The programme is in the ‘design the outcomes’ process. One risk to the programme is that new and improved meter technology may be developed during implementation. This risk has been assessed as high probability and high impact and is therefore a high priority. The initial delivery approach proposes a phased roll-out of the meters so that the programme can exploit any new technology that emerges. The CTO has been appointed as the owner of this risk.
Is this appointment an appropriate application of the identify and prioritize risks’ activity, and why?
The CFO has been appointed as the SRO for the Smart Meter Programme.
Is this appointment an appropriate application of the ‘organization’ theme, and why?
The task of organizational realignment relies heavily on getting results from existing staff and enhancing skills. Here are items of information to be recorded in the stakeholder engagement and communications plan. Under which heading should they be recorded?

Through which document programmes establish the context in which risks will be identified and assessed and responses planned and implemented?
In which document would you expect to find the levels of confidentiality to be applied in the programme?
At the start of the programme, the programme manager listed some design-related actions to be completed. Which role is MOST focused on each task?

At the end of Tranche 2, the programme office lead reported that the overall programme cost would exceed the current budget. The SRO has recommended to the sponsoring group that the programme budget be increased, to enable the programme to deliver the full target operating model, as originally planned.
Which theme is being applied to the ‘evaluate new information' process?
When approval to proceed is given at the end of Defining a Programme, what does this mean?
The programme is in the 'identify the programme' process. The CEngO is concerned that the engineering department will not be able to deliver the proposed Engineering Department Work at the same time as supporting the research into new smart meters and water leak detection equipment. The programme board believes that the engineering department will be able to manage, if the programme is planned optimally.
Which role is MOST LIKELY to approve the programme board's recommendation?
The programme is in Tranche 2 and has been progressing according to plan. However, there have been difficulties transitioning to the new ways of working at the end of Tranche 1 and UU has had some customer complaints as a result. Therefore, the SRO asked the programme manager to replan the programme so that all remaining capabilities are transitioned at the end of the programme, instead of at the end of the tranche.
Is this an appropriate application of the 'structure' theme, and why?
The programme is starting Tranche 1 and there is a lot of dissatisfaction in the workforce about the planned merging of the engineering roles. The programme board has made some proposals on how to deal with this issue but is unsure whether to involve the sponsoring group.
According to the ‘decisions’ theme, which document should be consulted to clarify whether it is necessary to escalate this issue to the sponsoring group?
Which of the following is Not one of MSP defined levels of stakeholder engagement?
The project team working on the Training Project in Tranche 3 needs to understand the new processes and knowledge required by staff members to develop a coherent set of training materials. The project team also needs to know the skills and qualifications for each role, and any new processes. The project manager is concerned that some of the documentation provided is outdated and does not now reflect the current processes being developed.
Which aspect of information management, if applied correctly, is MOST LIKELY to address these concerns?
Three pieces of information should be documented in the information approach section of the programme strategy. In which section should this information be documented?

For a business transformation programme, which of scenarios will lead to high probability of success?
The programme is in the middle of Tranche 2 and a new SRO has been appointed. In order to understand the current status of the programme, the SRO has asked for a health check to be carried out. The health check was not in the assurance plan, and there is no budget available to pay for an external auditor. As a result, the programme manager has agreed with the SRO that a senior member of the portfolio office, who is acting as the programme office lead, should complete the health check instead.
How well does this action by the programme manager apply the ‘assurance' theme, and why?
Significant changes to the customer processes have been delivered and Tranche 2 is now complete. Many engineering staff do not believe that the Training Project is needed in Tranche 3 as they feel the changes to the new customer processes are minor. The programme manager is concerned that the engineering staff may have misunderstood the extent of the changes. As a result, the programme manager noted in the end-of-tranche report for Tranche 2, that there needs to be more engagement with engineering staff during subsequent tranches.
Is this recommendation an appropriate application of the 'evaluate new information' process, and why?
Which of the following is NOT normally a characteristic of the Vision Statement?
The Smart Meter Programme is in Tranche 2 and the Customer Processes Project is delivering ahead of schedule. This means that fewer resources are required to complete the project. The Training Project, which was due to start in Tranche 3, has now become a higher priority and needs to be started early. The programme manager has recommended starting the Training Project now although Tranche 2 and Tranche 3 will then overlap.
Is this an appropriate application of the structure' theme, and why?