PgMP Sample Questions Answers

Questions 4

You are the program manager for your organization and are working with your team to create the program scope management plan. This plan defines several things in your program except for which one of the following?

Options:

A.

How quality control will be included in the scope

B.

How changes may be allowed to enter the program scope

C.

How the program scope will be created for your program

D.

How the program scope will be controlled

Buy Now
Questions 5

Julie is the program manager of the NHQ Program for her organization and she believes the program is now complete. Julie is closing her program, and she's working with her program sponsor to review the program's deliverables and benefits. Janet, the program sponsor, is very pleased with the program and agrees that the program has met the program scope. What should Julie and the program sponsor do next?

Options:

A.

Close the constituent projects before closing the program

B.

Complete the program's budget

C.

Release the program's resources

D.

Sign the certificate of program closure

Buy Now
Questions 6

A program manager for the construction of a ship reviews the program management plan with a shipyard representative. The shipyard representative indicates that while 65 percent progress was anticipated, only 60 percent has been achieved.

What should the program manager do to ensure benefits realization?

Options:

A.

Conduct a program performance analysis based upon the deviation, and update the program business case to reflect the schedule delay.

B.

Inform the program sponsor and the steering committee of the delay, and validate the program business case.

C.

Analyze the impact of the delay, review risks identify any corrective actions, and update the benefits management plan.

D.

Update the program schedule, and escalate the issue to the program management office (PMO) to accelerate shipyard work.

Buy Now
Questions 7

A program manager is identifying and verifying risks as outlined in the risk management plan.

The results will be recorded in which of the following?

Options:

A.

Risk register

B.

Risk monitoring and control

C.

Risk response planning

D.

Risk mitigation strategy

Buy Now
Questions 8

A multi-year complex program will deliver advanced driver assistance system (ADAS) components for autonomous vehicles. Several key stakeholders are concerned because they have not been regularly involved with the program and do not understand the program's benefits.

What should the program manager do to address these key stakeholders' concerns?

Options:

A.

Meet with the stakeholders and update the stakeholder map.

B.

Create a progress report to share with stakeholders after the next status meeting.

C.

Capture stakeholder expectations, and revise the stakeholder engagement plan.

D.

Update the communications management plan after meeting with the program steering committee.

Buy Now
Questions 9

A new program component provides an opportunity to enhance program outcomes. What does the program manager use to document and monitor the opportunity?

Options:

A.

Program risk register

B.

Program scope management plan

C.

Program risk management plan

D.

Component project risk register

Buy Now
Questions 10

The program selection committee presents several programs for approval:

Program A is estimated to cost US$250,000, and has an annual cash inflow of US$75,000. Program B is estimated to cost US$150,000, and has an annual cash inflow of US$55,000. Program C is estimated to cost US$100,000, and has an annual cash inflow of US$45,000. Program D is estimated to cost US$200,000, and has an annual cash inflow of US$35,000.

Which program was selected based solely on a three-year return on investment?

Options:

A.

Program A

B.

Program B

C.

Program C

D.

Program D

Buy Now
Questions 11

Hal is the program manager for his organization. He would like your organization to provide his program with 4 tons of pea gravel for a construction project in his program. Hal send you a statement of work and an IFB. What document should you provide to Hal?

Options:

A.

Invoice

B.

Proposal

C.

Bid

D.

Quote

Buy Now
Questions 12

Gary is the program manager for his organization. His current program has 432 stakeholders, some of which are external to his organization. He would like to create a chart that identifies each stakeholder's opinion of the program, influence over program decisions, their requirements and affect on program priorities, and other information. What kind of chart should Gary create in this instance?

Options:

A.

Resource breakdown structure

B.

Resource management chart

C.

Stakeholder analysis chart

D.

RACI chart

Buy Now
Questions 13

A program has been established and preparation is complete.

Component projects are planned as a part of which of the following?

Options:

A.

Program definition phase

B.

Program formulation

C.

Program planning

D.

Program delivery phase

Buy Now
Questions 14

What project management term would you associated with a predetermined budget you’re your program?

Options:

A.

Program governance

B.

Constraint

C.

Cost baseline

D.

Assumption

Buy Now
Questions 15

A company CEO meets with key customers to learn how they can be better served. After discovering that

some executive team members disagree with each other, the CEO asks the program management office (PMO) to develop a program to better serve key customers based on their strategic importance to the company’s long-term goals.

What should the program manager do to establish and successfully manage the program’s direction?

Options:

A.

Create a program strategy to obtain the required funding from the portfolio decision team

B.

Develop and foster relationships with stakeholders to improve communication

C.

Conduct stakeholder interviews to address their concerns and expectations

D.

Identify a list of projects, and then assign them suitable project managers

Buy Now
Questions 16

Robert's program is slipping on its schedule and management has asked that Robert find a method to compress the duration of the program. What approach could Robert take that would not dramatically add risks to program if he added labor to the effort-driven activities within the program?

Options:

A.

Lead time

B.

Crashing

C.

Lag time

D.

Fast tracking

Buy Now
Questions 17

You are the program manager of the NHQ Program. The program has reached its final deliverable and the certificate of completion has been created for the program. What else should you, the program manager,

create at this time?

Options:

A.

Life cycle costing estimates

B.

Lessons learned documentation

C.

Operational transfer plan

D.

Program closure reports

Buy Now
Questions 18

The program manager of a multinational program must reconcile data including subject matter experts’ labor hour estimates, and other direct resource hour estimates. In addition, the program manager must prepare the cash flow analysis.

Which of the following should be considered to get a baseline budget?

Options:

A.

Currency exchange rates

B.

Component cost estimates

C.

Baseline schedule

D.

Program payment schedules

Buy Now
Questions 19

Tom is program manager for his organization. His program is scheduled to last ten months and has a cost estimate for the program of $550,000. It is now month nine and Tom reports that he actually has a cost variance of a positive $56,000. While Tom is pleased, the new management is not. Why is a positive cost variance not necessarily good news?

Options:

A.

A poor cost estimate prevented the organization from adding things to the program scope.

B.

Tom has overestimated the cost of the program.

C.

A poor cost estimate could affect the organization's decisions to invest the funds elsewhere .

D.

Tom has forgot to include deliverables in the program.

Buy Now
Questions 20

You are the program manager of the NHQ Program. You are working with your program team to ensure that the work in the program is done accurately and according to scope. You are also reviewing the team inspection process that will need to be done to ensure that the work is being done according to the scope. If the work is found to be defective it will need to be corrected before the program customers can inspect the work. What process are you completing to ensure that the work is done accordingly to scope?

Options:

A.

Quality control

B.

Scope verification

C.

Quality assurance

D.

Planning

Buy Now
Questions 21

A program manager is working on benefits. The program team created and updated a benefits register earlier in the program.

The benefits register should include which of the following?

Options:

A.

List of planned benefits, earned value (EV), and responsible person

B.

List of planned benefits, measurement method, and component mapping

C.

List of planned benefits, benefit creator, and realization date

D.

List of planned benefits, stakeholders, and risk level

Buy Now
Questions 22

A program manager assigns project managers to five component projects and continues to develop the program team.

Which of the following represents the program manager's strategy?

Options:

A.

Rotate the responsibility for risk assessment among the program components

B.

Coach the project managers to manage project resources

C.

Cross-train the project managers to share expertise

D.

Prepare the project managers to assume larger roles with more responsibility

Buy Now
Questions 23

You are the program manager of the MQQ Program. Your program will use equipment and materials that are new to your industry. You have some concerns that there will be delays and waste by your program team because they've not worked with these materials or tools before. You elect to send the resources that will work the most with these tools through training. The cost of the training in this instance is known as which one of the following?

Options:

A.

Indirect costs

B.

Cost of doing business

C.

Direct costs

D.

Cost of conformance quality

Buy Now
Questions 24

During the selection of source process, you assign certain points towards various categories to judge the vendors. Which type of source selection process is it?

Options:

A.

Benefit-cost analysis

B.

Screening system

C.

Weighting system

D.

Preferred vendor list

Buy Now
Questions 25

Paula is program manager for her organization. It has come to her attention that several of the projects within her program have stalled which has now caused her project to be delayed. Paula is required by her organization to create a certain type of report when there are variances in the program dealing with time and cost. What type of report is Paula likely to create in this instance?

Options:

A.

Earned Value Management report on the schedule performance index

B.

Exceptions report

C.

Status report

D.

Quality Control Report

Buy Now
Questions 26

A large program consists of several component projects and six project managers. The program governance board requests that all components within the program undergo user acceptance testing before being released to the production environment.

Where should the program manager document this?

Options:

A.

Program governance plan

B.

Program requirements

C.

Component test plan and test cases

D.

Program quality management plan

Buy Now
Questions 27

At what point in the project is the risk of failing to achieve the project objectives the greatest?

Options:

A.

During project planning

B.

During the project execution

C.

At the project start

D.

At the end of the project

Buy Now
Questions 28

You are the program manager of HYH Program for your organization. Your program is to create a new sports arena for your city within 12 months. Your program has seven projects and you've worked with all of the project managers before. Even though you've worked with the project managers before you still need to define the authority of the project managers and their projects. What document names the project manager for the project?

Options:

A.

Project charter for each project

B.

Program human resource management plan

C.

Project scope statement

D.

Program management charter

Buy Now
Questions 29

You are the program manager for your organization. You're currently creating an accountability matrix starting with yourself, the program manager and the program sponsor. What program management process identifies the program sponsor?

Options:

A.

Pre-program setup phase

B.

Authorization of program processes and projects

C.

Initiate program process

D.

Initiation of the program management team

Buy Now
Questions 30

Mary has just completed a large program for her organization. What should Mary now do with the program records that she has created throughout the program?

Options:

A.

The program records should be archived with the program customer.

B.

The program records should be archived with the program sponsor.

C.

The program records should be archived as part of organizational process assets.

D.

The program records should be archived as part of enterprise environmental factors.

Buy Now
Questions 31

You are the program manager for your organization and you are preparing to launch several constituent projects within your program. You need to ensure that each project manager is authorized to utilize the appropriate project and program resources in order to complete the project requirements. What document do you need to create for each constituent project in your program to ensure that each project manager can use the appropriate resources?

Options:

A.

Project charter

B.

Project scope statement

C.

Project resource requirements document

D.

Roles and responsibilities chart

Buy Now
Questions 32

Julie is the project manager of the NHQ Project. She and her project team have successfully finished the project and the customers have signed the project closure agreement. Julie has compiled all of the project records and the project's lessons learned documentation. What should Julie do with the project's lessons learned documentation?

Options:

A.

These are for Julie's reference when she is reviewed by the project sponsor.

B.

These are given to the project sponsor so he can review the project.

C.

These are given to the project steering committee so they may review the project performance.

D.

These are transferred to the lessons learned knowledge base.

Buy Now
Questions 33

A global enterprise resource planning (ERP) program’s scope includes designing and building a global template. Plans include a pilot implementation project to validate the template, to be followed by several rollout projects. During the build of the global template, a new government regulation mandates implementation of a goods and services tax (GST).

What should the program manager update?

Options:

A.

Program communications management plan

B.

Benefits management plan

C.

Stakeholder engagement plan

D.

Benefits transition plan

Buy Now
Questions 34

After new private equity owners acquire an enterprise, they want to improve its value by reducing costs. A new program will restructure the enterprise, including an aging headquarters campus where the main data center is housed. A strategic component project presents significant risk to organizational objectives due to its complexity and dependencies on external parties. After a series of board meetings, the enterprise’s

investment committee approves a budget to implement this component project, which will move the old data center from the aging headquarters campus into a new colocation facility. Implementation of this component project may now begin, but is already one month behind schedule. The program manager now perceives significantly more risk to the larger program due to this delay.

What should the program manager do to address this risk with the program sponsor and governance board?

Options:

A.

Share the concerns with the program sponsor to confirm understanding of the new development. Next, update the program budget, implementation plan, and risk management plan for governance board approval.

B.

Update the component project’s risk register, issue log, implementation plan, and risk management plan.

Next, meet with the program sponsor to revise the program budget, implementation plan, and risk management plan for governance board approval.

C.

Revise the program budget, and implement the component project by managing it closely to recover the month-long delay. Next, update the component’s project and risk management plans for governance board approval.

D.

Update the program budget, and task the component project manager with implementing the plan. Next, submit a change order for approval to apply more resources to reduce the larger program’s risk profile.

Buy Now
Questions 35

Wan is the program manager for his organization. He has been hearing reports that some

project team members are complaining about the number of hours they're required to work on the program's projects and that some scheduling of team assignments are conflicting with their regular operational duties. You investigate the problem and agree that many team members are being assigned too much work within a given time period. You decide to enforce resource leveling heuristics to thirty hours of project work per week maximum. What will likely happen to the program and projects?

Options:

A.

The schedule to complete the work will take longer.

B.

The cost of the program and project will increase.

C.

The risks of failure will increase.

D.

The morale of the project managers will decline.

Buy Now
Questions 36

You are the project manager of a construction project. You have to close a phase of the project. Which is the only technique (or tool) available in the Close Project or Phase process?

Options:

A.

Change control meetings

B.

Project management information system

C.

Expert judgment

D.

Observations

Buy Now
Questions 37

An organization requests that a junior project manager, with no previous experience or training in the industry, take over a complex program component. The program component involves senior subject matter experts and has dependencies with other large projects to deliver key benefits to the organization.

How should the junior project manager respond to this request?

Options:

A.

Accept the assignment, identify the skill gaps, and request training.

B.

Reject the assignment, because of the ethical requirement not to accept work for which the project manager is not qualified.

C.

Accept the assignment as a challenge and an opportunity to acquire new skills and seek advice from a senior project manager.

D.

Reject the assignment because of fear of failure and resulting negative career impact.

Buy Now
Questions 38

An organization supports both programs and projects for various industries. What is a portfolio?

Options:

A.

A portfolio is the total amount of funds that have been invested in programs, projects, and operations.

B.

A portfolio describes all of the monies that are invested in the organization.

C.

A portfolio describes the organization of related projects, programs, and operations.

D.

A portfolio describes any project or program within one industry or application areA.

Buy Now
Questions 39

A new program is comprised of four component projects. The program manager must assign project managers to each of the four projects. There are eight potential project managers to consider.

What should the program manager do before assigning the project managers?

Options:

A.

Determine budgetary constraints related to the project managers’ salaries

B.

Request performance feedback from the project managers’ line managers

C.

Evaluate the project managers’ skills and match them to the needs of the projects

D.

Interview each project manager to determine their career aspirations

Buy Now
Questions 40

All of the following are resources that you will need to monitor and control in a program environment except for which one?

Options:

A.

Staff members

B.

Contracts

C.

Quality

D.

Equipment

Buy Now
Questions 41

You are the program manager of the YHT Program. You have been working with a vendor in the program but have decided that the contract between your program and the vendor needs to be terminated. What two things must be documented if you wish to terminate a vendor's contract?

Options:

A.

Contract and the quality measurements for the vendor's work

B.

The scope verification document and the termination notice

C.

Contract and scope verification process documents

D.

Work that has been completed and uncompleted work

Buy Now
Questions 42

A biometrics firm has a facial recognition program with multiple components and project managers. The

project manager from the mobile device division escalates a vendor-related risk to the program manager. After assessing the risk, the program manager determines that this risk may impact other projects within the program. However, this risk has a low degree of impact and probability of occurring.

What should the program manager do first?

Options:

A.

Obtain a risk reserve from the executive sponsor, and execute a contingency plan.

B.

Communicate the risk to all project managers to manage at the component level.

C.

Add the risk details and analysis to the program risk register.

D.

Brainstorm with the project manager to develop an appropriate risk response.

Buy Now
Questions 43

A program manager is concerned that a program will be unable to achieve its intended benefits.

How should the program manager handle this concern?

Options:

A.

Meet with the program management office (PMO) to review critical program success factors.

B.

Meet with the component project managers to reallocate resources within the program.

C.

Meet with the program stakeholders to determine if a reduction in program scope is acceptable.

D.

Meet with the component project managers to perform risk analysis.

Buy Now
Questions 44

A software company's program manager is conducting closing procedures for a program. At the last steering

committee meeting, realized benefits were presented to the program governance board. What should the program manager do next?

Options:

A.

Begin transitioning program resources, and update the resource and program management plans to reflect the change in the program's status.

B.

Initiate knowledge transfer with the receiving organization, and establish the program integration management plan.

C.

Update the financial, stakeholder, and contract management plans, and archive them in the program information repository.

D.

Obtain sponsoring organization approval to begin closeout procedures to transition benefits sustainment to the supporting organization.

Buy Now
Questions 45

Josh is the program manager for his organization and he's leading the analysis for a new program that may be initiated by his company. The analysis is a focus on the return on investment for new software that may be created if the program is initiated. What type of a document is Josh likely creating for his company?

Options:

A.

Business case

B.

Program charter

C.

Program scope statement

D.

Statement of work

Buy Now
Questions 46

A company is evaluating the implementation of enterprise resource planning (ERP) software. The program manager performs an analysis to confirm the program's feasibility.

What other important step should the program manager complete?

Options:

A.

Development of the program's vision statement

B.

Review of strategic goals against any external environmental factors

C.

Identification and documentation of the initial risks for ERP software implementation

D.

Mapping of the financial benefits to the ERP software's functionality

Buy Now
Questions 47

During the last steering committee meeting, a program manager presented the benefits register to the program governance board. Since the intended benefits of the program were realized, the program manager was asked to transition the program into operations.

At this stage, what is expected during the post-review session organized by the program manager?

Options:

A.

Earned value (EV) report

B.

Customer sign-off

C.

Benefits register updates

D.

Feedback and lessons learned

Buy Now
Questions 48

Leigh is working with the project stakeholders to define the project scope. The stakeholders are deciding on what type of flooring their new hotel should have in the lobby. They have narrowed their choices to either carpet or tile. The two acceptable choices of carpet or tile during scope definition is an example of what planning approach?

Options:

A.

Alternative identification

B.

Work packages

C.

Requirements

D.

Scope decomposition

Buy Now
Questions 49

What analysis type could you use in a program to compare the positive stakeholders and their position, power, and influence over your program to the same variable components of the negative stakeholders in your program?

Options:

A.

Sensitivity analysis

B.

Stakeholder analysis

C.

Monte Carlo simulation

D.

Force field analysis

Buy Now
Questions 50

A multiyear program is ready to conclude. It has achieved all business objectives and is delivering its intended benefits. However, the program sponsor is not willing to sign the formal program closure acceptance document and the program continues to incur operational costs.

What should the program manager do next?

Options:

A.

Ask the finance department to increase the program budget

B.

Escalate the issue to the program governance board

C.

Ask key stakeholders to influence the program sponsor

D.

Direct component project managers to archive all relevant project documents

Buy Now
Questions 51

You are the program manager of the YGH Program. A vendor has recently completed his contracted work for your program. You agree that the vendor has completed the procured work so what document should you and the vendors now sign?

Options:

A.

Certificate of completion

B.

Proposal agreement

C.

Invoice

D.

Contract

Buy Now
Questions 52

You are the program manager for your organization and are planning the roles and responsibilities in your program. You would like to create a RACI chart for the program work. What does RACI mean?

Options:

A.

It is a roles and responsibilities chart that uses responsible, accountable, consult, and inform responsibilities as the chart legend.

B.

It is a roles and responsibilities chart that uses responsible, action, consult, and interest responsibilities as the chart legend.

C.

It is a roles and responsibilities chart that uses resource, action, contribute, inform responsibilities as the chart legend.

D.

It is a roles and responsibilities chart that uses responsible, accountable, contribute, and inform responsibilities as the chart legend.

Buy Now
Questions 53

A small, regional utility closes a customer rewards program and transitions it to operations. The executive sponsor and program manager are concerned about the impact on benefits realization. The program manager assures the executive sponsor that any corrective actions will be included in the next phase.

What should the program manager do to ensure a successful transition?

Options:

A.

Ask each project manager to consolidate and file all program documentation in the corporate archives.

B.

Obtain all project manager’s contact information, and then have them reassigned back to their functional managers.

C.

Ask the program’s business analyst to collect all project information and create a report.

D.

Ensure that all program documents, including lessons learned, are archived in the knowledge repository.

Buy Now
Questions 54

The program manager must define the program and understand the organization’s target market and customer needs.

What should the program manager do first?

Options:

A.

Brainstorm with the program team to decide on the definitions of the target market.

B.

Meet with peers to identify the company’s competitors in the target market.

C.

Meet with the project managers to identify the target market.

D.

Work with the program sponsor to assess the needs of the target market.

Buy Now
Questions 55

The project manager of project A develops a communications management plan. The project manager of project B is new and is uncertain how to develop appropriate communications for the company's staff.

What should the program manager do to ensure communications on the component projects are consistent?

Options:

A.

Request a more experienced project manager to work on project B.

B.

Create a program communications management plan across all component projects.

C.

Direct all projects to use project A's communications management plan as a template.

D.

Rework the communications management plans for all projects to be consistent.

Buy Now
Questions 56

To create market advantage, a program sponsor requests accelerating the implementation of a new manufacturing process that is based on a recently improved system component. The program manager is concerned that the delivery of some program goals could be jeopardized.

What should the program manager do?

Options:

A.

Document the concerns that program goals may be affected and present at the next program governance board review meeting for guidance and actions to be taken

B.

Advise the program sponsor that the program will continue and follow the program management plan, unless the change control board (CCB) has approved changes to the plan

C.

Work with the project managers of the affected components to implement fast tracking and update the resource management plan accordingly

D.

Evaluate critical success factors and key performance indicators (KPIs) to monitor benefits throughout the program's life cycle

Buy Now
Questions 57

You are the program manager of the NQA Program. In this program you're planning which contract types you'll allow into the program and which ones you will not. One contract type you won't accept is the cost plus percentage of cost contract. Which of the following is a valid reason you would not allow this contract type into your program?

Options:

A.

The contract type requires the vendor to provide a fee for the time invested and the materials used.

B.

The contract type allows the vendor to change the price of the work he's completed.

C.

The contract type allows is the most dangerous for the buyer.

D.

The contract type requires the vendor to provide a fixed price for the work.

Buy Now
Questions 58

During the program execution stage, the component project manager responsible for testing estimates that budgeted hours may exceed 200 hours.

What should the program manager do?

Options:

A.

Communicate to the program sponsor regarding the additional estimated cost and request a change order.

B.

Determine which component projects have excess capacity and rebalance those resources to the project that needs additional hours.

C.

Request that the project manager make the team members work additional hours and not bill the project.

D.

Talk with the project manager and find ways to reduce hours in another part of the project.

Buy Now
Questions 59

Status information, including program and component status, cost information, risk analysis and other relevant information, is provided in which of the following?

Options:

A.

Program performance report

B.

Communications management plan

C.

Communications log updates

D.

Information gathering and retrieval system

Buy Now
Questions 60

You are the program manager of the JNH Program. Tom, a project manager in your program, has just completed his project and is ready to officially close his project. You agree that Tom's project is completed. What role do you play in Tom's project closure?

Options:

A.

You must ensure that the project sponsor closes the project.

B.

You must ensure that that the projects within the program have been closed at the project level.

C.

You must close the project before operations closes the project.

D.

You must ensure that the program management team closes the project for the project manager.

Buy Now
Questions 61

A program manager is responsible for constructing a US$50 million building. Management suggests it will take three years to complete. The program manager can select a design-build option to optimize the construction schedule to 1.5 years. However, heavy demand for steel is causing price increases and delivery delays. If this trend continues, it could take as long as 4.5 years to complete construction. You learn that a new technology can yield a definitive delivery schedule of 1.25 years.

What is the expected time of delivery?

Options:

A.

1.25 years

B.

1.50 years

C.

1.75 years

D.

1.00 years

Buy Now
Questions 62

Which of the following can be an effective tool during quality control to help determine the how the problem occurred?

Options:

A.

Rework

B.

Flowcharting

C.

Trend Analysis

D.

Pareto Diagram

Buy Now
Questions 63

A natural disaster shuts down operations for two days. The program has a major milestone that includes a timed payment of US$1 million.

Since the shutdown was not anticipated, what should the program manager do first?

Options:

A.

Implement the appropriate risk response plan and inform the stakeholders of the planned actions.

B.

Utilize contingency reserves to hire contractors, which will accelerate the schedule to meet the original milestone.

C.

Evaluate the impact, reassess the program risk, and determine options to be presented to the governance board.

D.

Collaborate with the sponsor to determine options and negotiate a new date for the milestone.

Buy Now
Questions 64

Near the end of an ongoing project, the program manager is terminated due to underperformance and a new program manager joins the team. The program's last component project will go live in one week.

What must the new program manager do before program closure?

Options:

A.

Review the benefits management plan to ensure that the first component project launched met stakeholder expectations.

B.

Ask the program steering committee to allow program closure to start immediately following the launch of the last component project.

C.

Begin to collect lessons learned from all stakeholders, and prepare mitigation strategies in advance of the last component project's launch.

D.

Work with the program sponsor to identify who is responsible for benefits sustainment, and identify measures from the benefits management plan to measure success.

Buy Now
Questions 65

Which of the following is responsible to sign off on the closure documents of a project?

Options:

A.

Project team members

B.

Project Manager

C.

End user

D.

Sponsor

Buy Now
Questions 66

You are the program manager for your organization. Your program has a budget of $750,000 and is expected to last one year. The program is currently 30 percent complete and has spent $245,000. The program is supposed to be 40 percent at this time. What is the cost performance index for this program?

Options:

A.

.83

B.

-$20,000 C. .91

C.

Negative ten percent

Buy Now
Questions 67

Which of the following can be used to help you or other project managers on future projects?

Options:

A.

Sponsor

B.

Charter

C.

Stakeholder

D.

Documentation

Buy Now