Pre-Summer Sale - Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 65percent

Welcome To DumpsPedia

PMI-RMP Sample Questions Answers

Questions 4

During the early planning stages of an AI-based software development project, the project team begins outlining the risk management activities. The risk manager notices that key stakeholders, such as data scientists, product owners, and external data vendors, lack a shared understanding of risk management principles.

What should the risk manager do to educate stakeholders?

Options:

A.

Conduct risk workshops tailored to all stakeholders.

B.

Invite all stakeholders to daily coordination meetings.

C.

Distribute risk-policy documents to all stakeholders.

D.

Provide project management training to all stakeholders.

Buy Now
Questions 5

A risk manager is managing risks of a mission critical application. A subject matter expert (SME) asks the risk manager to treat every single risk identified as an extremely high priority.

What should the risk manager do?

Options:

A.

Ask the project sponsor if every risk in the risk register can have the same priority.

B.

Mark every identified risk as an extremely high priority and any future risks as a lower priority.

C.

Agree with the SME, treat every risk with equal priority, and inform all stakeholders.

D.

Perform a sensitivity analysis and determine the correct priority of every identified risk.

Buy Now
Questions 6

A project manager is educating the project team on risk management regarding the role of threats and opportunities. The team decides to log the opportunities in the current project ' s risk register to try to maximize their chances of occurrence.

What should the project team do next?

Options:

A.

Conduct a strengths, weaknesses, opportunities, and threats (SWOT) analysis.

B.

Log the threats in the risk register to try to minimize the probability of occurrence.

C.

Log the threats in the risk register to try to maximize the probability of occurrence.

D.

Update the project management plan to ensure the results of the opportunities are captured.

Buy Now
Questions 7

Project stakeholders can often be risk averse with little to no knowledge of the risk process. How should a risk manager increase stakeholder risk appetite?

Options:

A.

Exclude risk averse stakeholders from future risk discussions

B.

Explain risk handling and mitigation strategies

C.

Increase the impact of all risks in the risk breakdown structure (RBS)

D.

Develop a generous probabilistic cash flow model

Buy Now
Questions 8

An organization with a portfolio of unique business functions kicks-off a performance improvement project across the entire organization. There are a large number of stakeholders the project team will need to consider during risk identification.

What three actions should the risk manager ensure the project team performs during risk identification? (Choose 3)

Options:

A.

Develop checklists based on historical information

B.

Conduct interviews, meetings, and focus groups

C.

Assign a different risk manager for each portfolio unit

D.

Employ brainstorming to generate spontaneous ideas

E.

Perform qualitative and quantitative risk analyses 

Buy Now
Questions 9

A project team is preparing a project plan for a government-funded project with multiple stakeholders, including government employees. The project sponsor requests the risk manager estimates the potential costs associated with delays that may arise from government employees, due to bureaucratic processes and other administrative factors.

How should the risk manager approach this task?

Options:

A.

Create a risk register to document all potential risks and estimated impacts, including delays due to government employees.

B.

Develop a risk response plan that includes specific mitigation strategies for government-related delays.

C.

Perform a quantitative risk analysis to determine the potential financial impact of government-related delays.

D.

Conduct a qualitative risk analysis to assess the likelihood and impact of potential delays.

Buy Now
Questions 10

A project team is discussing which risk requires more attention and resources for response planning. The team evaluated the schedule to determine which activity had the greatest impact on the project ' s total duration.

After analyzing the quantitative analysis results, which activity should the team pay more attention to?

Use the chart for the analysis.

Options:

A.

Activity 3.2

B.

Activity 2.3

C.

Activity 3.5

D.

Activity 1.2

Buy Now
Questions 11

During a risk identification process in a construction project, the lack of space to install air conditioners is raised as a risk with high impact. Which is an example of an early risk trigger?

Options:

A.

A potential need to share the space with other machinery

B.

A different type of equipment received before installation

C.

A time delay during air conditioning installation activities

D.

A quality nonconformance issue raised during the inspection

Buy Now
Questions 12

Members of a project team are not taking their risk management responsibilities seriously. They do not consider risk management as primary to the project’s success and do not believe that the benefits are significant.

What should the risk manager do?

Options:

A.

Schedule a meeting to review and develop realistic risk thresholds with the project team.

B.

Motivate and influence the project team with risk engagement activities like workshops.

C.

Ensure that risk management responsibilities are clearly identified in the risk management plan.

D.

Ensure that the risk language used by all stakeholders is consistent with the risk management plan.

Buy Now
Questions 13

An organization is executing two projects — Project A and Project B — simultaneously. A previously identified risk will impact the schedule for Project A. While executing the mitigation plan, a number of residual risks are identified that could provide cost savings for Project B.

Which action should the risk manager for Project A take?

Options:

A.

Review the findings in Project A ' s closure documents and propose a new organizational process for portfolio risk management.

B.

Consult with Project B ' s risk manager and determine where synergies might exist between the risk management plans for both projects.

C.

Combine the risk registers for Project A and Project B and determine if there are any additional cross-project opportunities to exploit.

D.

Continue executing the planned risk mitigation to avoid any additional schedule impact to Project A.

Buy Now
Questions 14

A project manager has just been assigned to a new project. The project manager has been tasked by the project sponsor to ensure the project risks are closely managed. The project manager starts with developing the risk management plan.

What is the expected outcome of developing the risk management plan?

Options:

A.

Being able to monitor and control risks throughout the project.

B.

Defining how risk management will be executed throughout the project.

C.

Documenting the communication strategy for risks throughout the project.

D.

Having the ability to identify risks throughout the project.

Buy Now
Questions 15

A project manager is developing the risk register and works with the team to analyze risks and determine their probability and impact. There is valuable historical data available that may be used to simulate the overall risk outcome.

Which type of analysis should the project manager use in this instance?

Options:

A.

Check list analysis

B.

Cause and effect

C.

Specialized meeting

D.

Quantitative analysis

Buy Now
Questions 16

A risk manager of a complex project has identified a risk and believes a deeper understanding of the source and likelihood is necessary. How should the risk manager proceed?

Options:

A.

Develop and employ an Ishikawa diagram

B.

Analyze the assumptions and constraints

C.

Perform a review of project documents

D.

Create prompt lists for expert interviews

Buy Now
Questions 17

A risk manager is collaborating with project stakeholders and the project team to identify risks in a construction project. The risk manager intends to use an approach that engages stakeholders based on information, such as scope baseline and project estimates, while also determining risk impacts based on this approach.

Which risk identification approach should the risk manager use to achieve this goal?

Options:

A.

Strengths, weaknesses, opportunities, and threats (SWOT) analysis

B.

Brainstorming technique

C.

Delphi technique

D.

Assumptions and constraints analysis

Buy Now
Questions 18

A risk manager has been assigned to a project constructing a chemical laboratory. Unfamiliar with chemical laboratories, the risk manager is unsure of where to start objectively identifying risks.

What should the risk manager do?

Options:

A.

Import a risk register from other industry chemical laboratories.

B.

Define chemical laboratory safety risk thresholds.

C.

Review published operational experience reports.

D.

Draft threat and opportunity risks that come to mind.

Buy Now
Questions 19

A risk manager manages risks in a construction project. A stakeholder mentions that if there is less than a 50% chance of rain, construction should continue. Another stakeholder says that if there is less than a 60% chance of rain, construction should continue.

What should the risk manager do next to find out the correct limit?

Options:

A.

Review the agreed-upon risk tolerance

B.

Perform a sensitivity analysis of the risk

C.

Find out the stakeholders’ risk appetite

D.

Use industry standard risk thresholds

Buy Now
Questions 20

During a virtual workshop presenting a product to potential clients, a facilitator emails the product brochure and asks attendees to check their spam folder if the email does not appear in their inbox. What kind of threat strategy is the facilitator applying?

Options:

A.

Accept actively

B.

Mitigate

C.

Accept passively

D.

Share

Buy Now
Questions 21

Three months into a program, multiple workstreams are showing issues. At this point, the program manager requires that a risk impact assessment be conducted.

What will help calculate the impact?

Options:

A.

Risk analysis

B.

Risk identification

C.

Risk treatment

D.

Risk evaluation

Buy Now
Questions 22

During project execution for a software development program, a risk manager notices the results vary from the stated expectations in the planning phase. The project team states that there was unrealistic planning.

What should the risk manager do next to understand the differences between planning and execution?

Options:

A.

Engage with the team to present the actual results to the sponsor.

B.

Prepare a management of change (MOC) to adjust the project cost and duration.

C.

Move forward with the lessons learned from the sprint.

D.

Review the assumptions to understand any change.

Buy Now
Questions 23

The project risk manager for an environmental preservation project has started the process of monitoring and controlling risks, The project manager has asked the project team to document the results of this process.

How should this documentation be utilized in the future?

Options:

A.

To return the remaining amount of the contingency reserve

B.

To ensure information is recorded for lessons learned

C.

To comply with the rules and regulations

D.

To hold those who created the risk accountable

Buy Now
Questions 24

A project ' s design has been completed and approved on time. The construction subcontractor should be mobilizing to start construction but does not have the necessary materials in place, causing a delaying in the project. The risk register only contains risks for the design phase of the project.

What should the project manager have done differently?

Options:

A.

Executed the Monte Carlo sensitivity analysis prior to mobilization

B.

Added generic construction risks to the risk register before construction began

C.

Reviewed the assumptions/exclusions register in the project charter

D.

Performed risk identification exercises for the full lifecycle of the project

Buy Now
Questions 25

After completing the risk register, many team members feel there is a lack of time prioritization for one of the identified risks What are the team members referring to?

Options:

A.

Risk trigger

B.

Risk escalation

C.

Risk urgency

D.

Risk time impact

Buy Now
Questions 26

A risk manager on an infrastructure project gathers and analyzes performance data. The risk manager wants to identify which variables will impact the schedule and determine how these factors interact.

Which data analysis tool should the risk manager use to forecast future performance?

Options:

A.

Sensitivity analysis

B.

What-if scenario analysis

C.

Regression analysis

D.

Decision tree analysis

Buy Now
Questions 27

During the execution phase of a construction project, a risk response strategy is implemented to mitigate the risk of supply chain disruptions. However, this leads to a secondary risk of increased logistics costs.

What should the risk manager do to address the new risk of increased logistics costs?

Options:

A.

Accept the increased costs as part of the project ' s risk threshold.

B.

Develop a contingency plan to cover additional logistics expenses.

C.

Switch suppliers to potentially reduce logistics expenses.

D.

Incorporate a cost-sharing arrangement with the suppliers.

Buy Now
Questions 28

Multiple new risks have come up on a project that were not included on the risk register. The project manager met with the team to explain that risk management is critical for the success of the project, and risk identification is key.

What should the project manager do next?

Options:

A.

Review assumptions and constraints around risks.

B.

Develop the risk response plans for identified risks.

C.

Determine the likelihood and impact of the risks.

D.

Apply an iterative approach to risk identification.

Buy Now
Questions 29

A risk manager wants to determine what risk has the biggest impact on project cost. The risk manager identified three risks, which could occur in different phases of the project.

What should the risk manager do first to understand the impact on project cost?

Options:

A.

Conduct a subject matter expert (SME) meeting.

B.

Perform qualitative analysis.

C.

Prioritize after quantitative analysis

D.

Prioritize the stakeholders affected.

Buy Now
Questions 30

A project team has completed the risk identification steps in a project and compiled a list of 25 risks. The team wants to create response plans for all the risks to avoid any future issues, but the resources and constraints limit the options.

What should the risk manager do?

Options:

A.

Perform a sensitivity analysis.

B.

Perform a qualitative risk analysis.

C.

Perform a constraint analysis.

D.

Perform a root-cause analysis. 

Buy Now
Questions 31

When selecting strategies as an activity of Plan Risk Response, what is the overall goal?

Options:

A.

Select the strategies with the least overall impact to resources.

B.

Select the strategies with the least financial impact.

C.

Select the strategies with the greatest overall positive influence.

D.

Select the strategies with the greatest benefit to stakeholders.

Buy Now
Questions 32

A two-year project with a budget of US$2 million has completed about 60% of the work at the end of the first year. The actual cost incurred to complete the remaining 40% of work is about USS1.5 million. As a part of performing a specialized risk analysis, the calculated schedule performance index (SPI) is 1.2 and cost performance index (CPI) is 0.53.

How should the risk manager interpret such a low CPI value?

Options:

A.

The cost control processes is ineffective.

B.

The cost baseline is inaccurate.

C.

The actual reported costs are inaccurate.

D.

The cost related risks are effectively managed.

Buy Now
Questions 33

A risk manager has a well-structured risk management process in place for a complex project with a tight schedule. Despite implementing preventive actions, one of the risks identified in the early stages of the project has still occurred and is now an issue.

What should the risk manager do next?

Options:

A.

Meet with the project team to brainstorm potential solutions to the problem.

B.

Implement the risk response plan to remedy the problem as soon as possible.

C.

Initiate discussions with the project manager to decide how to manage the problem.

D.

Escalate the problem to the project sponsor to agree on the best course of action. 

Buy Now
Questions 34

The stakeholders of a building construction project are not comfortable with the project manager ' s handling of the project as they believe there is a financial risk. The project manager asks the risk manager to assist in demonstrating to the stakeholders that the project risks are under a tolerable threshold.

What should the risk manager do first to demonstrate this to the stakeholders?

Options:

A.

Gather other project risk historical information.

B.

Gather and reconcile project risk report data.

C.

Work with the sponsor to convince the risks are under control.

D.

Work with the team to ensure the project is in good health. 

Buy Now
Questions 35

A risk manager is preparing risk reports to be included in the monthly status report for project executives. How should the risk manager present the information?

Options:

A.

Earned value management (EVM) variance metrics

B.

A risk burndown chart showing remaining risks

C.

The format established in the risk management plan

D.

An itemized list of remaining risks and their scores 

Buy Now
Questions 36

When processing freight invoices for a project, the project manager notices the shipping costs exceeded the budget due to increased fuel costs. The risk manager included this risk in the project ' s contingency allowance. When reviewing the project budget execution reports, the project manager notices unused budget remaining in other closed tasks of the project that could cover the additional shipping costs.

What should the project manager do?

Options:

A.

Process the freight invoices at higher shipping costs against the project ' s contingency allowance.

B.

Request a formal change order from the customer to increase the project ' s total budget.

C.

Process the freight invoices for the budgeted amount and hope the shipping company will forgive the difference.

D.

Ask the project sponsor to cover the additional shipping costs on the company ' s reserves account.

Buy Now
Questions 37

A new project is about to start, and the risk manager wants to review some documents that could be relevant for risk identification. Which document will help the risk manager in this process?

Options:

A.

Detailed work breakdown structure (WBS)

B.

Lessons learned from previous projects

C.

Baselines approved by the project team

D.

Actual data from the current project

Buy Now
Questions 38

While performing risk identification exercises, the risk manager often encounters biases from the project team. How can the risk manager accurately identify what will trigger a risk?

Options:

A.

Remind the project team to keep an open mind

B.

Review the results with the project manager afterward

C.

Review published operational experience reports

D.

Use the mean answers provided by the project team 

Buy Now
Questions 39

A risk manager documents the causes in the risk register and needs to ensure the risk is adequately described. What is critical for the risk manager to consider when describing the causes?

Options:

A.

Each cause has a degree of uncertainty

B.

Each cause has well defined owner

C.

The causes represent actual conditions

D.

The causes must be validated by the risk owner

Buy Now
Questions 40

.

A project manager is identifying risks on a project and decides to use a risk checklist to gather historical data accumulated from similar projects. With several different historical project files to choose from, which two pieces of information should the project manager include in their risk checklist? (Choose two.)

Options:

A.

Budget variance data from previously completed projects.

B.

Project scope and cost management plans from previous projects.

C.

Lessons learned from similar completed projects.

D.

Previous project risks that may be relevant to this project.

E.

Stakeholder analysis metrics from projects with similar risk profiles.

Buy Now
Questions 41

A Scrum team has recently lost its product owner to another team. A new product owner has been hired for the Scrum team. This product owner is currently new to the project, unfamiliar with the team ' s practices, and does not have a full grasp of the product users. After a few sprints, the product owner is receiving constructive feedback from both internal and external stakeholders related to the direction of the product and its current challenges.

What can the product owner do to improve the product ' s perception among stakeholders and ensure the team understands the product vision? (Choose 2)

Options:

A.

Re-assess the product goal, place it on the product backlog, and explain it to the team.

B.

Invite more stakeholders to the daily scrum meetings to voice their opinion of the product.

C.

Create sprint goals and communicate them at the sprint planning event.

D.

Invite product teams to more frequent reviews to observe the team ' s work and encourage feedback.

E.

Invite stakeholders to the sprint retrospective to brainstorm with the team improvements.

Buy Now
Questions 42

it typically takes 5 hours to perform a complete home inspection. If there are unforeseen risk factors, it can take up to 7 hours to finish the inspection. The earliest the project team has ever finished an inspection is in 3 hours.

Using the project evaluation and review technique (PERT) to estimate duration how many hours should the project manager plan to schedule the task taking into account all the positive and negative risk factors?

Options:

A.

4 hours

B.

5 hours

C.

6 hours

D.

12 hours

Buy Now
Questions 43

The project manager performed ' a variance analysis on the project during the execution phase. The variances were shown as increasing

What does this result imply?

Options:

A.

The uncertainty and risk are increasing.

B.

The project schedule is lagging behind.

C.

There is no potential for future deviation.

D.

The project is over budget.

Buy Now
Questions 44

Some engineers are completing an activity that will alert the project team if there is a risk of requiring additional effort to complete the project. What should the risk manager do in case the trigger arises?

Options:

A.

Activate the contingency plan.

B.

Request a reserves increase.

C.

Add the alert to the risk register.

D.

Update the risk response plan.

Buy Now
Questions 45

Several key stakeholders approach the project manager with concerns. The stakeholders have received feedback from local businesses that have reported a reduction in customers because of construction activities at the worksite, and they plan to submit a claim to the municipality to fine the project manager ' s company.

How should the project manager address this concern?

Options:

A.

Evaluate the risk with the team and update the issueing

B.

Discuss the concern with the local business owners.

C.

Update the key risks and perform a quantitative risk analysis.

D.

Adjust construction work hours to after business hours.

Buy Now
Questions 46

A project manager is assigned to a new project and is told they need to develop the project ' s risk register. When should the project manager identify the project risks?

Options:

A.

Identify risks only at the project ' s midpoint for the stakeholders to review them

B.

Ensure project team members proactively identify risks throughout the project to plan for possible response strategies

C.

Identify risks at the beginning of the project because the risk posture will not change

D.

Delegate risk identification to each team member and have them record the risks on separate risk registers for their areas

Buy Now
Questions 47

A project manager of an IT company is assigned to a project whose schedule may be delayed due to a lack of resources to conclude the backlog activities. The project manager decides to hire additional developers to reduce the project ' s technical debt and meet the project deadline.

What should the risk manager advise the project manager to do to address this situation?

Options:

A.

Immediately hire as soon as the project begins to fall behind schedule.

B.

Hire as soon as the project metrics trigger a risk response.

C.

Only hire when it is economically feasible to do so.

D.

Only hire if risk response is escalated and approved by the stakeholders. 

Buy Now
Questions 48

A risk manager of a major project facilitates a meeting to develop the risk management plan. What two factors does the risk manager need to consider to ensure an effective risk management plan is developed? (Choose two.)

Options:

A.

Applying modern risk management techniques.

B.

Aligning to project constraints and priorities.

C.

Ensuring risk response strategies mitigate all risks.

D.

Minimizing implementation costs.

E.

Obtaining stakeholder acceptance

Buy Now
Questions 49

As per the risk analysis process carried out for a project, two risks are registered. The probability risk A will occur is 40% and its monetary impact to the project is US$100,000. The probability risk B will occur is 60% and its monetary impact to the project is US$20,000.

What is the total contingency budget that should be created?

Options:

A.

US$68,000

B.

US$52,000

C.

US$120,000

D.

US$80,000

Buy Now
Questions 50

Towards the end of definitive design, project costs have increased to the point where it will be classified as a capital asset project. The customer has expressed they want one final total project completion date and will afford no extensions after it is established.

How should the risk manager proceed?

Options:

A.

Perform a qualitative risk analysis and update the results.

B.

Update the assumptions/exclusions register with the new information.

C.

Update the risk register and prepare for the Monte Carlo analysis.

D.

Perform a quantitative risk analysis and update the results.

Buy Now
Questions 51

During the monthly executive review meeting, the project sponsor would like to understand how the project team has planned to manage risks that were identified in the last meeting. What should the project manager do?

Options:

A.

Utilize a Monte Carlo assessment to provide risk related impacts.

B.

React to the secondary and residual risks only if they occur.

C.

Include secondary and residual risks as part of the response.

D.

Transfer secondary and residual risks to the project sponsor.

Buy Now
Questions 52

A risk manager for a financial organization is assigned to support a project team in developing a custom software solution to manage loans. Which document should the risk manager request first from the project sponsor to identify major risks?

Options:

A.

Risk management plan

B.

Clients ' credit scores

C.

Organization ' s mission and vision

D.

Historical data from the credit portfolio

Buy Now
Questions 53

A risk manager is tasked with establishing a risk management strategy for a multinational project with varying regulations and stakeholder priorities. The team is divided on how to approach risk management. Some suggest implementing rigid procedures to ensure consistency across regions, while others advocate for a flexible approach to adapt to the dynamic nature of local risks. Meanwhile, the sponsor emphasizes the need for a strategy that aligns with the overall project objectives.

What should the risk manager do?

Options:

A.

Implement a strict, standardized approach to ensure consistency across all regions.

B.

Develop a strategy combining structure with flexibility to address global and local uncertainties.

C.

Use organizational guidelines to create a strategy that prioritizes efficiency over adaptability.

D.

Adopt a fully flexible approach that allows teams to manage issues based on local context.

Buy Now
Questions 54

A project manager identified a risk of communication issues with the client which may impact the project schedule. A member of (he sales team advises that this client prefers face-to- face conversations.

What should the project manager do to avoid this risk?

Options:

A.

Record this risk and the clients preference in the risk register.

B.

Ask the sales person to lead the communication with the client

C.

Call the client and advise that online communication is easier and faster.

D.

Meet the client and plan tor critical milestone meetings.

Buy Now
Questions 55

After the initial assessment of a new project, a project manager found that in order to complete the expected results, detailed and exhaustive planning will be required to ensure the product ' s characteristics and quality. What should the risk manager propose to the project manager what to do?

Options:

A.

Use a predictive approach for the delivery.

B.

Use a hybrid approach for the delivery.

C.

Use an adaptive approach for the delivery.

D.

Use an agile approach for the delivery. 

Buy Now
Questions 56

Upon reviewing the risk analysis results, the project manager notices several risks that occur more frequently than others. What should the project manager do?

Options:

A.

Reduce the probabilities of those risks on the risk register

B.

Transfer ownership of those risks to the customer

C.

Implement the risk handling strategies for those risks

D.

Request additional management reserve for those risks

Buy Now
Questions 57

In a large mobile network deployment project, there is delay risk due to insufficient staffing. The risk manager is considering executing a response plan, which involves allowing staff members to work overtime. However, this action may lead to excessive additional cost.

What should the risk manager do?

Options:

A.

Document the concern over the potential excessive additional cost.

B.

Manage the potential excessive additional cost as a new risk.

C.

Ensure the project sponsor has the risk appetite for the residual risk created by allowing overtime.

D.

Prepare a detailed response plan for the residual risk with a clear owner and time line to ensure there are no impacts to the project. 

Buy Now
Questions 58

A risk manager has been assigned to prepare a risk management plan for a new project. Which factor should the risk manager prioritize when tailoring the risk management processes for the new project?

Options:

A.

Available funds for risk management activities

B.

Size and duration of the project

C.

Maturity of the organization ' s risk management processes

D.

Number of stakeholders associated with the project

Buy Now
Questions 59

 

One project in a program needs to be completed in 6 months because there is a large bonus for early completion. Consequently, the program manager transfers all resources to this project and arranges for employees to receive overtime pay.

Which risk response strategy is the program manager using in this scenario?

Options:

A.

Escalate

B.

Transfer

C.

Enhance

D.

Exploit 

Buy Now
Questions 60

During a project ' s planning phase, the project team identifies a potential supplier delay and marks it as a significant risk. A risk manager is tasked with effectively monitoring this risk.

What should the risk manager document as the risk trigger?

Options:

A.

The probability and impact rating of the supplier ' s delay on the project

B.

The response strategy, such as increasing inventory or finding an alternative supplier

C.

The specific event or condition, such as the supplier missing a delivery deadline

D.

The threshold for acceptable delay, such as a maximum of three days before impacting project milestones

Buy Now
Questions 61

The project manager asks the risk manager to determine the initial risk assessment for a six month initiative that is about to kick-off. Which two artifacts will help the risk manager conduct the related analysis? (Choose two.)

Options:

A.

Work breakdown structure (W & S)

B.

Project organizational chart

C.

Configuration management plan

D.

Brainstorming

E.

Monte Carlo analysis

Buy Now
Questions 62

A risk manager for a cross-functional project is initiating the risk identification process. The risk manager conducted some meetings for stakeholders to express their concerns, but some stakeholders are complaining that their opinions were not considered.

How should the risk manager address these concerns?

Options:

A.

Refer to the requirements documentation to confirm stakeholder requirements as they relate to risks.

B.

Refer to the project charter to find guidelines and stakeholder communication channels.

C.

Review the stakeholder register and stakeholder engagement plan to communicate and solicit stakeholder input.

D.

Rewrite the risk register to include the additional possible risks and inform the stakeholders.

Buy Now
Questions 63

A project manager is working on a complex construction project. During the risk identification process, hundreds of risks were identified. The team seems to be confused regarding on which risks to focus. The project manager advises the team to go ahead and start assessing the likelihood and impact of each risk.

What process is this part of?

Options:

A.

Plan Risk Management

B.

Perform Qualitative Risk Analysis

C.

Perform Quantitative Risk Analysis

D.

Monitor and Control Risk

Buy Now
Questions 64

During the design phase the project team is exploring various architecture options. After reviewing the results of design pilot, two conflicting infrastructure pieces were identified.

What action should the project manager take?

Options:

A.

Reassess the design for the two pieces.

B.

Escalate the situation and request approval to move forward.

C.

Confirm the results through a second pilot.

D.

Update the assumptions log and assess the risk associated with it.

Buy Now
Questions 65

A risk manager administered a pre-workshop risk survey in preparation for the upcoming workshop. The workshop invitees participated in the survey and submitted many risks encompassing all project phases and risk areas. The risk manager sorts risks by similarities and categories for the workshop.

What should the risk manager do next to visually organize the risks?

Options:

A.

Develop an affinity diagram

B.

Perform the analytical hierarchy process

C.

Perform a SWOT analysis

D.

Assign probability and impact

Buy Now
Questions 66

The project team recorded a risk in the risk register indicating that weather-related delays may impact equipment delivery during project execution. When it is time to request the equipment shipment there is bad weather, but the client wants the equipment delivered anyway.

What should the project manager do?

Options:

A.

Wait until the weather improves before sending the equipment.

B.

Ask the project sponsor to approve shipping the equipment.

C.

Proceed with the planned risk response to move the equipment.

D.

Request the shipment of the equipment to satisfy the client.

Buy Now
Questions 67

A project team identifies that there is a probability of missing a key milestone in a project. The team wants to move forward with the risk response planning.

What should the risk manager complete first?

Options:

A.

The risk categorization

B.

The risk simul-ation

C.

The full risk description

D.

The risk response plan

Buy Now
Questions 68

The project manager is reviewing the lessons learned from a previous similar project. The previous project was delayed due to the delay in delivery of a gas turbine generator (GTG). Construction of the previous project had to be shut down unexpectedly to wait for the late delivery of the GTG.

What should the project manager do first?

Options:

A.

Include the risk in the register and communicate with the stakeholders.

B.

Communicate with the client to provide the previous shutdown plan.

C.

Review and update the project schedule.

D.

Interview the other project manager to learn more details.

Buy Now
Questions 69

A project manager works on a long-term and high visibility project at an organization that has a low risk appetite towards this project due to its impact on the company ' s business. The project sponsors follow up weekly with the project manager, who was just informed by one of the risk owners that the exposure from two high-impact risks are hitting the risk thresholds.

What should the project manager do next?

Options:

A.

Update the project management plan to add contingency.

B.

Perform an assumptions and constraints analysis.

C.

Complete an assessment and confirm the response with the sponsors.

D.

Implement mitigation measures for those risks.

Buy Now
Questions 70

A project manager is working on a construction project. Based on past experience, the project manager identifies a risk that a supplier of a critical material may not deliver on time. The project manager has already accounted for this risk in the risk management plan. If this risk materializes, the project manager plans to procure the material from a different supplier. A potential risk in this plan is that there may be differences in the material provided by the first and second supplier.

What type of risk is this?

Options:

A.

Residual risk

B.

Primary risk

C.

Secondary risk

D.

Normal risk

Buy Now
Questions 71

Which statement describes the risk portrayed on the risk matrix heat map below?

Options:

A.

The risk has a probability of 60% of occurrence and a medium impact rating.

B.

The risk has a probability of 40% of occurrence and a high impact rating.

C.

The risk has a high impact and probability of occurring.

D.

The risk has a low probability and high impact rating.

Buy Now
Questions 72

A project manager has requested a risk manager facilitate risk identification on a project. While facilitating this effort, the project manager wants to ensure that stakeholders interact and provide their expertise so that an exhaustive list of risks is created.

Which risk identification technique should the risk manager use?

Options:

A.

Prompt lists

B.

Interviews

C.

Delphi technique

D.

Nominal group technique

Buy Now
Questions 73

A project is in progress when the product team requests a change to the scope. The team indicates that this is a minimal change and should not create any problems.

What should the risk manager do next?

Options:

A.

Update the work breakdown structure (WBS).

B.

Analyze any potential impact.

C.

Escalate the issue to management.

D.

Add a new risk to the risk register.

Buy Now
Questions 74

A project team has just completed a project plan, which includes extra days for most of the critical activities to cover any possible issues. Stakeholders want to remove these additional days, because the end date is longer than expected.

What should the risk manager do first?

Options:

A.

Remove the activity padding.

B.

Review the risk response plan.

C.

Update the risk contingency plan.

D.

Update the schedule constraints. 

Buy Now
Questions 75

During the construction of a housing development, a project team realizes they exceeded their materials budget during the first of three execution stages. The risk manager observed that the team did not notice that the cost of the materials increased due to continuous inflation in the steel market.

What could have been done during project planning to avoid overspending?

Options:

A.

Met weekly with the finance team to monitor the cost

B.

Communicated with the stakeholders that the project costs might increase

C.

Properly documented the triggers and actions for the risk

D.

Engaged with the sponsor to buy the steel in advance of the project 

Buy Now
Questions 76

During project development, a risk manager notices that a major update in the country ' s regulations might be happening in the upcoming months. These changes will affect the materials used in building some of the components of the final product. The project team is unsure if this risk will affect the project negatively or positively.

Which tool should the project team use to determine this?

Options:

A.

Sensitivity analysis

B.

Threshold analysis

C.

Reserve analysis

D.

Strengths, weaknesses, opportunities, and threats (SWOT) analysis 

Buy Now
Questions 77

An organization performs an annual strategies and initiatives workshop during which a strengths, weaknesses, opportunities, and threats (SWOT) analysis is being conducted. As part of this process the functional managers identify the opportunities and threats.

What should the risk manager do next?

Options:

A.

Add only the threats to the risk register

B.

Utilize different tools to identify the risks

C.

Plan risk responses to the threats

D.

Update the risk register with the identified risks

Buy Now
Questions 78

A project with impending risks has 12 deliverables as subprojects, which will be executed in three different locations involving multiple stakeholders. What should the risk manager do to organize the prevailing risks?

Options:

A.

Combine individual and focus groups to identify risks and create the overall risk register.

B.

Use focus groups to conduct group risk assessments of the project to identify risks.

C.

Request individual assessments of the project and its deliverables to identify risks.

D.

Use the external risk assessment of the project and its deliverables to identify risks.

Buy Now
Questions 79

The risk manager for a large-scale software development project with a tight deadline and multiple stakeholders highlights concerns about potential delays, communication gaps, and vendor reliability. During the early stages of the project, the project sponsor requests that the risk manager identify and address any potential risks that could disrupt project delivery.

What should the risk manager do?

Options:

A.

Create a list of potential issues.

B.

Consult the project management plan.

C.

Conduct risk management exercises.

D.

Perform qualitative risk analysis.

Buy Now
Questions 80

An IT project is 40% complete. During the initial analysis, risks A and B were identified for the project. Risk A has a probability of 0.6 and an impact of US$50.000. Risk B has a probability of 0.7 and an impact of USS60.000. After implementing the planned risk response for risk B. the probability of risk B has been reduced is 0.3.

What is the current project risk exposure?

Options:

A.

US$18,000

B.

US$72.000

C.

US$30,000

D.

US$48,000

Buy Now
Questions 81

A project manager for a predictive project just received a scope change request where additional development is required. What should the risk manager do to support the project manager with this scope change request?

Options:

A.

Evaluate any new risks that are introduced due to the change in scope.

B.

Update the risk management plan to reflect the scope change.

C.

Reassess the identified risks that impact the project scope.

D.

Update the risk register to identify, analyze, and plan a response for any new risk.

Buy Now
Questions 82

An organization faces immense competition in the market and decides to accelerate a key project. What is the first action for the project risk manager to take?

Options:

A.

Update the risk register

B.

Meet with the project ' s stakeholders

C.

Revise the risk management plan

D.

Ensure sufficient resources are available

Buy Now
Questions 83

During a brainstorming session, a stakeholder identifies a risk that, if realized, could greatly impact their team. The stakeholder insists that this particular risk should be

mitigated to the greatest extent possible, however, the majority of other stakeholders feel that different risks have higher probabilities of occurring.

Which action should the risk manager take to address this risk?

Options:

A.

Accept the identified risk because other stakeholders feel that there are higher priority risks to address.

B.

Mitigate the identified risk in order to reduce the probability of impacting the stakeholder ' s team.

C.

Escalate the identified risk to the project sponsor and allow them to determine the best course of action.

D.

Add the identified risk to the risk register for future probability and impact analysis.

Buy Now
Exam Code: PMI-RMP
Exam Name: PMI Risk Management Professional (PMI-RMP) Exam
Last Update: Apr 14, 2026
Questions: 278
$57.75  $164.99
$43.75  $124.99
$36.75  $104.99
buy now PMI-RMP