CTAL-TTA Sample Questions Answers

Questions 4

You are working on an internet banking project. Your company is offering this product to the financial market. For each new customer, some customization will typically be needed. To make the product successful there is a strong focus during development on a reliable and maintainable architecture. To support architectural reviews, a checklist will be developed. Within the checklist specific sections will be attributed to reliability and maintainability.

Which question from the list below should you include in the maintainability section of the architectural review checklist?

Options:

A.

Will the system use n-version programming for critical components?

B.

Will the user interface be implemented independently from the other software modules?

C.

Does the system have user-friendly error messages?

D.

Does the password protection of the system adhere to the latest regulations?

Buy Now
Questions 5

Which of the following is a generic risk factor that should be considered by a Technical Test Analyst during a product risk analysis?

Options:

A.

Frequency of use of the affected feature by end-users.

B.

Complexity of new technology.

C.

Visibility of failure leading to negative publicity and potential image damage.

D.

High change rate of business requirements.

Buy Now
Questions 6

Which of the following statements BEST describes how tools support model-based testing?

Options:

A.

Finite state machines are used to describe the intended execution-time behavior of a software-controlled system.

B.

Random sets of threads of execution are generated as test cases.

C.

Large sets of test cases are generated to provide full code coverage.

D.

An engine is provided that allows the user to execute the model.

Buy Now
Questions 7

Within an embedded software project, the maintainability of the software is considered to be critical. It has been decided to use static analysis on each delivered software component.

Which of the following metrics is NOT a maintainability metric typically used with static analysis?

Options:

A.

Number of Lines of Code (LOG)

B.

Number of Function Calls

C.

Mean Time Between Failures

D.

Comment Frequency

Buy Now
Questions 8

Which of the following statements about performance testing tools is NOT correct?

Options:

A.

Typical metrics and reports provided by performance testing tools include the number of simulated users throughout the test, and the number and type of transactions generated by the simulated users, and the arrival rate of the transactions.

B.

Significant factors to consider in the implementation of performance testing tools include the flexibility of the tool to allow different operational profiles to be easily implemented, and the hardware and network bandwidth required to generate the load.

C.

Performance testing tools typically drive the application by simulating user interaction at the graphical user interface level to more accurately measure response times.

D.

Performance testing tools generate a load by simulating a large number of virtual users following their designated operational profiles to generate specific volumes of input data.

Buy Now
Questions 9

A new web site has been launched for a testing conference. There are a number of links to other related web sites for information purposes. Participants like the new site but complaints are being made that some (not all) of the links to other sites do not work.

Which type of test tool is most appropriate in helping to identify the causes of these failures?

Options:

A.

Review tool

B.

Hyperlink tool

C.

Static analysis tool

D.

Dynamic analysis tool

Buy Now
Questions 10

Consider the following control flow graph:

The control flow represents a software component of a car navigation system. Within the project the maximum cyclomatic complexity to be allowed is set at 5.

Which of the following statements is correct?

Options:

A.

No defect needs to be reported since the cyclomatic complexity of the component is calculated at 3.

B.

No defect needs to be reported since the cyclomatic complexity of the component is calculated at 4

C.

No defect needs to be reported since the cyclomatic complexity of the component is calculated at 5.

D.

A defect needs to be reported since the cyclomatic complexity of the component is calculated at 6.

Buy Now
Questions 11

You are involved in testing a system in the medical domain. Testing needs to comply with the FDA requirements and is rated as being safety critical. A product risk assessment has been performed and various mitigation actions have been identified. Reliability testing is one of the test types that needs to be performed throughout the development lifecycle.

Based on the information provided, which of the following activities would need to be addressed in the test plan?

Options:

A.

Perform a vulnerability scan.

B.

Design and execution of specific tests that evaluate the software's tolerance to faults in terms of handling unexpected input values.

C.

Design and execution of test cases for scalability.

D.

Testing whether the installation/de-installation can be completed.

Buy Now
Questions 12

Consider the following specification:

If you are flying with an economy ticket, there is a possibility that you may get upgraded to business class, especially if you hold a gold card in the airline’s frequent flier program. If you don’t hold a gold card, there is a possibility that you will get ‘bumped’ off the flight if it is full when you check in late.

This is shown in the control flow graph below. Note that each box (i.e., statement, decision) has been numbered.

Three tests have been run:

Test 1: Gold card holder who gets upgraded to business class

Test 2: Non-gold card holder who stays in economy

Test 3: A person who is bumped from the flight

What is the level of decision coverage achieved by these three tests?

Options:

A.

60%

B.

67%

C.

75%

D.

80%

Buy Now
Questions 13

At which test level would reliability testing most likely be performed?

Options:

A.

Static testing

B.

Component testing

C.

System testing

D.

Functional acceptance testing

Buy Now
Exam Code: CTAL-TTA
Exam Name: Certified Tester Advanced Level Technical Test Analyst
Last Update: Apr 21, 2024
Questions: 45
$64  $159.99
$48  $119.99
$40  $99.99
buy now CTAL-TTA