Weekend Sale - Limited Time 60% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 575363r9

Welcome To DumpsPedia

PRINCE2-Agile-Foundation Sample Questions Answers

Questions 4

Which TWO project board responsibilities are specifically assigned to the senior user?

1) Demonstrating the achievement of benefits.

2) Specifying the needs of those impacted by the outputs.

3) Balancing business, user and supplier demands.

4) Ensuring that the project delivers value for money.

Options:

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Buy Now
Questions 5

Which process can take place during a release review workshop?

Options:

A.

Controlling a stage

B.

Managing product delivery

C.

Managing a stage boundary

D.

Directing a project

Buy Now
Questions 6

Which statement about the waterfall methodology definition is CORRECT?

Options:

A.

It states that deadlines should not be moved

B.

It has distinct goals for each stage of development

C.

It is a behavior that involves making things transparent

D.

It promotes the use of experiments carried out in a scientific way

Buy Now
Questions 7

What information is NOT typically displayed on a burn chart?

Options:

A.

Effort remaining

B.

Team working agreements

C.

Actual amount of work done

D.

Amount of time elapsed

Buy Now
Questions 8

Which is often used during a retrospective to capture lessons?

Options:

A.

A Glad! Sad! Mad! board

B.

A Kanban board

C.

A burn chart

D.

A Gantt chart

Buy Now
Questions 9

What is typically added to a user story as the understanding of the requirement evolves?

Options:

A.

An epic

B.

Acceptance criteria

C.

Definition of ‘ready’

D.

Effort actually expended

Buy Now
Questions 10

Which TWO are the purposes of a highlight report?

1. To describe the MoSCoW priority of user stories.

2. To summarize the status of a work package.

3. To summarize the stage status.

4. To report any potential issues and risks

Options:

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Buy Now
Questions 11

Which is a typical characteristic of ‘business as usual’ work?

Options:

A.

It requires a specific dedicated project manager

B.

It is executed by program management

C.

It is delivered by a temporary team

D.

It is delivered by an established team

Buy Now
Questions 12

What does velocity typically measure?

Options:

A.

Work packages completed by the team

B.

The rate of progress the team is making

C.

The number of timeboxes completed

D.

The speed that a minimum viable product is created

Buy Now
Questions 13

Which is a purpose of the ‘managing product delivery’ process?

Options:

A.

To plan the delivery of the products before committing to significant expenditure

B.

To agree on what is required for accepting, executing and delivering project work.

C.

To establish and deliver the project communications to the wider organization

D.

To delegate day-to-day management of the project to the project manager

Buy Now
Exam Code: PRINCE2-Agile-Foundation
Exam Name: PRINCE2 Agile Foundation Exam
Last Update: May 12, 2024
Questions: 92
$64  $159.99
$48  $119.99
$40  $99.99
buy now PRINCE2-Agile-Foundation