In order to monitor supplier’s performance, an organization decides to draft performance management frameworks. Which of the following are the components of a performance management framework? Select THREE that apply:
Which of the following is the contract provision that relieves the parties from performing their contractual obligations when certain circumstances like natural disasters, terrorist attacks, etc arise?
In the application of price adjustment formulae, which of the following would be acceptable for a supplier to increase its selling price?
Which of the following are always considered as minimum preconditions for a contract? Select TWO that apply:
Since services are intangible, so KPIs for services must be qualitative in all circumstances. Is this statement correct?
Maximum Score 1
Buyer O has placed an order for the supply and installation of six new servers for a total amount of £600,000 from Supplier A. Which of the following could potentially be treated as examples of a liquidated damages clause within the contract for the supply of the servers?
If the supplier delivers any of the servers late, £1,000 per server will be deducted from the order per day
This contract is subject to delay remedies of £X - the amount to be agreed by both parties during delivery
The sum for breach of the completion date for the order is £40,000 per day up to a maximum of 50% of the contract price
If the performance of any of the servers degrades within five years, a full refund of £600,000 will be provided
What are disadvantages of a buyer contracting on the supplier's terms? Select TWO that apply.
In which of the following conditions, request for quotation produces the best results?
Various terms are used to qualify a party's obligations under contract. Which of the following gives absolute obligation?
A retailer prefers to display its best selling products and promotion programme on the building windows. According to rule of contract formation, this act will generally constitute...?
Maximum Score: 1
A service contract for cleaning is due for expiry after a five year duration. Which of the following are good sources of data to create a specification for the new invitation to tender?
Incumbent supplier
Maintenance services
Alternative suppliers
Management information
Under a framework agreement, which of the following are supplier selection mechanisms? Select TWO that apply:
A procurement manager is preparing a long-term contract with a major supplier. She decides to use the variable pricing arrangement using price indices. The payment terms describe the circumstances and mechanism where the price is allowed to change. In order to successfully manage this type of contract, the buying organisation should have...?
CMS Corp goes into a gainshare agreement with the contractor, EIP Ltd. Both parties agree that the final fee will be calculated on target cost - target fee basis. Which of the following will affect the final fee payable in this gainshare agreement? Select TWO that apply:
Maximum Score 1
The Bravo Engineering Company is negotiating a maintenance contract with Express Deliveries Ltd. This large logistics company uses modern robotic storage and picking warehouse machinery to identify, sort, and facilitate over 200,000 orders each day. The volatile nature of the business means that the parties should build maximum flexibility into the performance management aspects of the contract.
Which of the following would be most appropriate to set out the parties’ obligations under the maintenance contract?
Which of the following regulates barriers to the trade of goods between Member States of WTO?
Maximum Score 1
A construction company wishes to place the contract for the building of a new hotel to a principal contractor using a model form contract. Which of these is an advantage of using a ‘model form contract’?
A Key Performance Indicator (KPI) states "Measure the effort exerted by the project team to control costs throughout the contract duration.” Is this KPI appropriate for measuring the management of contract costs?
Which of the following is the procedure that makes no further competition under a framework agreement?
Which of the following should be applied when measuring frequency of on-time deliveries during a contract period?
Solus Trading has begun a project to improve the level of delivery performance from its suppliers. They need to develop a key performance indicator (KPI) to measure the performance improvement. Which KPI would be suitable to use?
A buyer and a supplier plan to sign a contract with cost-plus arrangement. If the cost base is $350 and the markup component is 11% then the invoice price will be...
A tire manufacturer entered into a contract with a distributor. In the contract, the distributor is prohibited from selling the tire under the price list. The distributor must pay $5 for each tire sold in breach. The amount of $5 is known as...?
Which of the following will always give rise to a claim of misrepresentation?
1. Silence
2. False thought
3. Statement of fact
4. Representation by conduct
Cleveland Insurance (Cleveland) offers a range of insurance services. The main software used in the call centre is a customer relationship management (CRM) system. Cleveland perceived an urgent need to replace the existing CRM system to deal with the increasing number of customers and services.
Urgent Digital Ltd (Digital) is one of the bidders of Cleveland’s ITT for designing, building and managing the new CRM system. Its bid team is led by Hank Irvine, its technical director. Hank realises that winning the Cleveland contract (valued at approximately £50M) will enhance his career. During discussions with Cleveland, Hank offers certain assurances regarding timescales for the project. He has not carried out any investigations into the viability of the timescales. Hank has little idea whether the timescales can be met.
Cleveland decides that Digital’s bid meets with its requirements, especially given the assurances in timescale offered by Hank, and decides to proceed with it, subject to a formal contract. Eventually, a formal contract is signed by both parties. The initial assurances given by Hank about the timing of the project are never going to be achieved and are at best grossly exaggerated.
Cleveland brought the case to the court and sought rescission of contract with Digital. Is Cleveland’s claim appropriate in this case?
Which of the following is the model form of contract for construction which is recommended by World Bank?
In which scenarios would it be appropriate for a procurement organisation to include contractual indexation and/or price adjustment formulae clauses in a services contract? Select TWO that apply.
A category buyer is purchasing medical gases for a hospital, but is experiencing volatile and unfavourable market conditions due to multiple global external factors. Owing to the volatility, the hospital's finance director has tasked the buyer with providing certainty of costs for the next 18 months. Which of the following pricing methods will enable budgeting certainty, despite the highly volatile market conditions?
Maximum Score 1
When a company has decided to outsource part of its operation, the contract will need to include a number of key contract terms to minimise risk. Which of the following should be included?
A confidentiality clause designed to protect either party
A clause stating how long the service is to be outsourced
A clause stating how long the employees can take for holiday
A contract variation and price adjustment clause
Ellie is a junior buyer and her supplier asks her to use their contract terms for an order. Which of the following are clauses that may be included in the supplier contract that could pose a risk to Ellie's business? Select TWO that apply.
Which of the following should be done by procurement professionals right after obtaining a pre-written specification for a critical item so that the added value will be the greatest?
Maximum Score 1
A purchase order has been raised for £5,000. It allows the user department to order items of a £50 value when they need them. This is an example of what type of order?
Buyer D agrees a contract with Supplier C which includes the words 'to be agreed' in relation to the date for delivery of the goods. At the time of the contract, Buyer D is aware that the goods take two days to produce and one day to deliver. Buyer D contacts the supplier one week later, requesting the goods be delivered the following day. Supplier C is unable to deliver the next day but rather delivers the goods three days later. Is it the case that Buyer D can legally refuse to pay for the goods because Supplier C is in breach of contract?
Which of the following is a benefit to the buyer of using model form contracts?
Maximum Score 1
A service contract for cleaning is due for expiry after a five-year duration. Which of the following are good sources of data to create a specification for the new invitation to tender?
Incumbent supplier
Maintenance services
Alternative suppliers
Management information
Which of the following are likely to be implied terms in a contract? Select TWO that apply:
Which of the following is used to detail the complex matter that may be verbiage to the main document?
The nature of the "Battle of the forms" is when both buyer and supplier are attempting to ...
Which of the following is the reason why liquidated damage clauses are embedded into a contract?
Which of the following are most likely to be liabilities of suppliers under a guarantee clause?(SelectAny Two)
When writing an implementation section for an IT requirements specification, which factors would be appropriate for inclusion? Select TWO that apply.
Parkers Medical Supplies is a distributor of first aid supplies to supermarkets nationwide. A new supplier has approached Parkers with an offer to supply a new and innovative product. Parkers have never dealt with this company before, so are looking to ensure that the new supplier has the necessary insurance cover as the new product could potentially cause personal injury. Which type of insurance should Parkers insist the new supplier takes out?
Maximum Score: 1
Which of the following are examples of a lack of 'capacity' to enter into a contract?
A contracting party has a severe mental disorder
A contracting party has failed to concentrate during negotiations
A contracting party is 19 years of age
A contracting party (corporation) has acting 'ultra vires' (beyond its defined legal powers)
Maria is working on a new one-off construction project and is looking to expand a factory. A requisition comes through for an outright purchase of a digger. Maria changes this to a lease order instead. Is she right to do so?
Which of the following are express terms?
Sale by description
Fitness for purpose
Passing of risk
Passing of title
Key performance indicators (KPIs) are used to measure supplier performance. Which of the following are KPIs that may be used? Select THREE that apply.
In order to reduce the internal cost of administration from the raising of high-volume, low-value orders such as office stationery, a procurement manager implements the use of call-off orders for such circumstances. Is this an acceptable thing to do?
A construction company is undertaking a housing development project. They need lots of bricks and other building materials, but the construction site doesn't have large area for storage of materials.Therefore, the company's suppliers must deliver the building materials with fixed quantity and at fixed time intervals. What type of contract is used between the construction company and its suppliers?
Standard terms and conditions should become the governing terms for which group of items?
Foodstuffs may arrive from an overseas supplier in a deteriorated state. Is this covered under the implied term of 'satisfactory quality'?
Which of the following sections would typically be included in a specification for services? Select THREE that apply.
Which of the following should be specially noticed in market dialogue with suppliers in specification development?
SFO procurement manager sent a request for quotation to Vogon International in which he determined the contract terms and specification. In SFO's standard terms and conditions, it is stated that 'Goods shall be delivered and Services performed by the applicable Delivery Date. Supplier must notify Buyer 3 days prior to the Delivery Date if Supplier is likely to be unable to meet a Delivery Date.'
Vogon replied with a quotation without any amendment to SFO's terms & conditions. The SFO procurement manager found the prices were reasonable and submitted to senior management. Senior management team accepted that quotation and sent a notification to Vogon. On the Delivery Date, Vogon said they had no capacity to supply the product as the quotation due to a workers' strike. Did Vogon breach any agreement with SFO?
ABC Ltd is a UK based company. It plans to enter into a contract with XYZ Ltd which is based in Singapore. Which of the following are the mandatory elements for the contract between ABC Ltd and XYZ Ltd to be legally binding? Select THREE that apply.
Which of the following are most likely to be substantive elements of the specification of a truck? Select TWO that apply:
Which of the following would be considered as advantages of an industry model form contract?
It provides greater flexibility for negotiation
It reduces the cost of contract development
It is usually designed to be fair to both parties
It removes the need for the buyer to understand it
Which of the following would you expect to see in an Invitation to Tender (ITT)?
Maximum Score 1
Adornical Toys Ltd have recently declared their commitment to international labour standards. Karim is sourcing a supplier for a new range of wooden toys and is keen to ensure that the organisation's corporate objectives are met. Which of the following approaches could he include as part of his specification requirements to achieve this labour outcome?
A procurement manager is setting KPIs measurement for user satisfaction. He also wants to encourage users to share the reason why they feel the way they do. Which of the following types of KPI should the procurement manager apply?