As stage 3 approaches its end, the project manager seeks supplier-related advice from the CEO of BuildyBrick, acting in the senior supplier interest, about planning the testing and inspections in stage 4.
Under which ‘directing a project’ activity is this informal consultation provided?
The Business Opportunities Director, acting as project executive, proposes that the Head of the Portfolio Office should perform business assurance and should also approve the viability of the business case and the achievability of the project plan.
Is this an appropriate application of the organization practice, and why?
While preparing the project plan, the project manager and BuildyBrick’s planning specialist use the product flow and data from previous projects to determine that the utilities and systems can be delivered in parallel as separate work packages.
Is this an appropriate application of the ‘plans’ practice, and why?
The LouisShopping project is part of the LOB portfolio and is now in the ‘initiating a project’ process. The project manager asks the portfolio office to support preparation of the digital and data management approach.
Why is this involvement appropriate during the ‘agree the management approaches’ activity?
While preparing the risk management approach, the project manager holds a workshop to review the project context: the historic surroundings, sustainability targets and the need to minimize disruption to residents and businesses.
Is this an appropriate application of the risk practice, and why?
QUALITY
Here are three items of information relating to the testing of the solar panels during stage 4.
Under which heading of the quality register (A–E) should each item be recorded?
Choose only ONE heading for each item. Each heading can be used once, more than once, or not at all.
During stage 3, several BuildyBrick subcontractors are working on different work packages. The project manager is concerned that lessons identified by one team will not reach the others and could lead to rework, delay or additional cost. The project manager therefore holds a fortnightly cross-team ‘lunch and learn’ session.
Is this an appropriate application of the ‘learn from experience’ principle, and why?
PLANS
Here are three items of information included in the stage 2 plan.
Under which heading (A–F) should each item be recorded?
Choose only ONE heading for each item of information. Each heading may be used once, more than once, or not at all.
At the start of stage 3, the project board inserts detailed recycling tolerances directly into each work package without the project manager agreeing the delegated targets with the relevant team managers.
Is this an appropriate application of the progress practice, and why?
During the ‘starting up a project’ process, the project manager works with key business, user, and supplier stakeholders to co-create the project product description, clarify the shopping centre’s scope and agree its quality expectations and acceptance criteria.
What is the MAIN benefit of co-creating the project product description in this way?
ISSUES
During stage 1, BuildyBrick was appointed by the procurement team manager as the main contractor for the project. The project is now in stage 3 and BuildyBrick is part way through the site preparation. Following an environmental survey report, BuildyBrick will have to delay the site clearance by several weeks to enable protected amphibians to be relocated. There are two options to deal with this issue. The first is to wait for BuildyBrick to clear the site, but this will take longer. The second is to hire an additional contractor to clear the site more quickly, but this will cost more. Both of these options can be completed within cost and time tolerances, but appointing an additional contractor is beyond the project manager’s delegated authority.
Here are three actions related to the resolution of this issue.
Which role (A–E) should be responsible for each action?
Choose only ONE role for each action. Each role can be used once, more than once, or not at all.
Immediately after initiation is authorized, the Head of the Portfolio Office instructs the LouisShopping project to adopt the Council’s mature issue management approach without any project-specific review or tailoring.
Is this an appropriate application of the issues practice, and why?
PROGRESS
Here are three actions related to the ‘progress’ practice for the LouisShopping project.
Which role (A–E) should be responsible for each action?
Choose only ONE role for each action. Each role can be used once, more than once, or not at all.