation in dB, R = real measured value, M = maximum acceptable value. Which formula should be used to calculate the required attenuation factor of EMF shielding material?
You need to determine the strategy for the cooling audit. All the servers are based on a front-to-rear (F-R) airflow design.
Which location for the temperature/humidity measurement should you recommend for the audit?
You are working with a customer who requires a guarantee that THDi levels coming from the UPS should not exceed more than 3% THDi. Furthermore, he wants to run a power-efficient data center. The UPS has a 6-Pulse SCR/Thyristor based rectifier. The current load on the UPS is approximately 80%. The customer indicates they are not expecting any changes on the ICT infrastructure for the next 3 years.
What should you recommend?
The computer room has high levels of H2S gas contamination. What is the best option to resolve this issue?
What precaution shall be taken for cabling leading into an equipment rack when a data center is in a seismic-prone area?
FM-200 is phasing out as a halocarbon gas and management has decided to replace this with the more environmentally friendly Novec-1230 gas. Should you use exactly the same formula and parameters to calculate the gas content for the Novec-1230 gas?
What is the risk of high levels of hydrogen sulfide (H₂S) in the computer room?
You are allowed to use a calculator for this question. The total power consumption of the ICT equipment in a rack is 6 kW. The equipment is traditional ICT equipment with a Delta-T of approximately 11 °C / 20 °F. Calculate the approximate CFM required to cool the equipment in the rack.
You have three UPS systems connected in parallel. The UPS systems have an imbalance in the load sharing of approximately 20%.
What should you recommend?
A 5kW (power consumption) server keeps crashing with the message 'temperature too high'.
The intake temperature is measured at 25 °C/77 °F and a relative humidity (RH) level of 50%.
The exhaust temperature is 29 °C/84 °F and 45% RH.
The raised floor is providing an adequate amount of CFM/CMH at a reasonable velocity.
The pressure under the raised floor is approximately 25 Pa/0.1 inch H₂O.
Analyze the situation and indicate what the most likely cause is for this server to crash.
In which stage of the data center life cycle does testing and commissioning take place?
The building in which the computer room is housed is required to have a sprinkler system. The building is therefore equipped with a wet pipe system.
What action, if any, should you recommend for the computer room?
A battery bank has 800 Ah total capacity. How much charging current should the rectifier be able to supply?
The location of a data center is just above the Arctic Circle (North Pole). The outside air temperature is never above 21°C/70°F.
Taking energy efficiency as the highest priority, which cooling system should you recommend?
A new facility requires electrical distribution of 100A to be installed in the computer room, 1 m (3 ft) above sensitive IT equipment. What type of system minimizes EMF impact?
The data center has been in operation for about 1 year and 2 months. The dust levels in the computer room are relatively high.
What is the most likely root cause?
What is the effect of having a damper (in open position) construction in a raised-floor tile?
An air-conditioner unit needs to be selected. Two types are available:
Unit-A has a Sensible Heat Ratio (SHR) of 0.7.
Unit-B has a Sensible Heat Ratio (SHR) of 0.9.
From an efficiency point of view, which one should be selected?