An experienced project manager is working on a complex hybrid project that has several dependencies with other projects. How should the project manager reduce the risk related to those external
dependencies?
A steering committee member is complaining about the weekly report. They stated that the report is too long and has unnecessary details. As a result, they are unable to
obtain the main message and take action.
What should the project manager do to avoid similar complaints?
A research and development team is finishing up a two year initiative. The project manager is focused on the closing activities for the project.
Which activity should be considered as a priority?
A network transformation project to increase efficiency and return on investment (ROI) is in the implementation stage. A conflict between the head of the network and the
transformation manager arises.
What should the project manager do to manage this?
An agile senior project team member suddenly resigns from the organization. Following this departure, the remaining team members are having difficulty accessing information and are unable to complete a
deliverable.
What should the project manager have done to avoid this situation?
A project manager has noticed that the performance of a new team member has increased dramatically over the past fewmonths. The project manager hasbeen measuring this team member's performance through the cost performance index (CPI) and schedule performance index (SPI) of work packages. The
project manager has also assigned new, unrelated work packages to this team member. The project manager wants to formally record the team member'ssuccess in the project documentation.
What should the project manager do?
A project manager acquired information from the market that would reduce the business value being delivered by an ongoing project. Based on that information, the project manager believes the project shouldbe stopped.
How should the project manager handle the situation?
A team has been working on a project for several months, but the completion date is unclear because the scope is changing frequently as new knowledge is gained. Some
deliverables have already been completed, but when new stakeholders join the team, they complain that project outcomes are not meeting business goals.
How can the project manager prevent this situation from happening in the future?
During the daily standup meeting that is assessing progress against the current sprint, a team member reports some delays due toacomponent managed by an external vendor. How should the project manager address the team member's concern?
The project management office (PMO) assigns a project manager who specializes in hybrid approaches to apredictive project that is offtrack from both the cost and schedule perspectives. The project runs into further delays as the project manager is ramping up on theproject. The stakeholders are unhappy and ask senior management to replace the project manager.
How should the project manager approach this situation?
Ateam lead for a project that is currently in execution with multiple delivery teams is issuing status updates. This communication was not discussed with the project manager, and the project stakeholders areconcerned about nonalignment since other teams are not providing these updates.
What should the project manager do?
A new project manager is assigned to an ongoing agile innovation project that started 2 weeks ago. After reviewing the project, the new project manager discovered that the previous
project manager was planning to use a predictive approach. The previous project manager planned to present the first major deliverable to the client when the project was completely
finished in 8 months.
What should the new project manager do?
project is currently in the execution phase. Because of the complexity of the project and the large number of regulatory requirements involved,theproject manager decides to hold a management review with senior executives to ensure the successful implementation of project deliverables.
What should the project manager review during the management review to ensure the meeting is effective?
An agile project manager notices that one of the team members is developing extensive knowledge in a specific matter. Other team members are likely to require this
knowledge in the future.
What should the agile project manager do?
A project is in the final stages, and a key stakeholder demands a change to a product feature that will add 2 weeks to the critical path. What should the project manager do?
A project manager is meeting with the project sponsor regarding a new project. The project manager tells the sponsor that, as part of the communications management plan, a weekly email will be sent with thestatus of the project, so the sponsor can be informed of the progress. The sponsor indicates that the email is not necessary because they will ask for a status update whenever it is needed.
What should the project manager do next?
A project manager is assigned midway through a project. The team members are in different locations across the country and they are unable to meet in-person often. During a status review meeting, one of
the stakeholders highlighted that they were unaware of the status for the project deliverables.
What should the project manager do first?
A client wants to create an innovative software for the travel industry using an agile approach. A project manager from the company was assigned
to work on the details and estimates as requested by the client.
What should the project manager do before sending the information to the client?
During a project's closing phase, the project manager identified that the client did not use one particular service. The client then asks the project manager to informally extend the service beyond the contract
end date. The contract is clear about the expiration of the service.
How should the project manager address this situation in order to close the project?
A project team is prioritizing the creation of project artifacts and enforcing it rigidly, while they face issues with delays in deliverables.How should the project managerrespond?
During the planning stage of a project the project manager realizes that a standard stakeholder engagement approach will not suffice. One of the client representatives, who
is not a key decision maker, is extremely opinionated. This client representative could become a roadblock to progress due to their perceived level of authority during
meetings.
How should the project manager handle this moving forward?
A project sponsor has requested that the project manager reprioritize the team's tasks to include a feature that is not part of the minimum viable product (MVP) for the project. Although the project sponsor isvery keen on the feature, adding it has the potential of causing team burnout and/or delaying the release.
How should the project manager address this situation?
A project manager at a large corporation has been assigned to oversee a customer experience project. Within the project,customer satisfaction is a bigissue and there are many unresolved customer queries on a daily basis. The project manager has been informed that the customer service team isoverwhelmed with these unresolved queries.
Which two actions should the project manager take to correct this problem? (Choose 2)
A project manager has recently been asked to take over an existing project. The project manager would like to determine how the project has been progressing by tracking features that are in progress,
completed, or scheduled to be worked on.
Which of the following can help the project manager assess the state of the project?
An organization is about to start a multiphased project. Due to strict regulations, some of the phases must be completely planned in advance. However, other phases allowfor more flexibility and experimentation on scope and schedule. The sponsor wants to pursue the project objectives as planned, butalso wants to accommodate newinformation and changes as the project progresses.
Which project management approach should the project manager select for this project?
A project team member complained to the project manager that they are not sure if they are working on the latest requirements document because it was emailed to them about one week ago. They mentioned that, in the past, they worked on a document for more than 20 hours only to find out later that another team member had already updated that same document but did not send them the latest revisions.
What should the project manager do to avoid this situation in the future?
An agile project team discovers that they are unable to implement a feature completely in the first iteration. The team believes it may not be able to complete the tasks in the
second iteration. The feature is a critical component that the customer has prioritized.
What should the team do?
A project team is conducting sprint planning. Based on the estimated effort, only 95% of the items included in the sprint may be delivered. The product owner asks theproject manager for advice on how to prioritize the backlog items.
What should be used to prioritize the backlog items?
A project manager was recently assigned to a banking IT project. The project team has been developing products using a predictive approach for more than 10 years, butmanagement wants the team to change to an agile approach. The project manager met with the team to introduce the agile approach.Most of the team memberscomplained about changing approaches because the performance of this team has always been above average among the IT teams in the bank.
Which two actions should the project manager take? (Choose 2)
The product team is progressing with a prototyping approach to deliver a multiyear business initiative. A few user stories are taking longer to be delivered.
What should the project manager do?
A project manager implementing a hybrid project is dealing with multiple stakeholders in a rapidly changing business environment. How should the project manager ensure that the needs of stakeholders are consistently met?
A project manager is assigned to a major construction project. The project is critical to the city's population, and especially to the local government official who committed to
delivering the project on time as an election promise. A new project sponsor has been assigned and wants to include aspects that the previous project sponsor did not
support,
What should the project manager do next?
At a project status meeting, different activities were agreed upon for the following weeks. At the end of the first week, the project team
realizes that the activities were executed in the wrong way because each team member had a different understanding. These
misunderstandings have caused a delay in the project.
Which of the following actions should the project manager take to avoid this situation in the future?
A project manager is assigned to a project with a long time line and complex scope. The client requires a high-level, long-termplan as well as something thatwill work immediately, adding features to the product as the project progresses.
How should the project manager plan and deliver this project?
A company has decided to initiate a project to eliminate a sales channel that has been unprofitable for the past 3 years. Some members of the project team are pessimisticabout the project.
What should the project manager do in this situation?
A project manager is leading a global project with resources spread out in different locations. The stakeholders have different interpretations of therequirements. The project manager is concerned about scope creep.
Which action should the project manager take to control the scope?
Two members of a new project team disagree on the best approach to solve a problem. The conflict has been going on for 1 week. The two
members are tense around each other and are taking everything personally.
What should the project manager do?
A project manager has been approached by the project sponsor about adding fo the project scope. How should the project manager accommodate this request?
A project interfaces with other projects that are in the same portfolio but are being developed in international locations. One ofthe international projects hassuggested a tactical change that needs to be implemented in this project.
What should the project manager do next?
The client will not agree to closure, claiming that the project team has not performed the code inspections mandated in the development contract. The project team has
performed the code inspections, however the records are not complete.
What should the project manager do?
A project for developing software for a retail company's procurement system is in the initiation phase. The project sponsor has expressed concern that the forecasted project implementation date coincides withthe company's financial budget planning period.
Which two actions should the project manager take next to address this concern? (Choose two)
While managing a project, the project manager has just noticed that the last several monthly invoices have been challenged by the client when they were clearly defined.
The actual invoice payments received have also been late and were outside of the contracted payment schedule. Recent invoices have only been partially paid.
What should the project manager do?
A company is initiating a project to enhance one of its existing products. All of its products are developed internally.
What should the project manager do?
A project manager is working on a project for a startup company. The company launched cloud-based agile project management and DevOps training modules via the learning platform to support multiple self-paced and virtual learning formats. In a recent sprint, the quality assurance team failed to thoroughly inspect the modules before deployment, resulting in a poor customer experience.
Which of the following issues is the project manager facing?
A hybrid project has just deployed, and the project manager is planning project closure with lessons learned workshops. A key stakeholder informs the project manager that
having the Scrum team in the workshops is a waste of time because the project was delivered successfully.
What should the project manager do?
During an agile team retrospective, a project team member mentions that the code quality is degrading, which might result in future rework that could becomeunmanageable with time. What should the project manager do?
By the end of the first sprint, a project lead notices that one of the team members is not performing very well. Which form of communication should the
project lead use to handle the situation?
An information technology (IT) team is responsible for the validation and release of a product developed by the agile development team. Due to other priorities for the IT team, the releases are delayed.
What action should the project manager take?
A project manager is working on a major construction project. Part of the agreed-upon plan was to use a cloud-based system with a server that runs on high-speed internet
service since most of the team members work virtually. The company needs to reduce operating costs as much as possible and management insists that the project will now
use a system running on a conventional dial-up service.
What should the project manager do next?
A project manager has been selected to deliver one of an organization's key flagship solutions. Critical success factors include agility, market adaptation,and a quick response to market offerings.
What is one of the key activities that the project manager should undertake to ensure company success?
During project execution, a project manager discovers that the budget at completion has shifted significantly and is higher than expected.
What should the project manager do?
A project manager has just been assigned to a team that is developing a new design product. The work breakdown structure (WBS) has been created and the activities have been assigned to the team members. The project manager finds that there are activities that could be completed sooner by other team members. If the current assignments are left as is, the project could be delayed 2 weeks.
What should the project manager do in this situation?
A project manager has been assigned to a global project involving regulatory bodies, government agencies, internal company leaders, the
project team, and end users. What should the project manager do to engage them all effectively?
In a project, one core team member tends to do all the work and ensures all tasks are completed. This core team member is soon leaving the project, which may make the
project vulnerable.
What should the project manager do?
A project team is working hard to reach a milestone. The team morale is low because of the extended hours worked to meet the deadline.
Adding to this tension is the fact that the team works remotely, and there has been little time to build relationships or get to know team members beyond the tasks that everyone performs.
What should the project manager do to address the remote team's morale?
A company initiated a project to introduce a new product to the market. The product must undergo the industry's regulatory process prior to approval and launch. However, the company sees a great demand
for this product and wants it to launch as soon as possible.
What should the project manager do to realize this opportunity?
A project manager is leading an agile project in an organization that has not executed this type of project before. In order to ensure the project is following the compliance requirements, what should the project manager do?
An agile project started 6 months ago. Since the beginning of the project, there have been disagreements among team members regarding daily meetings since some of the team members are not available at the same time. The project manager is convinced an agile team should be self-organizing, and that meeting times should be worked out by the team.
What should the project manager do?
The marketing team is transitioning to using hybrid approaches for their projects. The marketing director is not knowledgeable about hybrid
methodologies, and the project manager needs the director's support as the marketing director is a key stakeholder.
What should the project manager do to obtain the support?
A company is transitioning from a predictive to an agile approach. During the last two sprint reviews, the product owner complained about the development team, indicating that the
increments do not meet the acceptance criteria defined in the user stories. The development team complained about the product owner, who is defining sprint backlog items, because
the backlog items cannot be delivered during the 2-week sprints agreed to at the beginning of the project.
How should the project manager resolve this situation in their new role as servant leader?
Ateam is not delivering the committed work. Cards are not moving on the kanban board, and the burndown chart shows that the sprint progress is slow.
What should the agile project manager do?
After the merger of two large companies, a project manager is assigned to a project. The company hires a consultant to ensure best practices are being used in information security. During an iteration, the consultant requests changes to a software component, claiming that it is not meeting market requirements.
What should the project manager do?
A project manager prepared a project benefits management plan. Which of the following should be included in this document?
A project team is having difficulties understanding technical details regarding requirements. The information was not initially provided by the customer, butthe information is critical in the current iteration for clarification on how tasks need to be accomplished.
How should the project manager approach this situation?
At the end of a project with multiple suppliers, the project manager is reviewing the closing process and finds that an unexpected financial balance is remaining. What will
help the project manager understand why this has occurred?
A project manager has recently moved to an organization to lead a key project. The project manager notices that team performance is
below the target, and the tasks assigned are not delivered on time. Team commitment is also not as appropriate as it should be.
What should the project manager do?
A project team began working on a complex project that involves new technology as a product. The team is new to the technology and the proposed approach. Additionally,
the customer is apprehensive about how the product will be received in the market.
What should the project manager do to help the team and the customer?
In a complex development project with many clients and team members, there have been delays in completing the required work. What should the project manager do?
A large corporation is transforming itself from a predictive to agile approach. A project team with knowledge of agile practices is experiencing significant conflicts with the
executives regarding the processes to be followed.
How should these conflicts be resolved?
A project is starting its third iteration out of six. During planning, the team realized that all of the requirements were not defined clearlyenough to start working.
What should the project manager do?
While following up on a deliverable, a team member expresses concern to the project manager about working with another team member. This team member states that the other team member, who is a functional manager, is often defensive and aggressive during meetings.
How should the project manager handle this situation?
A project team is working to deliver a solution to manage nationwide crisis relief operations. The project team is spending most of its time in
meetings with end users. The meetings have been slowing down project progress.
What should the project manager do to keep the deployment on track while obtaining stakeholder approval?
An organization is using a hybrid delivery approach for a complex project. In the iteration review, a senior manager is asking for a complete redesign of the functionality presented.This may require a significantchange in the technical architecture and an additional release.
What should the project lead do first?
A key team member informs the project manager that they have been accepted to a master's degree program. The team member explains that the first semester of the master'sprogram will coincide with thelast phase of the project.
What should the project manager do?
A laboratory is launching a new product, defined to be executed in eight iterations with a fixed release date. At the beginning of the second iteration, the project managerrealizes that a significant regulatory feature is missing in the project backlog.
What should the project manager do?
A project manager has taken over an agile project. There have been several issues during product development due to unclear product requirements.
How should the project manager resolve this issue?
A project manager in an automotive company is scheduling activities for a complex project Some of the project requirements are fixed and some are flexible Match the items on the left with the methodology on the right that the project manager is using.
A project manager is leading a project in an organization that has a functional structure. The project manager has been informed by the team that the tasks related to the
purchase of services are taking too long, as the purchasing department has other priorities.
What should the project manager do?
A project manager is using an agile approach. During the sprint planning meeting, the product owner flagged a backlog item as high business value and easy to implement.
However, the other team members identified a high dependency between this item and another item that is flagged as low business value and high complexity.
What should the project manager do to support the backlog prioritization?
A project manager is assigned to a project related to taxes, which will be managed using an agile approach. By reviewing lessons learned from a previous project, the
project manager discovers that a key stakeholder is an expert on taxes and is willing to help.
How should the project manager leverage this information?
A project manager for an application development firm is meeting with stakeholders prior to the launch of the latest release of the company's most profitable application. The stakeholder mentions the following key points:
• A major corporate rebrand was scheduled to occur with this launch, but the rebrand has been delayed by 3 weeks.
• Development processing improvements will be ready in 4 weeks.
• The company is preselling the updated product with a release date of next week.
Which action should the project manager recommend to the sponsor?
One of the team members is always late to the daily standup meeting. What should the project manager do?
A senior project manager is assigned to lead a team of project managers to run a large initiative. Oneof the key stakeholders oftenbypasses the senior project manager and gives instructions to the other project managers directly.
What should the senior project manager do?
A project manager is leading a global team that they have worked with in the past and has a high level of trust with them. The team is located in different countries and time zones and will need decisions in a
timely manner.
In order to ensure that the project runs smoothly across the team, how should the project manager approach delegation?
A project requires the procurement of a large amount of equipment that needs to be on-site before any other activity can begin. The procurement department has a lengthy
approval process.
What should the project manager do?
A new project has been kicked off following a planning session. The project is under direct oversight of an executive in the organization. After a review meeting, the project manager overhears an executive request a dashboard from one of the team members to show the overall project status.
What should the project manager do?
A project manager has been hired to lead a governance consulting project that is in the initial phase. The project manager has been assigned to evaluate the supplier search activity. There are many interested
candidates, including former suppliers and suppliers recommended by the sponsor.
What should the project manager do in this situation?
A project sponsor is promoting the use of a new technology that has not yet been approved. The technology guarantees cost savings and a delivery ahead of schedule. However, the operational support atproject completion is uncertain as the service organization expressed an inability to provide support without approval of the new technology.
What should the project manager do to resolve the conflict?
An agile project is approaching its first release date, and the product will be supported by the operations team. To ensure proper support for the product, what should the project manager do?
A mid-size capital project has shared resources from the company's contract department. During the execution phase, the project team observed a delay in contracting. After
communicating with the contract department, the project manager found the contract team is prioritizing other contracting jobs because they are not part of the project team.
What should the project manager do first in this situation?
A project manager has been managing a project for several months when an issue that had not been registered as a risk appeared. This issue may have a big impact on the
project.
What should the project manager do?
A project is scheduled to end in 2 weeks. The team is expected to continue working long hours and is showing signs of weariness and fatigue.
What should the project manager do to encourage the team?
In an agile project, the team planned to complete 40 story points in an iteration, but only completed 30 story points. What is the scheduleperformance index (SPI)?
A project manager has been assigned to a project that involves building 100 wells for a small community that is urgently in need of access
to water. What should the project manager do next?
A new marketing vice president just joined a software startup and is concerned that the agile model does not provide the needed accountability for their role.What should the responsible project manager do to ensure the vice president is comfortable with the project meeting its agreements?
The project team is experiencing schedule delays due to issues arising with suppliers. Some of the tasks are on the critical path.
What should the project manager do in this situation?
A project is being planned to deliver a proof of concept to evaluate technology compatibilities. The business and project stakeholders are having difficulty agreeing on what should be included in the final
product.
What should the project manager do?
A project sponsor wants to develop software that would have 30 features and would be used in 10 different countries. The team feels overwhelmed with the amount of work to be done.
What should the project manager do?
Organizational downsizing has resulted in the key subject matter expert (SME) resource leaving a multiyear project. What should the project manager do?
A company has decided to implement a new archiving system. A data breach occurred during the implementation of the project.
What should the project manager do first?
A project manager assigned team members to work in pairs on a large amount of technical reports. At times, the project manager noticed that important information was not shared properly among the team.
This has caused delivery delays and, ultimately, the failure to complete the project.
What is the root cause of this issue?
During the final stage of the launch for a new design, team members are having a conflict about some features of the design. What should the project manager do?