PK0-005 Sample Questions Answers

Questions 4

For an upcoming project kickoff. a PM is looking for a way to illustrate roles for major project activities. Which of the following would be the MOST useful option?

Options:

A.

Resource plan

B.

Organizational chart

C.

Project charter

D.

RACI chart

Buy Now
Questions 5

A project manager does not have the power to reward team members when they accomplish something or penalize them when they fail to perform well. As a result, the project manager is having issues with team members. Which of the following describes this organizational structure?

Options:

A.

Flat

B.

Projectized

C.

Weak matrix

D.

Functional

Buy Now
Questions 6

A project manager has decided to outsource portions of a project and will conduct a separate procurement. In which of the following phases does this task occur?

Options:

A.

Planning

B.

Initiating

C.

Controlling

D.

Executing

Buy Now
Questions 7

A few weeks before a project is scheduled to be completed, the client asks to add a new feature to the product that is being developed. The project manager analyzes the project schedule and determines the feature can be implemented quite easily without affecting the completion date. Which of the following should the project manager do first?

Options:

A.

Escalate the change to the CCB.

B.

Review the requested change.

C.

Document the change recommendations.

D.

Validate the implementation of the requested change.

Buy Now
Questions 8

Which of the following is a disadvantage of a cloud model?

Options:

A.

Limited processing and storage capacity

B.

Limited expansion capability

C.

Longer latency time

D.

Higher dependency on the vendor

Buy Now
Questions 9

A global shipping slowdown is causing critical raw materials needed for manufacturing to be delivered late. As a result, a project's production run will be delayed from the beginning.

Which of the following dependencies is most likely happening?

Options:

A.

Finish-to-start

B.

Start-to-start

C.

Finish-to-finish

D.

Start-to-finish

Buy Now
Questions 10

A project manager is reviewing a signed legal document pertaining to the hiring of a vendor who will develop an experimental solution. The vendor could not provide accurate estimates at this time because the requirements will probably be changing. The document also contains information about the resources involved and the rates the vendor will charge for the work. Which of the following best describes the legal document the project manager is reviewing?

Options:

A.

Time and materials contract

B.

Master service agreement

C.

Fixed-price contract

D.

Non-disclosure agreement

Buy Now
Questions 11

A project manager is currently meeting with a vendor who completed the project work. All invoices associated with the project have been paid. Which of the following best describes the project manager's objective for the vendor meeting?

Options:

A.

Reassigning resources

B.

Removing access

C.

Closing contracts

D.

Evaluating the project

Buy Now
Questions 12

A procurement team analyzes solutions submitted from multiple vendors for the upcoming release of a required development service. The procurement team identifies a potential partnership. Which of the following would the procurement team most likely request?

Options:

A.

Quote

B.

Information

C.

Proposal

D.

Bid

Buy Now
Questions 13

Which of the following best represents an intellectual property breach?

Options:

A.

Internal developers use code from a legacy in-house system to develop a new solution for the marketing department.

B.

The price list to end customers was stored on a stolen external hard drive.

C.

A service provider that worked on a project uses the developed software on a project for a new customer.

D.

Customer data is stored on a shared network drive that is accessible by employees from all departments.

Buy Now
Questions 14

Which of the following aspects are true of waterfall as compared to agile? (Select two).

Options:

A.

Waterfall is composed of smaller teams working together

B.

Waterfall reinforces customer collaboration

C.

In waterfall, solution validation occurs later in the development cycle.

D.

In waterfall, working software is more of a focus than comprehensive documentation.

E.

Waterfall is less tolerant to changes in scope.

F.

Waterfall is made up of sprints

Buy Now
Questions 15

Which of the following should be considered first when determining the privacy management for project data?

Options:

A.

Evaluating the current privacy protection program

B.

Understanding applicable privacy regulations

C.

Maintaining awareness of industry best practices

D.

Implementing security role-based controls

Buy Now
Questions 16

A team found a deficiency in an application and is proposing improvements, but the sponsor requests a business case. Which of the following best describes the intended objective of the business case?

Options:

A.

To identify the potential risk and issues for the project

B.

To determine the timeline and budget of the project

C.

To define the specific tasks required to create the project

D.

To specify what problem is being solved by the project

Buy Now
Questions 17

A team member needs to make an emergency update. The team member is unable to return to the office. Which of the following is the most secure way to make the update?

Options:

A.

At home, using home internet and the company’s computer

B.

At a coffee shop, using free Wi-Fi and the corporate computer

C.

At home, using home internet and the corporate virtual private network

D.

Anywhere the team member would like, using a mobile device and mobile internet

Buy Now
Questions 18

Which of the following concepts represents multiple resources interfaced to run reports?

Options:

A.

Code repository

B.

Data warehouse

C.

Storage server

D.

File-sharing system

Buy Now
Questions 19

Functional managers are reluctant to provide a project manager with resources for a project because they think the project should include a certain scope. The project manager reviews the project documentation and confirms the items the functional managers wanted to include were out of scope. Which of the following would be the best course of action for the project manager to take?

Options:

A.

Satisfy the functional managers by agreeing with their point of view in order to get the necessary resources.

B.

Advise the functional managers to submit a change request, record the issue in the issue log. and escalate the issue to the project sponsor

C.

Schedule a team meeting to discuss creative ways to incorporate the scope without having to formally submit a scope change request.

D.

Inform the functional managers that the project will produce only what has been approved and project modifications cannot be made at this point.

Buy Now
Questions 20

A project sponsor is struggling to provide the latest project status information on a weekly executive call. Which of the following should be reviewed?

Options:

A.

Meeting cadence

B.

Gap analysis

C.

Dashboard

D.

Adoption training

Buy Now
Questions 21

A member keeps bringing up unrelated topics during a team meeting. Which of the following should the protect manager do to keep the discussion on track?

Options:

A.

Remind the team member about the meeting agenda and invite the member to add the topic to the next meeting's agenda.

B.

Ask the team member to leave the meeting and create a new meeting to discuss these topics.

C.

Adjust the current meeting's agenda to accommodate the team member's topics.

D.

Allow the team member to bring up the topics, which could lead to important discussions and insights.

Buy Now
Questions 22

A project manager needs to pull data from a burndown chart. Which of the following should the project manager analyze to obtain this data in the most efficient way?

Options:

A.

Number of people available

B.

Remaining and completed tasks

C.

Cost variance

D.

Number of issues registered

Buy Now
Questions 23

Which of the following BEST illustrates how team members with different roles should interact on the team?

Options:

A.

SOW

B.

WBS

C.

RACI

D.

PERT

Buy Now
Questions 24

A critical business initiative introduced new processes and technology to the organization. Which of the following approaches should be used to ensure the deliverables are increasingly adopted and leveraged by the organization over time?

Options:

A.

Creation of a social news forum

B.

Management directives to use the new system

C.

New user kickoff meeting

D.

Monthly feedback and training sessions

Buy Now
Questions 25

A project team wants to compare two potential vendors' costs and risks for completing project tasks. Which of the following visualizations will best facilitate this analysis?

Options:

A.

Scatter diagram

B.

Decision tree

C.

Pareto chart

D.

Histogram

Buy Now
Questions 26

A system was implemented, and testing was successfully completed. Which of the following should the project manager do NEXT?

Options:

A.

Validate against the scope statement and ask for sign-off.

B.

Run a control chart to ensure the quality of the deliverables.

C.

Review the risk register and close up residual risks.

D.

Start the training and handoff for the operations team.

Buy Now
Questions 27

A company wants to move its data from on premises to off premises. Which of the following cloud models should be pursued?

Options:

A.

XaaS

B.

SaaS

C.

PaaS

D.

laaS

Buy Now
Questions 28

Which of the following provides a layered approach to logging in to systems that contain an organization's most valuable intellectual property?

Options:

A.

Remote access

B.

Password protection

C.

Multifactor authentication

D.

Virtual private network

Buy Now
Questions 29

Which of the following best describes the difference between the current state and the desired future state in project management?

Options:

A.

The current state is a high-level view of the project scope, and the desired state is what is happening right now.

B.

The current state is where the business is now, and the desired state is where the project is going to take the business.

C.

The current state is a high-level view of the project scope, and the desired future state is the specific outcome the business wants.

D.

The current state defines the specific outcome the business wants, and the desired state documents what is happening now that prevents it.

Buy Now
Questions 30

A project manager is unclear about the budget and timeline prior to the start of a project. Which of the following best describes what type of meeting needs to take place?

Options:

A.

Kickoff

B.

Demo

C.

Stand-up

D.

Status call

Buy Now
Questions 31

Given the following chart showing committed work (orange) vs. actual work completed (blue) across 10 sprints:

Which of the following best describes the team's performance?

Options:

A.

The team needs to adjust the planned work based on results.

B.

The team’s velocity is getting better.

C.

The team understands its velocity and is planning in an accurate manner.

D.

The team is doing more work than planned.

Buy Now
Questions 32

During the project initiation phase, a project manager needs to construct a project schedule and show the project dependencies. Which of the following should the project manager use for this task?

Options:

A.

Waterfall method

B.

Simulation method

C.

Precedence diagramming method

D.

Cost ratio analysis

Buy Now
Questions 33

Project team members enter their time sheets into a system that also displays incurred project cost. Which of the following systems can perform this task?

Options:

A.

EDRMS

B.

CRM

C.

CMS

D.

ERP

Buy Now
Questions 34

A PM wants to provide a visual representation of how a project is organized into tasks and how the tasks relate to each other. Which of the following can the PM use?

Options:

A.

Milestone chart

B.

Gantt chart

C.

PERT chart

D.

WBS

Buy Now
Questions 35

A project sponsor would like to develop a minimum viable product, but the requirements are not well defined. Which of the following should the project sponsor use?

Options:

A.

Rational Unified Process

B.

Waterfall

C.

Agile

D.

DevOps

Buy Now
Questions 36

The project manager must create a project charter. Which of the following should be included in the charter?

Options:

A.

Project schedule

B.

Resource allocation

C.

Risk plan

D.

Stakeholder identification

Buy Now
Questions 37

Which of the following pieces of data are examples of Pll?

Options:

A.

Medical record and test result values

B.

IP address and email address

C.

Name and year of birth

D.

X-ray and blood type

Buy Now
Questions 38

As a result of an internal assessment, the steering committee states that the company does not currently have the required skill set or technical tools to develop a particular feature in the project. Which of the following procurement methods would help the company?

Options:

A.

Subscription

B.

Subcontract

C.

Lease

D.

Build

Buy Now
Questions 39

A project team member recalls a specific chat with another member that contained key information related to a previous project, which no one else on the project team is aware of. Which of the following best describes what was needed to address this concern?

Options:

A.

Integrity

B.

Security

C.

Archival

D.

Lessons learned

Buy Now
Questions 40

A project manager is monitoring team performance by comparing committed versus completed work. The project manager creates the following:

Which of the following most likely represents the number of items in the backlog?

Options:

A.

23

B.

5

C.

10

D.

15

Buy Now
Questions 41

Which of the following is a quality assurance tool?

Options:

A.

Defining project goals

B.

Identifying the root cause analysis

C.

Assessing employee efficiency

D.

Assessing skill gaps

Buy Now
Questions 42

A project manager is conducting an evaluation of a product to determine whether it is meeting the requirements. The manager needs to compare the current status of the product with its optimal future status and determine what, if anything, needs to be done to improve it. Which of the following types of evaluations would be best for the manager to use?

Options:

A.

Gap analysis

B.

External status report

C.

Cost-benefit analysis

D.

Project closeout report

Buy Now
Questions 43

Which of the following is a capital expense?

Options:

A.

Building lease

B.

Building purchase

C.

Building maintenance

D.

Building insurance

Buy Now
Questions 44

A company purchases new software. The project manager needs to present the new software’s features to the stakeholders. Which of the following meeting types should the project manager and stakeholders have?

Options:

A.

Status

B.

Focus

C.

Brainstorming

D.

Informative

Buy Now
Questions 45

As a result of an approved change, the project manager updates the project plan with the newest project end date. Which of the following change control processes should the project manager complete NEXT?

Options:

A.

Document the request in the change control log.

B.

Communicate the change deployment.

C.

Conduct an impact assessment.

D.

Implement the change.

Buy Now
Questions 46

Which of the following tasks should the project manager complete first when validating deliverables?

Options:

A.

Assess the documentation.

B.

Obtain stakeholder feedback.

C.

Review the project objectives.

D.

Mitigate risks.

Buy Now
Questions 47

A car manufacturer is presenting to three vendors the abilities and qualifications required to develop the last module of a data warehouse application. The manufacturer is emphasizing the technical skills necessary to complete the project on time and highlighting its current internal IT project. Which of the following best describes this activity?

Options:

A.

Key stakeholder identification

B.

Preliminary procurement

C.

Solution design determination

D.

Critical factor enlistment

Buy Now
Questions 48

As a result of lessons learned, a project manager convenes a meeting to understand the poor quality of the project documentation. During the meeting, project team members provide insights from their perspectives and discussions with group members. Which of the following is the project team doing?

Options:

A.

Executing the approved contingency plan

B.

Constructing an Ishikawa diagram to determine the root cause

C.

Using a Pareto chart to prioritize the different causes

D.

Engaging the senior management team in regard to the issue

Buy Now
Questions 49

A project sponsor asked the PM to provide a summary of the current financial status. The PM uses the following burn up chart for the analysis:

Based on the chart, which of the following is the current status of the project?

Options:

A.

Behind schedule and over budget

B.

Behind schedule and under budget

C.

Ahead of schedule and over budget

D.

Ahead of schedule and under budget

Buy Now
Questions 50

During a brainstorming meeting, a project manager identifies multiple techniques that will help the project team ensure confidence and alignment with the project scope and goals. Which of the following plans is the project manager creating?

Options:

A.

Procurement

B.

Communication

C.

Quality assurance

D.

Risk

Buy Now
Questions 51

Which of the following is a potential challenge that may arise from language barriers among a project team?

Options:

A.

A project team is unable to communicate effectively due to a lack of common technical terminology and jargon.

B.

A project team refuses to learn foreign languages to cater to remote colleagues.

C.

A project team cannot use communication tools due to a lack of IT knowledge.

D.

A project team member located in a different time zone fails to access project resources.

Buy Now
Questions 52

During the execution of a project, a project manager wanted to discover how the number of worked hours was affecting the quality of given tasks. For a two-month period, the following data was documented:

Average worked hours

Which of the following describes the result?

Options:

A.

A negative correlation exists between the number of mistakes and the working hours.

B.

No correlation exists between the number of mistakes and the working hours.

C.

A low correlation exists between the working hours and the number of mistakes.

D.

A positive correlation exists between the number of mistakes and the working hours.

Buy Now
Questions 53

During the project execution phase, Ann, a project manager, received an email from the project sponsor asking for an additional work package to be added to the project scope due to new legislation.

INSTRUCTIONS

Review the email with the latest updates sent by the project sponsor and respond in

the following order:

1. Select the best tool for tracking the server migration progress.

2. Select the new critical path.

3. Select the correct number of engineers required for the server migration phase.

If at any time you would like to bring back the initial state of the simulation, please click

the Reset All button.

Select the Appropriate Tool:

Select the new critical path.

Option A

Option B

Option C

Options:

Buy Now
Questions 54

Hackers are attempting to extract large amounts of data to sell on the dark web. Which of the following steps should a project manager take next to mitigate this risk?

Options:

A.

Update the issue log.

B.

Apply the contingency plan.

C.

Transfer the risk.

D.

Submit a change request.

Buy Now
Questions 55

Although a project was successfully released into production a month ago, a project manager continues to receive project-related work. Which of the following is the reason for this issue?

Options:

A.

The project manager did not release the resources.

B.

The project is in the verification testing phase.

C.

The project manager did not complete the project closure phase.

D.

The project manager did not remove access.

Buy Now
Questions 56

Two developers are discussing the design solution for a particular feature. The meeting is taking longer than expected, and the parties have been unable to reach an agreement. The project manager decides to take a break and continue the meeting on another day. Which of the following techniques is the project manager using?

Options:

A.

Avoiding

B.

Smoothing

C.

Forcing

D.

Compromising

Buy Now
Questions 57

Which of the following aspects are true of agile as compared to waterfall? (Select two).

Options:

A.

Agile works through larger integrated teams.

B.

Agile promotes project manager ownership over deliverables.

C.

Agile reinforces the importance of comprehensive documentation.

D.

Agile has more customer involvement throughout development.

E.

Agile is more flexible to allow for changes in scope.

F.

Agile is comprised of well-defined phases.

Buy Now
Questions 58

Project team members are leaving the company due to a stressful work environment. The project manager needs to capture this concern about potentially losing team members again. Which of the following logs should the project manager use?

Options:

A.

Risk

B.

Change

C.

Defect

D.

Issue

Buy Now
Questions 59

A project manager is assigned to a project that has contracted with vendors. Which of the following actions should the project manager most frequently take? (Select two).

Options:

A.

Update the issue log

B.

Create a project charter

C.

Validate the status report

D.

Monitor performance

E.

Approve deliverables

F.

Baseline the project schedule

Buy Now
Questions 60

Which of the following would be best to utilize when managing communications for project teams across multiple time zones?

Options:

A.

Business collaboration tool

B.

Email

C.

Virtual meetings

D.

Enterprise CMS

Buy Now
Questions 61

A meeting agenda included the following items:

. Review the goals of the project.

. Review the progress of the project.

. Discuss if the project is ready to move forward.

Which of the following best describes this type of meeting?

Options:

A.

Stand-up

B.

Monthly status

C.

Gap analysis

D.

Gate review

Buy Now
Questions 62

A project team evaluated the performance of a new reporting system and the quantity of queries to be processed during predetermined time stamps.

Which of the following is the current status of the process?

Options:

A.

Based on the rule of seven, the process is under control

B.

The amount of data is insufficient to determine if quality is low.

C.

The process is out of control and should be revised.

D.

The goal should be adjusted since most of the data points are close to the lower limit.

Buy Now
Questions 63

A project stakeholder has asked the project manager to provide the performance data of a project. Which of the following should the project manager send to the stakeholder?

Options:

A.

Issue log

B.

Dashboard

C.

WBS

D.

Milestone chart

Buy Now
Questions 64

Which of the following can help identify opportunities for future improvement following the successful closure of a project?

Options:

A.

Contract review

B.

Archived documents

C.

Postmortem

D.

Project rewards

Buy Now
Questions 65

A project manager has been very diligent in maintaining the version control for the documentation of requirements. Which of the following tools is the project manager using?

Options:

A.

Multiauthoring software

B.

Word processor

C.

Real-time polling

D.

Conferencing platforms

Buy Now
Questions 66

A number of unexpected issues have occurred during the execution of a project that will negatively impact the timeline and costs. Which of the following would be best for the project manager to do to mitigate this situation?

Options:

A.

Update the issue log.

B.

Communicate with stakeholders.

C.

Use the contingency reserves.

D.

Review the risk register.

Buy Now
Questions 67

During timeline creation, the project manager is unsure if the development team can complete coding before new servers are installed in the IT department. Which of the following should the project manager do to increase project certainty?

Options:

A.

Hold a new backlog prioritization meeting.

B.

Add milestones to check the project's progress.

C.

Adjust the task relationship to complete coding in advance.

D.

Apply contingency buffers to the critical path.

Buy Now
Questions 68

A project manager is eager to define access requirements during the initiation phase of a project. Which of the following steps should the project manager perform first?

Options:

A.

Define the WBS.

B.

Develop a RAM.

C.

Manage the vendors.

D.

Assess the resource pool.

Buy Now
Questions 69

A project manager distributes minutes after each project meeting. However, the project manager is having difficulties hosting the meetings and documenting the discussions simultaneously. Which of the following should the project manager do in order to be most efficient?

Options:

A.

Assign a scribe to take notes.

B.

Record the meeting and transcribe the notes later.

C.

Instruct each team member to take notes.

D.

Get a facilitator for the meetings.

Buy Now
Questions 70

When creating a project schedule, a project manager adds activities with zero duration. Which of the following describes these types of activities?

Options:

A.

Critical paths

B.

Resources

C.

Milestones

D.

Work breakdown structures

Buy Now
Questions 71

Which of the following BEST identifies the intent and purpose of a project closeout report?

Options:

A.

To provide documentation of lessons learned

B.

To document variances from the initial project baseline

C.

To validate that a project has been successfully completed

D.

To release resources and terminate all access rights

Buy Now
Questions 72

A product manager is producing a project status report for key stakeholders Which of the following should most likely be included? (Select two).

Options:

A.

Feedback

B.

Financial summary

C.

Project schedule

D.

Organizational chart

E.

Approval

F.

Risks

Buy Now
Questions 73

A project manager identifies stakeholders who will be impacted when a new product is delivered to the company. The project manager notices that more stakeholders will be positively impacted than negatively impacted. Which of the following actions should the project manager take?

Options:

A.

List both positively and negatively impacted stakeholders.

B.

Update the communication plan with the new findings.

C.

List the negatively impacted stakeholders only.

D.

List the positively impacted stakeholders only.

Buy Now
Questions 74

A third party needs to perform a short-term task for which the duration cannot be accurately estimated and the cost cannot be calculated in advance. Which of the following should the project manager put in place before work begins?

Options:

A.

Time and materials contract

B.

Master service agreement

C.

Fixed-price contract

D.

Statement of work

E.

Cost-plus agreement

Buy Now
Questions 75

During the execution phase of a project, the project team faced an unexpected website downtime The project manager how a brainstorming session and the team identified causes and effects tor the problem Now the project team needs to analyze and determine whether the particular cause and effect are related by using one of the following charts. Which of the following should the team use?

A)

B)

C)

D)

Options:

A.

Option A

B.

Option B

C.

Option C

D.

Option D

Buy Now
Questions 76

A PM has identified all the resources involved in a project. The next step is to identify which resources are responsible for which tasks. Which of the following should be used to document this information?

Options:

A.

RFI

B.

RACI

C.

WBS

D.

SOW

Buy Now
Questions 77

A highly scored negative risk causes a risk trigger, but the issue has not started yet. Which of the following is the next step the project team should take?

Options:

A.

Execute the contingency plan

B.

Perform a work-around

C.

Escalate to senior management

D.

Assign a risk owner

Buy Now
Questions 78

Government projects require that personnel submit to background screenings for certain clearance requirements. Which of the following best describes this process?

Options:

A.

Data security

B.

Operational security

C.

Physical security

D.

Digital security

Buy Now
Questions 79

A contractor attended a project meeting that was exclusively for company employees. Which of the following actions should the PM take?

Options:

A.

Escalate to vendor management.

B.

Consult the request for proposal.

C.

Review the meeting cadence.

D.

Reinforce the rules of engagement.

Buy Now
Questions 80

During a stand-up meeting, a team member asks to include a change that an important stakeholder requested in the project board. This request is denied, and the team member has to go back to what was originally planned for the sprint. Which of the following individuals should the stakeholder have asked to request the change instead of the team member?

Options:

A.

Architect

B.

Project sponsor

C.

Scrum master

D.

Product owner

Buy Now
Questions 81

Which of the following should a product manager choose in order to enable collaboration between team members located in different regions? (Select two).

Options:

A.

Real-time surveys/polling

B.

Wiki knowledge base

C.

Spreadsheets

D.

Meetings/face-to-face

E.

Real-time, multi-authoring editing software

F.

Charting/diagramming

Buy Now
Questions 82

A project team needs a tool to store information that is captured throughout the life cycle of a project. The information should be stored in a centralized location that is easily accessible to all stakeholders and will provide search functionality. Which of the following tools should be used?

Options:

A.

Secure folder

B.

Real-time, multiauthoring editing software

C.

Digital whiteboard

D.

Wiki knowledge base

Buy Now
Questions 83

Which of the following best describes a benefit of the CI/CD process?

Options:

A.

Software delivery is sped up without compromising quality.

B.

Incremental changes are done at the end of the project.

C.

The software is integrated with other projects easily.

D.

Updates are released every sprint.

Buy Now
Questions 84

During a brainstorming session, a team member expressed concerns that solar flares could cause intermittent outages for those individuals working on the project. Which of the following would be the best tool to communicate this information to stakeholders?

Options:

A.

Status report

B.

Issue log

C.

Risk report

D.

Risk register

Buy Now
Questions 85

Which of the to and allowing interactive feedback from a project team?

Options:

A.

Text message

B.

Chat

C.

Email

D.

Videoconference

Buy Now
Questions 86

A project misses a deadline. The project manager creates the following diagram:

Execution: The change control process was not followed. The customer added requests for previously unrequested features. The team developed unnecessary features.

Requirements: The customer did not provide all requirements during the initiation phase.

Which of the following is most likely the root cause of the delay?

Options:

A.

Team conflicts

B.

Unvalidated deliverables

C.

Scope creep

D.

Gold plating

Buy Now
Questions 87

Which of the following best describes a benefit of the CI/CD process?

Options:

A.

Software delivery is sped up without compromising quality

B.

Incremental changes are done at the end of the project

C.

The software is integrated with other projects easily

D.

Updates are released every sprint

Buy Now
Questions 88

Which of the following would help a project manager identify that project goals have been reached?

Options:

A.

Audit report

B.

Key performance indicators

C.

Backlog

D.

Lessons learned

Buy Now
Questions 89

Which of the following items must be protected as Pll? (Select TWO).

Options:

A.

Job title

B.

Home address

C.

Work phone number

D.

Time zone

E.

Date of birth

F.

Blood type

Buy Now
Questions 90

A project was selected for an audit years after the project closed. Which of the following is most likely to be needed for the audit?

Options:

A.

Signed contracts

B.

Archived documentation

C.

Project closeout report

D.

Lessons learned

Buy Now
Questions 91

A project manager is in the closing phase of an IT asset refresh project that involves the disposal of several computers. The project sponsor notified the project manager that the company recently received a penalty as a result of disposing of some computers improperly. Which of the following should have been considered during initial planning to prevent this situation?

Options:

A.

ESG

B.

PHI

C.

Pll

D.

ROI

Buy Now
Questions 92

Which of the following would a scrum team discuss during a daily stand-up meeting?

Options:

A.

The likelihood of uncertain events occurring, the impact of the uncertain events, and the responses to take

B.

Actions to continue, actions to stop, and recommendations on how to proceed in the future for similar endeavors

C.

Buffer utilization and reallocation, critical resources with schedule impacts, and path convergence coordination

D.

Progress from the previous day, projected accomplishments for today, and foreseen issues that may interfere with work

Buy Now
Questions 93

During a PMO audit, an auditor notices a discrepancy between the existing financial report and the financial information provided by the project manager at the end of the project in the previous quarter. Which of the following activities would have most likely avoided this discrepancy?

Options:

A.

Validation of deliverables

B.

Closing contracts

C.

Project sign-off

D.

Removing access

Buy Now
Questions 94

During a quality analysis review, the causes of several issues have been highlighted. Which of the following should the project manager use to identify the MOST important causes?

Options:

A.

Ishikawa diagram

B.

Scatter diagram

C.

Pareto chart

D.

Decision tree

Buy Now
Questions 95

A company needs to have structured cabling installed in one of its buildings. Which of the following would be the best document for the company to use to obtain and compare information on cabling services and costs from various vendors?

Options:

A.

RFB

B.

RFQ

C.

RFI

D.

RFP

Buy Now
Questions 96

Which of the following is the focus of DevSecOps?

Options:

A.

Securing, testing, and maintaining new software

B.

Developing, testing, and maintaining software

C.

Developing, maintaining, and securing software

D.

Developing, securing, and testing software

Buy Now
Questions 97

A customer requests some changes to a product, and those changes are approved by the CCB. Which of the following should be changed first?

Options:

A.

ROI

B.

KPI

C.

RACI

D.

SOW

Buy Now
Questions 98

A project is executed to migrate all data to a single system following the merger of two companies. The team validates that system performance will not be impacted. Which of the following did the team perform?

Options:

A.

Regression testing

B.

Smoke testing

C.

Stress testing

D.

Automation testing

Buy Now
Questions 99

A project manager notices a resource is overloaded and not completing tasks on time. After reviewing the Gantt chart, the project manager notices the resource has multiple simultaneous tasks that could be executed independently. Which of the following should the project manager do next?

Options:

A.

Change the precedence of the tasks to "finish-to-start".

B.

Evaluate and modify the schedule with a burndown chart

C.

Assign additional resources to prevent overwork.

D.

Perform critical path analysis

Buy Now
Questions 100

A fix that was not submitted to the CCB for approval was applied to an application. Although the change did not have negative consequences, the sponsors expressed concern to the project manager. Which of the following should the project manager do first to prevent this situation from reoccurring?

Options:

A.

Meet with the team and highlight the importance of change management.

B.

Roll back the process and submit a change request.

C.

Document the event as a lesson learned.

D.

Remove the team member who bypassed the CCB process.

Buy Now
Questions 101

Given the following information:

Which of the following represents the critical path of the project?

Options:

A.

A-C-F-I-J

B.

A-C-F-H-J

C.

A-B-D-G-J

D.

A-B-E-G-J

Buy Now
Questions 102

A team is working on a project that has different stages, such as initiation, planning, execution, and closure. Which of the following is this an example of?

Options:

A.

Agile

B.

Waterfall

C.

Standard

D.

Hybrid

Buy Now
Questions 103

A project manager has been scheduling and facilitating project meetings, scribing the minutes, distributing the minutes, and sending agendas prior to upcoming meetings. However, the project manager is frustrated because action items are not being completed. Which of the following should the project manager do to alleviate these concerns?

Options:

A.

Use a software tool during the meeting that can create a transcript of what is discussed.

B.

Have a standing agenda that is vague enough so that it can be used again.

C.

Delegate the roles and responsibilities to improve meeting management.

D.

Reprimand project team members for not completing assigned action items.

Buy Now
Questions 104

In the initiation phase, a PM is reviewing the objectives, the high-level requirements, the success criteria, and the budget resources. Which of the following action items will benefit from this analysis?

Options:

A.

Developing a RACI

B.

Identifying and assessing stakeholders

C.

Assigning project resources

D.

Establishing communication channels

Buy Now
Questions 105

Which of the following best describes the results?

Options:

A.

No correlation exists between the extra hours worked and the number of defects in the code.

B.

A positive correlation exists between the extra hours worked and the number of defects in the code.

C.

A non-linear correlation exists between the extra hours worked and the number of defects in the code.

D.

A negative correlation exists between the extra hours worked and the number of defects in the code.

Buy Now
Questions 106

A software development team implemented an approved change but does not obtain the expected results. The team notifies the change control board (CCB) about the failed change. Which of the following control processes is being followed?

Options:

A.

Scope creep

B.

Recovery plan

C.

Incident report

D.

Risk response

Buy Now
Questions 107

Which of the following cloud models is designed to provide compute, storage, and networking resources on demand?

Options:

A.

Software as a service

B.

Infrastructure as a service

C.

Data as a service

D.

Platform as a service

Buy Now
Questions 108

A project manager, who finished a project some time ago, keeps receiving questions from another project manager who is currently leading a similar project. Which of the following is the most likely cause of this situation?

Options:

A.

The retrospective session feedback was not communicated properly.

B.

The project resources were released ahead of time.

C.

The documentation was not archived as per the PMO standards.

D.

The validation of deliverables is running behind schedule.

Buy Now
Questions 109

Which of the following is a Kanban concept?

Options:

A.

Ensuring business alignment by development iteration

B.

Representing cost-effective tasks through different colors

C.

Allocating resources to high-priority tasks

D.

Managing flow by limiting work in progress

Buy Now
Questions 110

A system is scheduled to go live, and the client signed an SLA. Which of the following elements is part of the agreement?

Options:

A.

Resolution time

B.

Issue list

C.

Work breakdown structure

D.

Cost optimization

Buy Now
Questions 111

A project manager wants to maximize the cost savings on software expenditures for a project. Currently, the project manager does not know how many users will acquire the product. Which of the following procurement methods should the project manager pursue?

Options:

A.

Build

B.

Subscription

C.

Lease

D.

Buy

Buy Now
Questions 112

Which of the following is the most important activity for the project manager during the closure of a project?

Options:

A.

Obtain project sign-off.

B.

Capture lessons learned.

C.

Document historical information.

D.

Release resources.

Buy Now
Questions 113

Stakeholders ask the PM to provide an updated budget. Which of the following is the most important reason to update a project's budget during the execution phase?

Options:

A.

Evaluate the project's communication plan.

B.

Track and manage the project’s financial condition.

C.

Report the project’s risks and issues.

D.

Distribute resources to the project.

Buy Now
Questions 114

A new project has been assigned to a project manager. In order to move forward with the project charter, which of the following should the project manager work with to define the success criteria for the initiative?

Options:

A.

Lead architect

B.

Project sponsor

C.

Program manager

D.

Scrum master

Buy Now
Questions 115

During an executive call, a project sponsor found out about issues with the project but was not able to provide details about the next steps. Which of the following needs to be revised?

Options:

A.

Project dashboard

B.

Gap analysis

C.

Risk register

D.

Communication plan

Buy Now
Questions 116

A financial manager reports that several employees' allocations from the past month appear to be 200% even though they are only assigned to a particular project. Which of the following could MOST likely be the cause of this issue?

Options:

A.

A project manager assigned the wrong resources.

B.

A project manager did not release the resources

C.

A project manager did not remove the system access.

D.

A project manager did not provide the project sign-off.

Buy Now
Questions 117

When assigning access, classifying information based on sensitivity is referred to as:

Options:

A.

Digital security

B.

Physical security

C.

Data security

D.

Operational security

Buy Now
Questions 118

Because the project team lacks hands-on experience, the project manager has decided to involve a third-party vendor to complete the development of a product. Which of the following documents should the project manager expedite first?

Options:

A.

RFI

B.

RFP

C.

RFQ

D.

RFB

Buy Now
Questions 119

A senior PM is working on the development of a tax application and focuses efforts to create an environment to facilitate and motivate teamwork. The team members seem to be in the storming phase. Which of the following best describes the team life cycle?

Options:

A.

The team members are in a conflict that affects their relationship.

B.

The team members perform as a well-organized unit.

C.

The team members have met and are learning about the project.

D.

The team members have completed the work and are moving on from the project.

Buy Now
Questions 120

Given the following velocity chart:

Which of the following updates on the project status should the Scrum master provide to the senior management team?

Options:

A.

The project utilized all of its available reserve.

B.

The project has scope creep.

C.

The project deviated from the critical path.

D.

The project is trending ahead of schedule.

Buy Now
Questions 121

A project manager working in a strong matrix organization was selected to manage a new project with trending technologies. During the kickoff meeting, one of the stakeholders mentions that the company has never worked with such technologies. Which of the following should the project manager do next?

Options:

A.

Train the project team members and develop a detailed scope statement.

B.

Assign project resources and procure additional team members.

C.

Perform a preliminary procurement needs assessment and determine budget considerations.

D.

Define units of work and develop a project schedule.

Buy Now
Questions 122

Project members are based in three countries and each work remotely Which of the following would a project manager use to improve internal project communication?

Options:

A.

Progress reporting

B.

Meeting minutes

C.

Team touch points

D.

Change management

Buy Now
Questions 123

A team is analyzing the backlog in order to decide what to include in the next sprint. Which of the following aspects is the most important for the team to take into consideration?

Options:

A.

Time to be fixed

B.

Impact to project

C.

Issue category

D.

Resource availability

Buy Now
Questions 124

A project sponsor requires a system that is capable of providing integrated management of all the business's core functions. Which of the following systems is the project sponsor describing?

Options:

A.

CMS

B.

CRM

C.

EDRMS

D.

ERP

Buy Now
Questions 125

A project manager provided the team with a summary Gantt chart for the project. The team, however, has expressed interest in seeing the sequencing between all of the tasks. Which of the following should the project manager provide?

Options:

A.

Project network diagram

B.

Fishbone diagram

C.

Burndown chart

D.

Milestone chart

Buy Now
Questions 126

Defects associated with project deliverables have been reported. The project team needs to find the cause of the defects. Which of the following tools should the project team use to find the cause?

Options:

A.

Kanban board

B.

Pareto chart

C.

Ishikawa diagram

D.

Decision tree

Buy Now
Questions 127

A project was closed according to the planned project schedule. Security teams later identified that one of the contractors stole data after the project's closure. Which of the following would have most likely prevented the data from being stolen?

Options:

A.

Removing access

B.

Closing contracts

C.

Project sign-off

D.

Project evaluation

Buy Now
Questions 128

Which of the following demonstrates awareness of regulations and standards when conducting a project?

Options:

A.

Establishing a measurement system for the team members' performance

B.

Controlling project costs to fall within the company-approved variance

C.

Reviewing advertising trends in the market before launching a new product

D.

Submitting architectural plans for approval before commencing construction

Buy Now
Questions 129

A project team has just experienced an unexpected event and implemented a work-around. Which of the following documents should be used to record the event? (Select TWO).

Options:

A.

Risk report

B.

Defect log

C.

Issue log

D.

Backlog

E.

Change log

F.

Progress report

Buy Now
Questions 130

During a status meeting, the development team reviews work and finds an unforeseen dependency on one of the critical project activities. As a result, the project will most likely be delayed. Which of the following actions should the project manager MOST likely perform?

Options:

A.

Work with the project scheduler to update the project timeline.

B.

Communicate to the stakeholders about the updated timeline.

C.

Ask the development team to fast-track upcoming activities.

D.

Add two resources so the critical activities will finish on time.

Buy Now
Questions 131

A company is working on a software development project that involves an external customer. Which of the following describes a project manager's responsibility within this type of project?

Options:

A.

Manage the project schedule.

B.

Define the functional requirements.

C.

Develop components for the software.

D.

Assess and authorize security policies.

Buy Now
Questions 132

During the testing process, testers have found multiple bugs that could jeopardize the project commitment date Which of the following tools should the project manager use first to update the findings?

Options:

A.

Defect log

B.

Change log

C.

Issue log

D.

Risk log

Buy Now
Questions 133

Which of the following is an intended outcome of a stand-up meeting?

Options:

A.

To identify team members for next tasks

B.

To identify future tasks

C.

To identify stakeholders for next tasks

D.

To identify blocking tasks

Buy Now
Questions 134

Which of the following tools should a project manager use to assess the activities performed, work effort applied, and the productivity of a project?

Options:

A.

Project status report

B.

Project evaluation review

C.

Project management software

D.

Requirements traceability matrix

Buy Now