As the owner’s representative, you are providing on-site construction management services to a municipality for their new design-build city hall project.
The mechanical subcontractor discovers that his ductwork will not fit in the above-ceiling area of the Mayor’s office. Which entity is best-suited to resolve this risk?
When applying Business Intelligence (also known as data mining) to manage large volumes of construction project data, the source data must
When developing schedule specifications, which of the following practices should the CM recommend to the Owner to avoid disputes regarding weatherdelays per year?
In what decade was the new occupation of "construction manager" created to fulfill an identified need?
At what stage of the design phase shall the CM conduct a constructability review?
A program management function that promotes the efficient use of completed projects and/or parts of completed projects to maximize the owner's return on investment is called
Lifecycle analysis of a project will provide the greatest impact during which of the following phases?
Contract administration includes, but is not limited to, planning for implementation of drawings, specifications, and
As the owner's rep, you are providing on-site construction management services to a municipality for their new design-build city mall project.
During your review of the design-build team's schedule update, you discover the project is five weeks behind schedule. What is your recommendation to the owner regarding the document needed from the design-build team to correct the situation?
= P × [(C + T + Q) + 3]
P is Probability
C is Cost
T is Time
Q is Quality
This equation best describes a(n)
Owner's representation staff are managing the construction of a new water treatment plant. The owner has specific operational and sustainability goals they want met and are contracting the team for full commissioning services. The commissioning plan should include which of the following requirements for each party in the commissioning process?
An agency CM is overseeing the construction of a large, complex multi-story, high security building in a remote area. The building had a specialized spire installed at the top, which serves as an encrypted signal transmitter. Construction is complete and the contractor has de-mobilized, but then it is discovered that the signal transmitter is not transmitting the signal. The owner's QC plan required testing for the functionality of the transmitter, but the contractor has not shown test results reflecting adequate performance. Who is responsible for the cost of remobilization?
While conducting an inspection of the work in progress for a design-bid-build project, a CM notices that some of the completed work does not conform to the construction documents. The FIRST thing the CM should do is
The joint between a cast-in-place wall and a cast-in-place roof slab contains a waterstop for a sub-grade structure. While installing roof beams, the waterstop became dislodged from the already-placed wall. A non-conformance report was issued. The engineer of record's repair detail showed to cut and remove the dislodged waterstop sections. The authority/agency re-approved the detail as the waterstop is part of a secondary waterproofing system and the primary system was deemed sufficient. The contractor did not comply with the detail and placed the concrete roof slab over the dislodged material. In this scenario, which of the following options represents the BEST course of action?
A CM is milling and paving a 2-mile-long bridge with a surface that is in total failure. The owner gave the contractor October 24 as the fixed completion date. Meanwhile, the owner has promised the public that work hours would be 7am–7pm, 5 days per week and that the bridge would be completed by September 1.
The bridge deck is poured on a steel grid deck, but this type of operation has never been performed in the state and complications from weather have slowed progress. The contractor has requested to work nonstop 24/7 to meet the deadline told to the public.
The CM should