For an upcoming project kickoff. a PM is looking for a way to illustrate roles for major project activities. Which of the following would be the MOST useful option?
A project manager does not have the power to reward team members when they accomplish something or penalize them when they fail to perform well. As a result, the project manager is having issues with team members. Which of the following describes this organizational structure?
A project manager has decided to outsource portions of a project and will conduct a separate procurement. In which of the following phases does this task occur?
A few weeks before a project is scheduled to be completed, the client asks to add a new feature to the product that is being developed. The project manager analyzes the project schedule and determines the feature can be implemented quite easily without affecting the completion date. Which of the following should the project manager do first?
A global shipping slowdown is causing critical raw materials needed for manufacturing to be delivered late. As a result, a project's production run will be delayed from the beginning.
Which of the following dependencies is most likely happening?
A project manager is reviewing a signed legal document pertaining to the hiring of a vendor who will develop an experimental solution. The vendor could not provide accurate estimates at this time because the requirements will probably be changing. The document also contains information about the resources involved and the rates the vendor will charge for the work. Which of the following best describes the legal document the project manager is reviewing?
A project manager is currently meeting with a vendor who completed the project work. All invoices associated with the project have been paid. Which of the following best describes the project manager's objective for the vendor meeting?
A procurement team analyzes solutions submitted from multiple vendors for the upcoming release of a required development service. The procurement team identifies a potential partnership. Which of the following would the procurement team most likely request?
Which of the following aspects are true of waterfall as compared to agile? (Select two).
Which of the following should be considered first when determining the privacy management for project data?
A team found a deficiency in an application and is proposing improvements, but the sponsor requests a business case. Which of the following best describes the intended objective of the business case?
A team member needs to make an emergency update. The team member is unable to return to the office. Which of the following is the most secure way to make the update?
Which of the following concepts represents multiple resources interfaced to run reports?
Functional managers are reluctant to provide a project manager with resources for a project because they think the project should include a certain scope. The project manager reviews the project documentation and confirms the items the functional managers wanted to include were out of scope. Which of the following would be the best course of action for the project manager to take?
A project sponsor is struggling to provide the latest project status information on a weekly executive call. Which of the following should be reviewed?
A member keeps bringing up unrelated topics during a team meeting. Which of the following should the protect manager do to keep the discussion on track?
A project manager needs to pull data from a burndown chart. Which of the following should the project manager analyze to obtain this data in the most efficient way?
Which of the following BEST illustrates how team members with different roles should interact on the team?
A critical business initiative introduced new processes and technology to the organization. Which of the following approaches should be used to ensure the deliverables are increasingly adopted and leveraged by the organization over time?
A project team wants to compare two potential vendors' costs and risks for completing project tasks. Which of the following visualizations will best facilitate this analysis?
A system was implemented, and testing was successfully completed. Which of the following should the project manager do NEXT?
A company wants to move its data from on premises to off premises. Which of the following cloud models should be pursued?
Which of the following provides a layered approach to logging in to systems that contain an organization's most valuable intellectual property?
Which of the following best describes the difference between the current state and the desired future state in project management?
A project manager is unclear about the budget and timeline prior to the start of a project. Which of the following best describes what type of meeting needs to take place?
Given the following chart showing committed work (orange) vs. actual work completed (blue) across 10 sprints:
Which of the following best describes the team's performance?
During the project initiation phase, a project manager needs to construct a project schedule and show the project dependencies. Which of the following should the project manager use for this task?
Project team members enter their time sheets into a system that also displays incurred project cost. Which of the following systems can perform this task?
A PM wants to provide a visual representation of how a project is organized into tasks and how the tasks relate to each other. Which of the following can the PM use?
A project sponsor would like to develop a minimum viable product, but the requirements are not well defined. Which of the following should the project sponsor use?
The project manager must create a project charter. Which of the following should be included in the charter?
As a result of an internal assessment, the steering committee states that the company does not currently have the required skill set or technical tools to develop a particular feature in the project. Which of the following procurement methods would help the company?
A project team member recalls a specific chat with another member that contained key information related to a previous project, which no one else on the project team is aware of. Which of the following best describes what was needed to address this concern?
A project manager is monitoring team performance by comparing committed versus completed work. The project manager creates the following:
Which of the following most likely represents the number of items in the backlog?
A project manager is conducting an evaluation of a product to determine whether it is meeting the requirements. The manager needs to compare the current status of the product with its optimal future status and determine what, if anything, needs to be done to improve it. Which of the following types of evaluations would be best for the manager to use?
A company purchases new software. The project manager needs to present the new software’s features to the stakeholders. Which of the following meeting types should the project manager and stakeholders have?
As a result of an approved change, the project manager updates the project plan with the newest project end date. Which of the following change control processes should the project manager complete NEXT?
Which of the following tasks should the project manager complete first when validating deliverables?
A car manufacturer is presenting to three vendors the abilities and qualifications required to develop the last module of a data warehouse application. The manufacturer is emphasizing the technical skills necessary to complete the project on time and highlighting its current internal IT project. Which of the following best describes this activity?
As a result of lessons learned, a project manager convenes a meeting to understand the poor quality of the project documentation. During the meeting, project team members provide insights from their perspectives and discussions with group members. Which of the following is the project team doing?
A project sponsor asked the PM to provide a summary of the current financial status. The PM uses the following burn up chart for the analysis:
Based on the chart, which of the following is the current status of the project?
During a brainstorming meeting, a project manager identifies multiple techniques that will help the project team ensure confidence and alignment with the project scope and goals. Which of the following plans is the project manager creating?
Which of the following is a potential challenge that may arise from language barriers among a project team?
During the execution of a project, a project manager wanted to discover how the number of worked hours was affecting the quality of given tasks. For a two-month period, the following data was documented:
Average worked hours
Which of the following describes the result?
During the project execution phase, Ann, a project manager, received an email from the project sponsor asking for an additional work package to be added to the project scope due to new legislation.
INSTRUCTIONS
Review the email with the latest updates sent by the project sponsor and respond in
the following order:
1. Select the best tool for tracking the server migration progress.
2. Select the new critical path.
3. Select the correct number of engineers required for the server migration phase.
If at any time you would like to bring back the initial state of the simulation, please click
the Reset All button.
Select the Appropriate Tool:
Select the new critical path.
Option A
Option B
Option C
Hackers are attempting to extract large amounts of data to sell on the dark web. Which of the following steps should a project manager take next to mitigate this risk?
Although a project was successfully released into production a month ago, a project manager continues to receive project-related work. Which of the following is the reason for this issue?
Two developers are discussing the design solution for a particular feature. The meeting is taking longer than expected, and the parties have been unable to reach an agreement. The project manager decides to take a break and continue the meeting on another day. Which of the following techniques is the project manager using?
Which of the following aspects are true of agile as compared to waterfall? (Select two).
Project team members are leaving the company due to a stressful work environment. The project manager needs to capture this concern about potentially losing team members again. Which of the following logs should the project manager use?
A project manager is assigned to a project that has contracted with vendors. Which of the following actions should the project manager most frequently take? (Select two).
Which of the following would be best to utilize when managing communications for project teams across multiple time zones?
A meeting agenda included the following items:
. Review the goals of the project.
. Review the progress of the project.
. Discuss if the project is ready to move forward.
Which of the following best describes this type of meeting?
A project team evaluated the performance of a new reporting system and the quantity of queries to be processed during predetermined time stamps.
Which of the following is the current status of the process?
A project stakeholder has asked the project manager to provide the performance data of a project. Which of the following should the project manager send to the stakeholder?
Which of the following can help identify opportunities for future improvement following the successful closure of a project?
A project manager has been very diligent in maintaining the version control for the documentation of requirements. Which of the following tools is the project manager using?
A number of unexpected issues have occurred during the execution of a project that will negatively impact the timeline and costs. Which of the following would be best for the project manager to do to mitigate this situation?
During timeline creation, the project manager is unsure if the development team can complete coding before new servers are installed in the IT department. Which of the following should the project manager do to increase project certainty?
A project manager is eager to define access requirements during the initiation phase of a project. Which of the following steps should the project manager perform first?
A project manager distributes minutes after each project meeting. However, the project manager is having difficulties hosting the meetings and documenting the discussions simultaneously. Which of the following should the project manager do in order to be most efficient?
When creating a project schedule, a project manager adds activities with zero duration. Which of the following describes these types of activities?
Which of the following BEST identifies the intent and purpose of a project closeout report?
A product manager is producing a project status report for key stakeholders Which of the following should most likely be included? (Select two).
A project manager identifies stakeholders who will be impacted when a new product is delivered to the company. The project manager notices that more stakeholders will be positively impacted than negatively impacted. Which of the following actions should the project manager take?
A third party needs to perform a short-term task for which the duration cannot be accurately estimated and the cost cannot be calculated in advance. Which of the following should the project manager put in place before work begins?
During the execution phase of a project, the project team faced an unexpected website downtime The project manager how a brainstorming session and the team identified causes and effects tor the problem Now the project team needs to analyze and determine whether the particular cause and effect are related by using one of the following charts. Which of the following should the team use?
A)
B)
C)
D)
A PM has identified all the resources involved in a project. The next step is to identify which resources are responsible for which tasks. Which of the following should be used to document this information?
A highly scored negative risk causes a risk trigger, but the issue has not started yet. Which of the following is the next step the project team should take?
Government projects require that personnel submit to background screenings for certain clearance requirements. Which of the following best describes this process?
A contractor attended a project meeting that was exclusively for company employees. Which of the following actions should the PM take?
During a stand-up meeting, a team member asks to include a change that an important stakeholder requested in the project board. This request is denied, and the team member has to go back to what was originally planned for the sprint. Which of the following individuals should the stakeholder have asked to request the change instead of the team member?
Which of the following should a product manager choose in order to enable collaboration between team members located in different regions? (Select two).
A project team needs a tool to store information that is captured throughout the life cycle of a project. The information should be stored in a centralized location that is easily accessible to all stakeholders and will provide search functionality. Which of the following tools should be used?
During a brainstorming session, a team member expressed concerns that solar flares could cause intermittent outages for those individuals working on the project. Which of the following would be the best tool to communicate this information to stakeholders?
A project misses a deadline. The project manager creates the following diagram:
Execution: The change control process was not followed. The customer added requests for previously unrequested features. The team developed unnecessary features.
Requirements: The customer did not provide all requirements during the initiation phase.
Which of the following is most likely the root cause of the delay?
Which of the following would help a project manager identify that project goals have been reached?
A project was selected for an audit years after the project closed. Which of the following is most likely to be needed for the audit?
A project manager is in the closing phase of an IT asset refresh project that involves the disposal of several computers. The project sponsor notified the project manager that the company recently received a penalty as a result of disposing of some computers improperly. Which of the following should have been considered during initial planning to prevent this situation?
Which of the following would a scrum team discuss during a daily stand-up meeting?
During a PMO audit, an auditor notices a discrepancy between the existing financial report and the financial information provided by the project manager at the end of the project in the previous quarter. Which of the following activities would have most likely avoided this discrepancy?
During a quality analysis review, the causes of several issues have been highlighted. Which of the following should the project manager use to identify the MOST important causes?
A company needs to have structured cabling installed in one of its buildings. Which of the following would be the best document for the company to use to obtain and compare information on cabling services and costs from various vendors?
A customer requests some changes to a product, and those changes are approved by the CCB. Which of the following should be changed first?
A project is executed to migrate all data to a single system following the merger of two companies. The team validates that system performance will not be impacted. Which of the following did the team perform?
A project manager notices a resource is overloaded and not completing tasks on time. After reviewing the Gantt chart, the project manager notices the resource has multiple simultaneous tasks that could be executed independently. Which of the following should the project manager do next?
A fix that was not submitted to the CCB for approval was applied to an application. Although the change did not have negative consequences, the sponsors expressed concern to the project manager. Which of the following should the project manager do first to prevent this situation from reoccurring?
Given the following information:
Which of the following represents the critical path of the project?
A team is working on a project that has different stages, such as initiation, planning, execution, and closure. Which of the following is this an example of?
A project manager has been scheduling and facilitating project meetings, scribing the minutes, distributing the minutes, and sending agendas prior to upcoming meetings. However, the project manager is frustrated because action items are not being completed. Which of the following should the project manager do to alleviate these concerns?
In the initiation phase, a PM is reviewing the objectives, the high-level requirements, the success criteria, and the budget resources. Which of the following action items will benefit from this analysis?
A software development team implemented an approved change but does not obtain the expected results. The team notifies the change control board (CCB) about the failed change. Which of the following control processes is being followed?
Which of the following cloud models is designed to provide compute, storage, and networking resources on demand?
A project manager, who finished a project some time ago, keeps receiving questions from another project manager who is currently leading a similar project. Which of the following is the most likely cause of this situation?
A system is scheduled to go live, and the client signed an SLA. Which of the following elements is part of the agreement?
A project manager wants to maximize the cost savings on software expenditures for a project. Currently, the project manager does not know how many users will acquire the product. Which of the following procurement methods should the project manager pursue?
Which of the following is the most important activity for the project manager during the closure of a project?
Stakeholders ask the PM to provide an updated budget. Which of the following is the most important reason to update a project's budget during the execution phase?
A new project has been assigned to a project manager. In order to move forward with the project charter, which of the following should the project manager work with to define the success criteria for the initiative?
During an executive call, a project sponsor found out about issues with the project but was not able to provide details about the next steps. Which of the following needs to be revised?
A financial manager reports that several employees' allocations from the past month appear to be 200% even though they are only assigned to a particular project. Which of the following could MOST likely be the cause of this issue?
When assigning access, classifying information based on sensitivity is referred to as:
Because the project team lacks hands-on experience, the project manager has decided to involve a third-party vendor to complete the development of a product. Which of the following documents should the project manager expedite first?
A senior PM is working on the development of a tax application and focuses efforts to create an environment to facilitate and motivate teamwork. The team members seem to be in the storming phase. Which of the following best describes the team life cycle?
Given the following velocity chart:
Which of the following updates on the project status should the Scrum master provide to the senior management team?
A project manager working in a strong matrix organization was selected to manage a new project with trending technologies. During the kickoff meeting, one of the stakeholders mentions that the company has never worked with such technologies. Which of the following should the project manager do next?
Project members are based in three countries and each work remotely Which of the following would a project manager use to improve internal project communication?
A team is analyzing the backlog in order to decide what to include in the next sprint. Which of the following aspects is the most important for the team to take into consideration?
A project sponsor requires a system that is capable of providing integrated management of all the business's core functions. Which of the following systems is the project sponsor describing?
A project manager provided the team with a summary Gantt chart for the project. The team, however, has expressed interest in seeing the sequencing between all of the tasks. Which of the following should the project manager provide?
Defects associated with project deliverables have been reported. The project team needs to find the cause of the defects. Which of the following tools should the project team use to find the cause?
A project was closed according to the planned project schedule. Security teams later identified that one of the contractors stole data after the project's closure. Which of the following would have most likely prevented the data from being stolen?
Which of the following demonstrates awareness of regulations and standards when conducting a project?
A project team has just experienced an unexpected event and implemented a work-around. Which of the following documents should be used to record the event? (Select TWO).
During a status meeting, the development team reviews work and finds an unforeseen dependency on one of the critical project activities. As a result, the project will most likely be delayed. Which of the following actions should the project manager MOST likely perform?
A company is working on a software development project that involves an external customer. Which of the following describes a project manager's responsibility within this type of project?
During the testing process, testers have found multiple bugs that could jeopardize the project commitment date Which of the following tools should the project manager use first to update the findings?
Which of the following tools should a project manager use to assess the activities performed, work effort applied, and the productivity of a project?