Which TWO project board responsibilities are specifically assigned to the senior user?
1) Demonstrating the achievement of benefits.
2) Specifying the needs of those impacted by the outputs.
3) Balancing business, user and supplier demands.
4) Ensuring that the project delivers value for money.
What is typically added to a user story as the understanding of the requirement evolves?
Which TWO are the purposes of a highlight report?
1. To describe the MoSCoW priority of user stories.
2. To summarize the status of a work package.
3. To summarize the stage status.
4. To report any potential issues and risks