Questions 4

As stage 3 approaches its end, the project manager seeks supplier-related advice from the CEO of BuildyBrick, acting in the senior supplier interest, about planning the testing and inspections in stage 4.

Under which ‘directing a project’ activity is this informal consultation provided?

Options:

A.

Authorize a stage or exception plan

B.

Give ongoing direction

C.

Authorize initiation

D.

Authorize the project

Buy Now
Questions 5

The Business Opportunities Director, acting as project executive, proposes that the Head of the Portfolio Office should perform business assurance and should also approve the viability of the business case and the achievability of the project plan.

Is this an appropriate application of the organization practice, and why?

Options:

A.

Yes, because appointing project assurance transfers the project executive’s accountability to the assurance provider

B.

Yes, because business assurance, rather than the project executive, owns the business case and project plan

C.

No, because assurance may review and provide confidence, but the project executive remains accountable for the business case

D.

No, because a portfolio-office role may never perform assurance work for an individual project

Buy Now
Questions 6

While preparing the project plan, the project manager and BuildyBrick’s planning specialist use the product flow and data from previous projects to determine that the utilities and systems can be delivered in parallel as separate work packages.

Is this an appropriate application of the ‘plans’ practice, and why?

Options:

A.

Yes, because data from previous projects should determine the schedule without reviewing the dependencies between the products

B.

Yes, because product dependencies determine sequence, and independent work packages may be planned to run in parallel

C.

No, because work delivered by the same supplier must be scheduled sequentially and should avoid running in parallel

D.

No, because setting work-package tolerances determines the order in which products must be produced

Buy Now
Questions 7

The LouisShopping project is part of the LOB portfolio and is now in the ‘initiating a project’ process. The project manager asks the portfolio office to support preparation of the digital and data management approach.

Why is this involvement appropriate during the ‘agree the management approaches’ activity?

Options:

A.

Because the sequencing within the ‘agree the management approaches’ activity requires the digital and data management approach to be finalized before other management approaches, including the communication management approach

B.

Because the primary purpose of the digital and data management approach is to identify what data the project will need and to establish the appropriate security and access controls for that data

C.

Because a linear-sequential delivery method inherently generates a greater volume of formal data and documentation than an iterative or incremental approach, which justifies seeking specialist portfolio support

D.

Because the digital and data management approach must be consistent with the data governance standards and technical requirements that the portfolio office applies across all projects in the LOB portfolio

Buy Now
Questions 8

While preparing the risk management approach, the project manager holds a workshop to review the project context: the historic surroundings, sustainability targets and the need to minimize disruption to residents and businesses.

Is this an appropriate application of the risk practice, and why?

Options:

A.

Yes, because the contextual statement is itself a complete set of cause-event-effect risk descriptions

B.

Yes, because understanding the project’s context and objectives is necessary to design a risk management approach

C.

No, because risk responses must be selected before the risk management approach can be fully prepared

D.

No, because project objectives should not influence how risk is managed

Buy Now
Questions 9

QUALITY

Here are three items of information relating to the testing of the solar panels during stage 4.

Under which heading of the quality register (A–E) should each item be recorded?

Choose only ONE heading for each item. Each heading can be used once, more than once, or not at all.

Options:

A.

Quality method

B.

Dates

C.

Responsibilities

D.

Result

E.

Records

Item 1:

Specialist equipment will be used to verify that the energy output from the solar panels meets the applicable industry standards.

Item 2:

The solar-panel testing will be completed in week 2 of stage 4, one week after the security-system testing.

Item 3:

Testing found that one solar panel did not meet the required energy-output standard.

Buy Now
Questions 10

During stage 3, several BuildyBrick subcontractors are working on different work packages. The project manager is concerned that lessons identified by one team will not reach the others and could lead to rework, delay or additional cost. The project manager therefore holds a fortnightly cross-team ‘lunch and learn’ session.

Is this an appropriate application of the ‘learn from experience’ principle, and why?

Options:

A.

Yes, because the regular knowledge-sharing sessions provide a structured mechanism for team managers to identify and apply lessons arising during the current stage

B.

Yes, because the subcontractors are expected to contribute lessons from previous construction projects that are directly relevant to the current stage

C.

No, because subcontractors should concentrate on meeting their work package commitments and tolerances rather than attending sessions that take them away from delivery

D.

No, because the Regeneration Manager should gather lessons through individual interviews with team managers and document them formally in a lessons report at the end of the stage

Buy Now
Questions 11

PLANS

Here are three items of information included in the stage 2 plan.

Under which heading (A–F) should each item be recorded?

Choose only ONE heading for each item of information. Each heading may be used once, more than once, or not at all.

Options:

A.

Dependencies

B.

Planning assumptions and prerequisites

C.

Products to be delivered

D.

Budget

E.

Tolerances

F.

Monitoring, control and reporting arrangements

Item 1:

The plan assumes that limited familiarity with new sustainable technologies will increase the likelihood of design errors, so additional time has been allowed for quality control.

Item 2:

During stage 2, the project manager will send the project board a summary of design progress every two weeks.

Item 3:

Stage 2 will produce archi

Buy Now
Questions 12

At the start of stage 3, the project board inserts detailed recycling tolerances directly into each work package without the project manager agreeing the delegated targets with the relevant team managers.

Is this an appropriate application of the progress practice, and why?

Options:

A.

Yes, because team managers generally need to comply with sustainability metrics set directly by the project board

B.

Yes, because the project board should collect and review work-package progress directly from each delivery team

C.

No, because the project manager should authorize the work packages and agree the delegated sustainability tolerances

D.

No, because sustainability tolerances should be recorded only at project level rather than delegated through work packages

Buy Now
Questions 13

During the ‘starting up a project’ process, the project manager works with key business, user, and supplier stakeholders to co-create the project product description, clarify the shopping centre’s scope and agree its quality expectations and acceptance criteria.

What is the MAIN benefit of co-creating the project product description in this way?

Options:

A.

It transfers accountability for approving the project product description to the stakeholders involved

B.

It removes the need for a communication management approach later in the project

C.

It confirms that stakeholders will accept the shopping centre when it is handed over

D.

It brings together business, user, and supplier perspectives, improving adoption and reducing handover risks

Buy Now
Questions 14

ISSUES

During stage 1, BuildyBrick was appointed by the procurement team manager as the main contractor for the project. The project is now in stage 3 and BuildyBrick is part way through the site preparation. Following an environmental survey report, BuildyBrick will have to delay the site clearance by several weeks to enable protected amphibians to be relocated. There are two options to deal with this issue. The first is to wait for BuildyBrick to clear the site, but this will take longer. The second is to hire an additional contractor to clear the site more quickly, but this will cost more. Both of these options can be completed within cost and time tolerances, but appointing an additional contractor is beyond the project manager’s delegated authority.

Here are three actions related to the resolution of this issue.

Which role (A–E) should be responsible for each action?

Choose only ONE role for each action. Each role can be used once, more than once, or not at all.

Options:

A.

Project executive

B.

Senior user

C.

Senior supplier

D.

Project assurance

E.

Project manager

Action 1:

Review the issue report and decide which response should be authorized.

Action 2:

After the decision is made, update the issue record with the selected response and decision.

Action 3:

Once the appointment is authorized, confirm that the supplier resources required for the additional site-clearance work can be provided.

Buy Now
Questions 15

Immediately after initiation is authorized, the Head of the Portfolio Office instructs the LouisShopping project to adopt the Council’s mature issue management approach without any project-specific review or tailoring.

Is this an appropriate application of the issues practice, and why?

Options:

A.

Yes, because a mature organizational approach should always be used without alteration

B.

Yes, because portfolio funding gives the portfolio office authority to prohibit all project-level tailoring

C.

No, because the project manager should consider the nature of the products, delivery method and project context when preparing the issue management approach

D.

No, because product version control must be decided outside the issue management approach by the delivery teams alone

Buy Now
Questions 16

PROGRESS

Here are three actions related to the ‘progress’ practice for the LouisShopping project.

Which role (A–E) should be responsible for each action?

Choose only ONE role for each action. Each role can be used once, more than once, or not at all.

Options:

A.

Project executive

B.

Project manager

C.

Project assurance

D.

Team manager

E.

Project support

Action 1:

Assist the project manager in compiling the lessons report, including the recommendation that future projects allow more time for testing and inspections.

Action 2:

When delays to the floor installation cause the stage to be forecast beyond tolerance, submit an exception report to the project board for a decision.

Action 3:

Review the exception plan and decid

Buy Now
Exam Code: PRINCE2-7-Practitioner
Exam Name: PRINCE2 Project Management Practitioner (Version 7)
Last Update: Oct 24, 2026
Questions: 56

PDF + Testing Engine

$51.42 $171.4

Testing Engine

$38.57 $128.55

PDF (Q&A)

$42.85 $142.82