In a large mobile network deployment project, there is delay risk due to insufficient staffing. The risk manager is considering executing a response plan, which involves allowing staff members to work overtime. However, this action may lead to excessive additional cost.
What should the risk manager do?
A newly assigned risk manager realizes that a project has unrealistic funding and low resources. Which document should the risk manager review?
A risk manager has been assigned to an upcoming project. A senior risk manager within the organization recently completed a similar project and has provided a lessons learned document to aid planning efforts for the upcoming project. Upon reviewing the document, the risk manager discovers that the completed project was delivered several months behind schedule and several thousands of dollars over budget. The root cause was determined to be an unforeseen risk trigger that caused several items to be reworked, creating cascading schedule delays and depleting management reserves.
What should the risk manager do to mitigate the chance of the same issues reoccurring?
While implementing the risk response plan for a previously identified risk, some secondary risks were identified but not captured on the risk register. The project manager decided to review the risk management plan to ensure this does not happen for future, similar situations.
What should the project manager do next?
A risk manager wants to determine what risk has the biggest impact on project cost. The risk manager identified three risks, which could occur in different phases of the project.
What should the risk manager do first to understand the impact on project cost?
As a project approached completion, a risk manager conducted a risk response audit and verified the effectiveness of risk responses. What should the risk manager do next?
A project team does not understand why a very low probability risk occurred during project execution. The team was especially vigilant about planning for this type of risk during the risk planning phase. The project has been delayed by 2 months, and the stakeholders are considering canceling the project. The risk manager needs to demonstrate that the project can be concluded.
Which analysis should the risk manager perform to demonstrate this to the stakeholders ' ?
A risk manager and project team are managing a software system project, which is expected to be completed within 12 months. The project is currently halfway through, and the team has just delivered the second version of the prototype. During the weekly status meeting, a team member reported that an important stakeholder is facing an issue, which will likely result in a change request that is outside the scope of the current prototype.
What should the risk manager advise the team to do first?
in a complex and critical project, a sponsor asks the risk manager to determine where the project ' s concentration of risks is greatest by performing a quantitative risk analysis. There are no organizational process assets (OPAs)s about the risk categories.
Which tool could the risk manager use to discover the project risk categories?
A risk manager for a large project has completed documenting the risk management plan. The project is moving from planning to execution.
Which three actions should the risk manager take to ensure the risk management plan remains effective during the project timeframe? (Choose 3)
A project team is developing a software system for a financial organization and is conducting a failure modes and effects analysis (FMEA) to identify and evaluate potential failure points. The risk manager must guide the team on how to prioritize risks based on FMEA results for effective risk management.
What should the risk manager do?
A financial services company has implemented a risk response plan to mitigate potential cybersecurity threats. The project team has conducted a series of tests to ensure the new security measures are effective. However, some executives have expressed concerns about the impact of these measures on daily operations.
What should the risk manager do?
A project manager has requested the risk manager ' s support in deciding whether to purchase a new component to expedite project execution. The component price is US$100,000 and there is a 30% chance that it might not function as expected resulting in an additional US$50,000 cost However, if the component does work well the project will make a profit of USS500.000. If the component is not purchased, there is an 80% chance of failure with an impact of US$250 000.
What should the risk manager recommend?
A risk manager is integrated into a team overseeing a crucial software development project. During the information gathering phase, the risk manager notices significant weaknesses in the maturity of the risk management process. The team needs to establish a more structured approach to managing risks, including the documentation of strategies, ownership structures, and details about the organization ' s project risk baseline.
What should the risk manager do?
A key project is delayed and all contingency reserves have been used even though the project team has implemented all planned risk responses. What should the risk manager do next?
During project implementation, a risk manager wants to determine the effectiveness of risk response plans and which risk will have an impact on the project outcome. Which analysis should the risk manager do?
A risk manager was recently hired to assist with a mid-sized infrastructure project. The risk manager becomes aware that they have an inexperienced project team.
What two items should the risk manager have their team review in order to prepare for an upcoming risk identification workshop? (Choose two.)
A new risk manager has been assigned to a project experiencing delays, quality issues, low performance, and client complaints. The work is being completed with the
client ' s vendor, which apparently has been causing all of the issues.
What should the risk manager do first?
One project in a program needs to be completed in 6 months because there is a large bonus for early completion. Consequently, the program manager transfers all resources to this project and arranges for employees to receive overtime pay.
Which risk response strategy is the program manager using in this scenario?
A project manager has determined that an activity is too complex to complete internally so they hire a licensed contractor to complete the work. What is the project manager performing in this situation?
A project manager wants to work on understanding the project risks. The project manager works with the integrated project team to develop the risk handling strategies for the identified risks.
How should the project manager work with these risk handling strategies?
A project team has completed the risk identification steps in a project and compiled a list of 25 risks. The team wants to create response plans for all the risks to avoid any future issues, but the resources and constraints limit the options.
What should the risk manager do?
During a risk reassessment workshop with the project team and some external stakeholders, two key external stakeholders are overemphasizing the impact of a few project risks. This has led to a conflict.
How should the risk manager handle this situation?
During project development, a risk manager notices that a major update in the country ' s regulations might be happening in the upcoming months. These changes will affect the materials used in building some of the components of the final product. The project team is unsure if this risk will affect the project negatively or positively.
Which tool should the project team use to determine this?
A risk manager of a complex project has identified a risk and believes a deeper understanding of the source and likelihood is necessary. How should the risk manager proceed?
During the design phase the project team is exploring various architecture options. After reviewing the results of design pilot, two conflicting infrastructure pieces were identified.
What action should the project manager take?
A technology company is in the final stages of an IT system implementation project. As part of ongoing risk monitoring, the risk manager reviews current risk levels and identifies significant changes in the external regulatory environment that may affect project delivery.
What should the risk manager do next?
There is confusion among risk action owners on a project about when and under which conditions they should initiate risk responses. Project team members often need to consult with the risk manager to get this conflict resolved.
What should the risk manager do to resolve this recurring situation?
Multiple new risks have come up on a project that were not included on the risk register. The project manager met with the team to explain that risk management is critical for the success of the project, and risk identification is key.
What should the project manager do next?
A project manager has just been assigned to a new project. The project manager has been tasked by the project sponsor to ensure the project risks are closely managed. The project manager starts with developing the risk management plan.
What is the expected outcome of developing the risk management plan?
A risk manager is preparing for the first meeting with their project sponsor on a potential project for a large client. The risk manager reviews their newly developed project risk register to identify any risks that should be analyzed further and begins by prioritizing the probability column based on the following criteria:
1 = Very Low
2 = Low
3 = Medium
4 = High
5 = Very High
What type of risk analysis is the risk manager performing?
The project manager is reviewing the lessons learned from a previous similar project. The previous project was delayed due to the delay in delivery of a gas turbine generator (GTG). Construction of the previous project had to be shut down unexpectedly to wait for the late delivery of the GTG.
What should the project manager do first?
A company manages confidential customer information, and a data breach exposing sensitive information was discovered. What should the risk manager do?
A company has been awarded a large government contract to develop a new transportation system. There is uncertainty surrounding the project ' s timeline. The project team is struggling to finalize the project ' s budget due to unclear estimates from vendors. An updated vendor price list detailing the costs of available technologies is an essential component in determining the project ' s final cost. The project team will not be able to finalize the project ' s timeline until the budget is finalized.
What should the risk manager do?
There is a debate within the organization on whether projects need to be agile or waterfall. Some agile terms and principles are understood differently by the key stakeholders, and this delays the decision-making process.
The project manager for project X was expecting the mobilization of critical equipment from another project, project Y. However, a day before the mobilization was scheduled, another project manager notifies project X ' s project manager that the equipment would not be available for at least another month due to delayed activities for project Y. This has jeopardized meeting a critical milestone for project X.
How should project X ' s project manager avoid this situation in the future?
An external vendor needs to be contracted to provide additional capacity and expertise to a project team to reduce the probability of delays in a project. The contracts department is raising a concern about confidentiality risks not addressed in the proposed contract and missing from the risk register.
What should the risk manager do next?
A risk manager manages risks in a construction project. A stakeholder mentions that if there is less than a 50% chance of rain, construction should continue. Another stakeholder says that if there is less than a 60% chance of rain, construction should continue.
What should the risk manager do next to find out the correct limit?
A project manager is trying to realize benefits from new material on an adaptive project. This is the first time the project team is using the material so the team does not have information to identify and analyze risks. A team member informs the project manager that a local university has recently published a research journal on the same material.
Where should the project manager find this information?
During a complex infrastructure project, the team successfully mitigated a risk related to equipment failure. However, the mitigation strategy resulted in a secondary issue due to the use of alternative machinery.
What should the risk manager do?
Some project risks are applicable for the project ' s lifecycle while others risks are only applicable to specific project activities. When should project risks be closed?
The sponsor of a construction project is upset about the results of the risk management team. The sponsor believes the team did not properly identify the risks that could affect the project. The team did manage the risks; however, some of the risk response strategies created secondary risks.
What should the risk management team have done to manage this situation?
The major investor in a road construction project is constantly asking project team members for information about the project ' s execution. This has resulted in the project team working 20% of their day preparing project reports for the stakeholders.
What should the risk manager do to enhance the project team ' s approach to risk reports?
During the risk management planning, key stakeholders recommend adding more factors other than probability and the impact to refine the score of prioritized threats in subsequent iterations of the qualitative risk analysis. The stakeholders ask the risk manager to prepare a list to discuss this further.
Which three valid factors should the risk manager prepare on the list for discussion? (Choose 3)
After completing the risk register, many team members feel there is a lack of time prioritization for one of the identified risks What are the team members referring to?
The risk manager loaded the risk register, built the risks into the simul-ation software, and ran the Monte Carlo analysis. The P80 and P90 end dates are the same as the deterministic date.
What should be the risk manager ' s next step?
A project manager is developing the risk register and works with the team to analyze risks and determine their probability and impact. There is valuable historical data available that may be used to simulate the overall risk outcome.
Which type of analysis should the project manager use in this instance?
The project director and project manager have met with the board and determined that the project has depleted the entire contingency reserve and has started eroding the profit margin.
The project manager would like the risk manager to take full advantage of opportunities.
Which response should the risk manager take?
A project team is discussing which risk requires more attention and resources for response planning. The team evaluated the schedule to determine which activity had the greatest impact on the project ' s total duration.
After analyzing the quantitative analysis results, which activity should the team pay more attention to?
Use the chart for the analysis.
The risk manager is facilitating risk planning activities with the team. The team is documenting all the check points along the way that might indicate delays on critical deliverables.
What is this an example of?
A project has consistently been lagging in cost performance index (CPI) and schedule performance index (SPI) over the past few months. The risk manager realizes that some activities are taking longer than expected and more resources are needed.
Which project artifact should the risk manager analyze to mitigate the risk of further project overrun?
A complex project that had hundreds of risks is almost done. The project manager is closing the risks as part of the closing process. One team member mentions that there are important documents to be updated.
Which document will need to be updated?
During a project ' s planning phase, the project team identifies a potential supplier delay and marks it as a significant risk. A risk manager is tasked with effectively monitoring this risk.
What should the risk manager document as the risk trigger?
A project manager is assigned to a new project and is told they need to develop the project ' s risk register. When should the project manager identify the project risks?
During project planning, a risk is identified for which the risk manager has defined a mitigation strategy. Later during project execution, this risk still leaves substantial residual risk.
What should the risk manager do to handle this situation?
A risk manager is working on the risk management plan for a new digital platform and realizes the project sponsor, who is the IT manager, has not been invited to the project team meetings. The IT manager is concerned that the IT infrastructure is unable to host the new platform the team is creating. The risk manager asks the IT manager to be included in the meetings.
What should the IT manager ' s role be in the project team meetings?
Towards the end of definitive design, project costs have increased to the point where it will be classified as a capital asset project. The customer has expressed they want one final total project completion date and will afford no extensions after it is established.
How should the risk manager proceed?
After presenting a list of risks to the major project stakeholders and project sponsor, the board requested the risks be sorted differently from the results presented by the project team. This is a major issue and will cause a 2-week delay in the project.
How could the risk manager have avoided the board ' s response?
While planning for project execution phase stakeholders are making decisions on how to respond to known and new risks. What artifact should the stakeholders prepare?
A project manager has determined that they cannot outsource work nor eliminate the scope. They also discover that they cannot buy insurance or mitigate the risk.
What should the project manager do?
A project manager managing a high-risk rating project was just informed that one of the key project resources has decided to leave the organization. The project manager asks the risk manager for their recommendations. The risk manager previously identified this as a risk and had created a transition plan to enable another resource to carry out the same duties. The risk manager was informed that by transitioning the responsibilities to the new resource, new risks to the completion dates of other project-related tasks appear.
What should the risk manager advise the project manager?
An organization faces immense competition in the market and decides to accelerate a key project. What is the first action for the project risk manager to take?
A project team in a multinational organization is working on a risk management plan for a multimillion-dollar project. This project involves three global regions with a wide range of critical stakeholders with varying degrees of risk appetite.
What should the risk manager advise the project team to do?
A project team is presenting a delivery plan to a client. Some of the client ' s experts do not feel comfortable with some activities at a critical stage. The experts ask to change the plan and present a better alternative.
What should the risk manager do first?
A newly appointed risk manager for a critical project is working with a project team to develop a risk management strategy. One team member suggested creating an influence diagram to help analyze the options, risks, outcomes, and their relationships. Another team member feels the influence diagram is not enough because this project is important and complex.
Which approach should the risk manager take to improve the quality of the project risk analysis?
A risk manager administered a pre-workshop risk survey in preparation for the upcoming workshop. The workshop invitees participated in the survey and submitted many risks encompassing all project phases and risk areas. The risk manager sorts risks by similarities and categories for the workshop.
What should the risk manager do next to visually organize the risks?
A project manager is working on a complex construction project. During the risk identification process, hundreds of risks were identified. The team seems to be confused regarding on which risks to focus. The project manager advises the team to go ahead and start assessing the likelihood and impact of each risk.
What process is this part of?
After the initial assessment of a new project, a project manager found that in order to complete the expected results, detailed and exhaustive planning will be required to ensure the product ' s characteristics and quality. What should the risk manager propose to the project manager what to do?
A project team is concluding the first monthly meeting on a new engineering project, with regular review of project risks. Which document should the risk manager update to reflect the risks ' current status?
A risk manager is reviewing documentation for a project following a risk planning workshop with project stakeholders and team members. Several items have been identified on the risk log that would be detrimental to project success, but the associated triggers cannot be managed by the organization and are unlikely to occur.
Which response should the risk manager recommend for these risk items?
A risk manager has been assigned to a project in a company that is undergoing a significant cultural and organizational change. The risk manager will start planning risk management. activities with stakeholders but is unsure with whom to engage.
What should the risk manager do?
A risk manager has been assigned to a project constructing a chemical laboratory. Unfamiliar with chemical laboratories, the risk manager is unsure of where to start objectively identifying risks.
What should the risk manager do?
A new vice president in one of its divisions observed that the portfolio of projects within their division experienced significant variations beyond the ±10% established threshold with the potential of not achieving its overall business goals. Hence, they directed all project leaders and sponsors to ensure that they set and work toward more stringent thresholds of ±5% and reports on the basis of any variance outside that range.
How should the risk manager respond?
What is an example of legal and regulatory requirements and/or constraints when assessing a project environment for threats and opportunities?
A risk manager completed risk response planning for a project that is currently in the execution phase. During a periodic review of the risk register, the project manager recognizes that some key secondary risks have not been considered.
Who should the project manager hold accountable for missing the risks?
A nonprofit organization is working on a project to deliver a fundraising concert event. The concert is only a few weeks away, and the project team has completed revising the risk processes when an opportunity is identified. The key stakeholders want to capitalize on it.
What should the risk manager do?
The project team has correctly identified, assessed, and planned responses for a project ' s risks. The risk manager is required to prepare a quarterly report on the performance of managing the risks.
What are two options the risk manager should consult for the analysis? (Choose two.)
Product testing can be done in multiple ways. A few project team members suggest testing be done in a laboratory environment, whereas others recommend completing the analysis via simu-lation methods. The testing manager has consulted with a peer, who recommends undertaking testing using field trials. The testing manager consults with the risk manager to assess the risk involved in the testing.
Which tool should the risk manager consider for assessing the test risk?
A project manager is working on a high priority and high profile project. The project team had identified three opportunities, and after analysis, risk responses were recorded. Although risk responses were adequate for the identified opportunities, two of those opportunities were not acted upon. During the risk audit, the project manager found out that several of the planned risk responses were not implemented.
What should the project manager have done to avoid this?
A project is In the initiation phase. The project stakeholders are Invited to a meeting to share their thoughts that may impact the project In a positive or negative way.
What will be the main output of this meeting?
A two-year project with a budget of US$2 million has completed about 60% of the work at the end of the first year. The actual cost incurred to complete the remaining 40% of work is about USS1.5 million. As a part of performing a specialized risk analysis, the calculated schedule performance index (SPI) is 1.2 and cost performance index (CPI) is 0.53.
How should the risk manager interpret such a low CPI value?
In a large industrial business, an on-going system development project faces a previously identified risk. The risk is adequately managed by the risk manager, however there is still residual risk.
What should the risk manager do?
Some issues and unexpected results were found after completing the first phase of a project. The project team is planning the next phase and team members want to avoid the previous issues.
What should the risk manager do to avoid the previous issues?