Labour Day Sale - Limited Time 60% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 575363r9

Welcome To DumpsPedia

PMI-SP Sample Questions Answers

Questions 4

Jenny is the project manager for her organization. Her project is not doing well on project schedule performance, and management wants her to predict how the project schedule and cost will end. Management has asked Jenny to report and forecast her project's performance based on the Judgmental methods. Which of the following judgmental methods will Jenny use to accomplish the task? Each correct answer represents a complete solution. Choose all that apply.

Options:

A.

Forecast by analogy

B.

Technology forecasting

C.

Autoregressive moving average

D.

Scenario building

Buy Now
Questions 5

Your project team has identified a project risk that must be responded to. The risk has been recorded in the risk register and the project team has been discussing potential risk responses for the risk event. The event is not likely to happen for several months but the probability of the event is high. Which one of the following is a valid response to the identified risk event?

Options:

A.

Risk audit

B.

Technical performance measurement

C.

Earned value management

D.

Corrective action

Buy Now
Questions 6

Alicia works as a project manager for NacTec project. She is undergoing the project monitoring phase in her project. Which of the following will she choose to accomplish the task? Each correct answer represents a complete solution. Choose all that apply.

Options:

A.

Reports

B.

Meetings

C.

Diaries

D.

Future planning

Buy Now
Questions 7

Della works as a project manager for BlueWell Inc. She has asked her assistant Beth to provide activity duration estimate for an activity. Beth provides Della the following estimate chart:

What will be the activity duration according to the PERT three-point analysis?

Options:

A.

19

B.

24

C.

29

D.

46

Buy Now
Questions 8

Fill in the blank with an appropriate phrase. The _______contains the schedule components and the rules for relating and using the components to represent the process for completing a project.

Options:

Buy Now
Questions 9

Andy is the project manager of the NHGQ project for his organization. He has elected to use a three-point estimate for his project. His project team, however, is complaining about participating in this estimate type because of the time it takes to predict the duration of activities. Andy, as the project manager, tells the project team that they must create the time estimate, as it will help this project and future similar projects. What is a three-point estimate?

Options:

A.

Each activity must be estimated for its optimistic, pessimistic, and most likely duration.

B.

Each activity must be estimated for its optimistic, pessimistic, and most likely duration and then an average for the estimate is created.

C.

A three-point estimate, also known as PERT, uses the formula optimistic, plus four times the most likely, plus the pessimistic. This value is then divided by six.

D.

A three-point estimate, also known as GERT, uses the formula optimistic, plus four times the most likely, plus the pessimistic. This value is then divided by six.

Buy Now
Questions 10

You are the project manager of the NQQ project. You are working with your project team to create the activity duration estimates for the project. For each reported activity duration, your project team offers you an addition of five percent extra time for risks, errors, or aggressive estimating. What does Parkinson's Law state about this scenario?

Options:

A.

Work expands to fulfill the amount of time allotted to it.

B.

Risks will be allowed into activities in which management creates risk provisions.

C.

Laborers will create errors when time has been allotted for errors to exist.

D.

Errors will be allowed into assignments when management creates error opportunity.

Buy Now
Questions 11

You are the project manager of the NHQ project. This project is slightly larger than the TR project, in which you also served as the project manager. You decide to use the actual activity duration of the GTR project as a basis for your current NHQ project. This, you reason, will save time for your project, as the previous project has provided the information. Which one of the following terms best describes the action you are doing in this scenario?

Options:

A.

You are creating an analogous estimate.

B.

You are creating a bottom-up estimate.

C.

You are relying on expert judgment.

D.

You are creating a rough order of magnitude estimate.

Buy Now
Questions 12

You are the project manager for your company. You are currently working with your project team to begin sequencing the activity list. You will need organizational process assets and four other documents as inputs to this process. Which of the following is NOT one of the four documents you will need for activity sequencing?

Options:

A.

Project scope statement

B.

Milestone list

C.

Project schedule network diagrams

D.

Activity list

Buy Now
Questions 13

Paula works as a project manager for her organization. She is working with the project team to define the activity attributes. Which of the following is NOT a valid activity attribute?

Options:

A.

Activity Name

B.

Activity ID

C.

Risk event

D.

WBS ID

Buy Now
Questions 14

You are the project manager for your organization. You are working through the control schedule process. According to the PMBOK, there are four inputs to this process. Which one of the following is NOT an input to the control schedule process?

Options:

A.

Schedule data

B.

Work performance information

C.

Project management plan

D.

Project schedule

Buy Now
Questions 15

Bonnie is the project manager for her organization. She is developing a strategy to manage the project stakeholders. She wants to identify the key stakeholders, their influence over the project, their interest in project, and an assessment of methods. What can Bonnie create to gain support from the stakeholders in her project?

Options:

A.

Stakeholder identification tools

B.

Expert judgment

C.

Stakeholder Analysis Matrix

D.

Communications management plan

Buy Now
Questions 16

Tom is the project manager for the ABC Construction Company. As part of the project scheduling for the construction of a new office building, he has allotted time for the inspectors of the building structure, as well as electrical, plumbing, and safety into the project's schedule. These inspectors can be considered what type of dependency in the project?

Options:

A.

Mandatory dependencies

B.

Required dependencies

C.

Discretionary dependencies

D.

External dependencies

Buy Now
Questions 17

In the project time management knowledge area, there are six processes. According to the PMBOK, which project time knowledge area will have the majority of the effort?

Options:

A.

Estimate activity resources

B.

Define activities

C.

Control schedule

D.

Develop schedule

Buy Now
Questions 18

Tom works as the project manager for BlueWell Inc. He is working with his project to ensure timely and appropriate generation, retrieval, distribution, collection, storage, and ultimate disposition of project information. What is the process in which Tom is working?

Options:

A.

Work performance measurement

B.

Stakeholder expectation management

C.

Project communication management

D.

Stakeholder analysis

Buy Now
Questions 19

John works as a Project Manager for Blue Well Inc. He is measuring cost efficiency of his project. The key values are provided in the table below:

What is the cost performance index (CPI) of the project at the current point of time?

Options:

A.

0.96

B.

1.082

C.

0.833

D.

1.0625

Buy Now
Questions 20

You are the project manager of a project that has a budget of $675,000 and you have completed 40 percent of the project work. Your project is supposed to be 60 percent complete but you are actually only 40 percent complete. Due to some errors, however, you have actually spent $335,000 of the budget. Management wants to know what the project's cost performance index (CPI) is. What value do you report?

Options:

A.

-$135,000

B.

.67

C.

.81

D.

-$65,000

Buy Now
Questions 21

Holly is the project manager for her organization. She is creating the activity list and would like to tag those activities that are comprised of discrete effort. What is discrete effort?

Options:

A.

It is a term used to describe activities whose effort cannot be directly measured to the project objectives.

B.

It is a term used to describe activities whose effort can be directly measured and linked to the project objectives.

C.

It is a term used to describe activities that are supportive of the project work, but not linked to the project deliverables.

D.

It is a term used to describe activities that are core project management processes, but not core project activities.

Buy Now
Questions 22

The figure given below demonstrates the communication model for a project. What role does the component E play in the communications model?

Options:

A.

Static

B.

Deterrent

C.

Noise

D.

Barrier

Buy Now
Questions 23

Ben is the project manager for his organization. His project has 26 stakeholders this week and will have five additional stakeholders next week. How many more communication channels will Ben's project have next week?

Options:

A.

140

B.

10

C.

325

D.

5

Buy Now
Questions 24

You work as a Project Manager for Dreams Unlimited Inc. You are looking for performance efficiencies of a project. The related key values are provided in the table below:

MeasurementsValues

BCWP (or EV)325

BCWS (or PV) 300

ACWP (or AC)410

What will be the cost performance index (CPI) of the project at the current point of time?

Options:

A.

0.923

B.

1.083

C.

1.261

D.

0.792

Buy Now
Questions 25

Which of the group creativity techniques enhances brainstorming with a voting process used to rank the most useful ideas for further brainstorming or prioritization?

Options:

A.

Idea/mind mapping

B.

Delphi technique

C.

Nominal group technique

D.

Affinity diagram

Buy Now
Questions 26

Which one of the following estimate types is a form of expert judgment?

Options:

A.

Parametric estimate

B.

Analogous estimate

C.

Bottom-up estimate

D.

Definitive estimate

Buy Now
Questions 27

Holly is the project manager for her organization. In her project, she has worked with the project team to define when the project team will be utilized in the project, the duration of the project activities, and the sequence in which the project work must be completed. During several phases of her project, the project team will need to work more than fifty hours per week. The project team members have agreed this is necessary and they're willing to do the work to complete the project. Management, however, has not approved Holly's schedule based on the overtime the scheduling will require. They have set a limit on the project schedule of 45 hours per week. What is this limit technically called? Each correct answer represents a complete solution. Choose all that apply.

Options:

A.

Constraint

B.

Assumption

C.

Execution variance analysis

D.

Resource leveling heuristic

Buy Now
Questions 28

You are the project manager of the GHY Project. Management wants you to create a process improvement plan for your project. Your project will be studied by management and will become a standard for all future organizational projects based on your project's performance, approach, and implementation of project processes. All of the following should be included in your project's process improvement plan except for which one?

Options:

A.

Process boundaries

B.

Process configuration

C.

Targets for improved performance

D.

Identification of project risks

Buy Now
Questions 29

You are the project manager of the GHE Project. You have identified the following risks with the characteristics as shown in the following figure:

Options:

A.

Communications bull's eye

B.

Performance goals

C.

Earned value management goals

D.

Project exception report

Buy Now
Questions 30

Nancy is the project manager of the JJJ Project. This project has recently been approved by the project customer as complete so Nancy must now finalize the administrative closure. Nancy needs to create the final project report to report the successes and failures in the project. Who should Nancy deliver this final project report to if she is participating in a projectized structure?

Options:

A.

Functional Management

B.

Project sponsor

C.

Whomever the communications management plan directs her to

D.

Project customer

Buy Now
Questions 31

Marty is the project manager of the recently completed NHK Project. The project was deemed successful by the project customer and they have signed the formal acceptance documentation. Marty has written the final project report, released the project team, and completed the lessons learned documentation. What else should Marty do in the closure of the NHK Project?

Options:

A.

Archive the project records.

B.

Summarize the project risks costs.

C.

Summarize the project variance.

D.

Close the project office.

Buy Now
Questions 32

Your project has a BAC of $750,000 and is 75 percent complete. According to your plan, however, your project should actually be 80 percent complete. You have spent $575,000 of your project budget to reach this point and you are worried about the project not being able to complete based on your current project budget. What is the to-complete performance index for this project?

Options:

A.

0.98

B.

-$16,677

C.

1.07

D.

0.94

Buy Now
Questions 33

You are the project manager of the GHT Project. Ben, one of your project team members, does not understand the idea of a milestone. Which of the following best describes what a milestone is?

Options:

A.

A significant point in the project

B.

A goal of reaching a significant delivery of project benefits by an identified date

C.

An imposed date for the project to reach a given point

D.

The completion of a project activity that is crucial to project completion

Buy Now
Questions 34

You are the project manager of the NHQ Project. Management has set a conformance to the project schedule for your project at 0.95. What does this term mean?

Options:

A.

It means the largest schedule variance you can have is five percent.

B.

It is the earned value divided by the planned value for your project.

C.

It is the expectation of management to be 95 on schedule at 95 percent of the project.

D.

It means you will need to earn at least 95 cents per dollar invested in the project.

Buy Now
Questions 35

Your project team is executing the project plan and things are going well. Your team has reached its first milestone and is now in the second phase of the project. The project stakeholders have requested that you find a method to reduce the duration of the project. They will reward you and your project team with a 25 percent bonus of the project costs if you can finish the project thirty days earlier than what was already planned. The stakeholders, however, will not approve any additional labor costs as part of the agreement. Which approach could you use to shorten the duration of the project?

Options:

A.

Perform resource leveling for the project.

B.

Crash the project schedule.

C.

Fast track the project.

D.

Remove things from the project scope.

Buy Now
Questions 36

You work as a project manager for BlueWell Inc. You want to increase the overall duration of the project. If the management elects to use resource leveling, then what will happen to the project duration?

Options:

A.

The duration will increase, but the labor will stay the same.

B.

The duration will decrease as new team members are brought onto the project.

C.

Nothing, new resources will be incorporated into the project team.

D.

The duration will increase, but the labor will decrease.

Buy Now
Questions 37

You are the project manager of the NHT Project. This project has 12,345 office doors to install throughout a campus. Each of the doors costs the project $456 and requires special hardware to electronically lock and open the doors. You've gathered the project team before they begin the installation for a hands-on training. As a group you and the project team install 50 doors following a checklist of instructions so that every door will be installed exactly the same throughout the campus and with minimal waste. This is an example of what project execution technique?

Options:

A.

Preventive action

B.

Defect repair validation

C.

Implemented corrective action

D.

Quality control

Buy Now
Questions 38

You are the project manager of the NHQ Project. You have created the project network diagram as shown in the figure:

Based on the project network diagram, how much float is available for Activity H if Activity B is delayed by four days and Activity D is delayed by two days?

Options:

A.

One

B.

Five

C.

Four

D.

Zero

Buy Now
Questions 39

Examine the figure given below:

If Activity B takes eight days to complete instead of five days as schedule, how long can you now delay Activity H?

Options:

A.

Three days

B.

One day

C.

Four days

D.

Zero days

Buy Now
Questions 40

Fill in the blank with the appropriate word. When activities are logically linked, they become the . __________

Options:

Buy Now
Questions 41

You are the project manager of the NHQ Project. You have created the project network diagram as shown in the figure:

You are concerned about a risk on Activity G that if it happens will delay the project by four days. You would like to utilize float for Activity G. How much float is available for Activity G to help offset the risk event?

Options:

A.

Five days

B.

Four days

C.

Eleven days

D.

Zero

Buy Now
Questions 42

You are the project manager for your organization. You are managing a project to create new software for your clients. During the project execution, there have been some unforeseen delays that will require your attention. You will need four inputs to the control schedule process. Which of the following documents would not be an input for the control schedule process?

Options:

A.

Project schedule

B.

Work performance information

C.

Project management plan

D.

Earned value management results

Buy Now
Questions 43

Which of the following provides a method to track project progress during project execution against what was planned?

Options:

A.

Team members profile

B.

Benefit-cost ratio

C.

Schedule baseline

D.

Detailed project budget

Buy Now
Questions 44

Mary is the project manager of the H1QZ Project. This project is a subproject of the HQZ Project and the project schedule is fixed and cannot vary. Stephen, a project team member, reports that he's having trouble completing his project assignment and will likely be at least two days late. Examine the figure given below:

If Stephen's assignment is Activity B, what impact will his two days of lateness have on the project end date?

Options:

A.

The project will complete on time.

B.

The project will be late by one day.

C.

The project will be late by two days.

D.

The project will be early by two days.

Buy Now
Questions 45

You are the project manager for the GHB Organization. Management has asked that you review your recent SPI to determine why there was a schedule variance. They'd also like you to explain what approach you'll do to counteract the SPI going forward in the project. You complete the variance analysis and report to management that you'll be fast tracking a portion of your project work. What will be the management's concern with, when it comes to fast tracking the project?

Options:

A.

Added costs for the additional project labor

B.

Added risk

C.

Continued variances in the SPI

D.

Slippage in the project quality

Buy Now
Questions 46

Harry works as a project manager for BlueWell Inc. A risk that has been identified and analyzed in the project planning processes is now coming into fruition. Who among the following is responsible for implementing the risk responses or contingency plan?

Options:

A.

Risk owner

B.

Harry

C.

Project sponsor

D.

Subject matter expert

Buy Now
Questions 47

You are the project manager for your organization. Your project is doing fine on time and cost, but management wants to address the project performance for future accomplishment. Management has asked you to begin reporting and forecasting your project's health based on a moving average, extrapolation, trend estimation, and growth curve. What type of forecasting method is management asking you to use?

Options:

A.

Judgmental methods

B.

Causal/econometric methods

C.

Time series methods

D.

Estimate at completion method

Buy Now
Questions 48

Sam works as a project manager for BlueWell Inc. Which of the following processes will he use for selecting a scheduling method, scheduling tool, incorporating project specific data within that scheduling tool to develop a project specific schedule model, and generating project schedule?

Options:

A.

Constructability Analysis process

B.

Schedule Maintenance process

C.

Schedule Development process

D.

Perform Integrated Change Control process

Buy Now
Exam Code: PMI-SP
Exam Name: PMI Scheduling Professional
Last Update: May 1, 2024
Questions: 323
$64  $159.99
$48  $119.99
$40  $99.99
buy now PMI-SP