Labour Day Sale - Limited Time 60% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 575363r9

Welcome To DumpsPedia

PMP Sample Questions Answers

Questions 4

An experienced project manager is working on a complex hybrid project that has several dependencies with other projects. How should the project manager reduce the risk related to those external

dependencies?

Options:

A.

Schedule a daily interproject review to track the progress of each project plan and their dependencies.

B.

Assess consolidated project plans for dependencies, gaps, and continued business value.

C.

Ask the project management office (PMO) to review the project plan dependencies.

D.

Delegate the review of dependencies to the project sponsor and resource manager.

Buy Now
Questions 5

A steering committee member is complaining about the weekly report. They stated that the report is too long and has unnecessary details. As a result, they are unable to

obtain the main message and take action.

What should the project manager do to avoid similar complaints?

Options:

A.

Send a shorter daily report to this steering committee member.

B.

Demonstrate the weekly reports in a presentation for the steering committee member.

C.

Verify the information needed for steering committee members.

D.

Present the status at a weekly meeting with the steering committee.

Buy Now
Questions 6

A research and development team is finishing up a two year initiative. The project manager is focused on the closing activities for the project.

Which activity should be considered as a priority?

Options:

A.

Mark the product backlog completion status and update the communications management plan.

B.

Release the resources and plan for a project completion celebration.

C.

Hold a steering committee meeting to inform them of the project completion.

D.

Ensure that knowledge transfer activities are executed as planned.

Buy Now
Questions 7

A network transformation project to increase efficiency and return on investment (ROI) is in the implementation stage. A conflict between the head of the network and the

transformation manager arises.

What should the project manager do to manage this?

Options:

A.

Analyze the context of the issue.

B.

Evaluate the influence of the parties involved.

C.

Lead the parties to find a compromise.

D.

Escalate the problem to the project sponsor.

Buy Now
Questions 8

An agile senior project team member suddenly resigns from the organization. Following this departure, the remaining team members are having difficulty accessing information and are unable to complete a

deliverable.

What should the project manager have done to avoid this situation?

Options:

A.

Updated the job descriptions for all team roles.

B.

Ensured the project repository is up to date.

C.

Made an effort to reemploy the senior project team member.

D.

Provided specialist training for all team members.

Buy Now
Questions 9

A project manager has noticed that the performance of a new team member has increased dramatically over the past fewmonths. The project manager hasbeen measuring this team member's performance through the cost performance index (CPI) and schedule performance index (SPI) of work packages. The

project manager has also assigned new, unrelated work packages to this team member. The project manager wants to formally record the team member'ssuccess in the project documentation.

What should the project manager do?

Options:

A.

Attach a note to the project management plan about the team member.

B.

Send a communication to management recognizing the team member's contributions.

C.

Hold a project team meeting about the team member's contribution and take minutes.

D.

Record the team member's contribution in the responsibility assignment matrix (RAM).

Buy Now
Questions 10

A project manager acquired information from the market that would reduce the business value being delivered by an ongoing project. Based on that information, the project manager believes the project shouldbe stopped.

How should the project manager handle the situation?

Options:

A.

Have a discussion with the project sponsor and cancel the project.

B.

Have a discussion with the sponsor and recommend the project business value be reassessed.

C.

Remove the items no longer applicable from the backlog and present the backlog to the project team.

D.

Continue working on the defined scope and review the risk matrix.

Buy Now
Questions 11

A team has been working on a project for several months, but the completion date is unclear because the scope is changing frequently as new knowledge is gained. Some

deliverables have already been completed, but when new stakeholders join the team, they complain that project outcomes are not meeting business goals.

How can the project manager prevent this situation from happening in the future?

Options:

A.

Create a detailed work breakdown structure (WBS) and milestone schedule approved by all stakeholders.

B.

Create a prioritized backlog and define iteration review sessions with stakeholders.

C.

Schedule a kick-off meeting for every project phase to share the project management plan with all stakeholders.

D.

Schedule a daily meeting to review team performance and impediments.

Buy Now
Questions 12

During the daily standup meeting that is assessing progress against the current sprint, a team member reports some delays due toacomponent managed by an external vendor. How should the project manager address the team member's concern?

Options:

A.

Implement fast tracking to reduce the impact of the delay on the sprint.

B.

Ask the team member to provide details to address the issue with the vendor.

C.

Update the communications management plan to prevent future reoccurrence.

D.

Ask the team member to resolve the issue independently to minimize further delays.

Buy Now
Questions 13

The project management office (PMO) assigns a project manager who specializes in hybrid approaches to apredictive project that is offtrack from both the cost and schedule perspectives. The project runs into further delays as the project manager is ramping up on theproject. The stakeholders are unhappy and ask senior management to replace the project manager.

How should the project manager approach this situation?

Options:

A.

Socialize with the stakeholders to better understand their needs and reset expectations.

B.

Escalate the stakeholder issue to the management team and ask for help with resolving the conflict.

C.

Continue to work on the project until the stakeholders and management come to a decision.

D.

Meet with the stakeholders to understand their concerns and define an action plan to resolve issues.

Buy Now
Questions 14

Ateam lead for a project that is currently in execution with multiple delivery teams is issuing status updates. This communication was not discussed with the project manager, and the project stakeholders areconcerned about nonalignment since other teams are not providing these updates.

What should the project manager do?

Options:

A.

Instruct the team lead to stop sending the update report.

B.

Examine the project reporting requirements with the stakeholders.

C.

Discuss with the team lead to understand the reason for the report.

D.

Tell the other team leads to provide similar update reports.

Buy Now
Questions 15

A new project manager is assigned to an ongoing agile innovation project that started 2 weeks ago. After reviewing the project, the new project manager discovered that the previous

project manager was planning to use a predictive approach. The previous project manager planned to present the first major deliverable to the client when the project was completely

finished in 8 months.

What should the new project manager do?

Options:

A.

Meet with the team to review the backlog and create small iterations that can deliver incremental value to the client.

B.

Continue working with the predictive approach to deliver the value at the end of the project.

C.

Use a hybrid approach in which agile practices are used but the value is provided to the client at the end of the project.

D.

Submit a change request to the project board to adjust the delivery date to 2 months earlier than planned.

Buy Now
Questions 16

project is currently in the execution phase. Because of the complexity of the project and the large number of regulatory requirements involved,theproject manager decides to hold a management review with senior executives to ensure the successful implementation of project deliverables.

What should the project manager review during the management review to ensure the meeting is effective?

Options:

A.

The deliverables that are performing well and those that need more work.

B.

Specialized reports created specifically for the meeting as per directions from the project sponsor.

C.

Potential changes to the project's strategy and the feedback from senior executives.

D.

Metrics and key performance indicators (KPIs) that objectively reflect the status of deliverables.

Buy Now
Questions 17

An agile project manager notices that one of the team members is developing extensive knowledge in a specific matter. Other team members are likely to require this

knowledge in the future.

What should the agile project manager do?

Options:

A.

Ask the team member to produce a lessons learned document and share it with the team.

B.

Ask the team member to develop more expertise and become a subject matter expert (SME).

C.

Ask the team member to record highlights the team may want to know.

D.

Ask the team member to provide a training session for the rest of the team.

Buy Now
Questions 18

A project is in the final stages, and a key stakeholder demands a change to a product feature that will add 2 weeks to the critical path. What should the project manager do?

Options:

A.

Reject the changes as the project is in the final stages.

B.

Perform a detailed assessment to analyze the impact.

C.

Use schedule compression methods to alter the critical path.

D.

Initiate a risk response strategy from the risk register.

Buy Now
Questions 19

A project manager is meeting with the project sponsor regarding a new project. The project manager tells the sponsor that, as part of the communications management plan, a weekly email will be sent with thestatus of the project, so the sponsor can be informed of the progress. The sponsor indicates that the email is not necessary because they will ask for a status update whenever it is needed.

What should the project manager do next?

Options:

A.

Ask the project sponsor what sort of information is needed and agree on a frequency for the communication.

B.

Tell the project sponsor that if they prefer to not receive the communication, there is no problem in removing them from the email distribution.

C.

Advise the project sponsor to request a 15-minute meeting, whenever necessary, with prior notification.

D.

Agree to the project sponsor's request, but continue to copy them on the weekly email so they can be informed of progress in case it is needed.

Buy Now
Questions 20

A project manager is assigned midway through a project. The team members are in different locations across the country and they are unable to meet in-person often. During a status review meeting, one of

the stakeholders highlighted that they were unaware of the status for the project deliverables.

What should the project manager do first?

Options:

A.

Request the project team include the stakeholder's details and make sure the project status reports are shared with the stakeholder.

B.

Schedule a meeting with the stakeholder, and include the stakeholder’s needs in the project management plan.

C.

Review the stakeholder management plan and update the stakeholder register for incorporation in the project management plan.

D.

Review the communications management plan and verify whether the stakeholder's needs are captured in the project management plan.

Buy Now
Questions 21

A client wants to create an innovative software for the travel industry using an agile approach. A project manager from the company was assigned

to work on the details and estimates as requested by the client.

What should the project manager do before sending the information to the client?

Options:

A.

Analyze the tasks, provide estimates, include a prototype demo, and send to the client directly.

B.

Sequence the tasks with estimates and add standard risk reserves to use for software development.

C.

Put the tasks with estimates in the backlog and clarify that the project will not need any reserves.

D.

Work with the team to understand their views and add the appropriate dependencies and risks.

Buy Now
Questions 22

During a project's closing phase, the project manager identified that the client did not use one particular service. The client then asks the project manager to informally extend the service beyond the contract

end date. The contract is clear about the expiration of the service.

How should the project manager address this situation in order to close the project?

Options:

A.

Issue a change request and activate the formal change control process to address the situation.

B.

Escalate the request to the functional manager to approve the additional service hours.

C.

Deny the request and include it in lessons learned documentation for the next contract renewal.

D.

Accept the client's proposal to use the service until the additional hours are exhausted.

Buy Now
Questions 23

A project team is prioritizing the creation of project artifacts and enforcing it rigidly, while they face issues with delays in deliverables.How should the project managerrespond?

Options:

A.

Implement stricter controls so that project artifact creation is given the utmost importance.

B.

Facilitate the implementation of an automated tool for the team to manage project artifacts.

C.

Advise the team that solely focusing on artifacts will not produce successful project deliverables.

D.

Recognize the team’s efforts for documenting artifacts and motivate them with an incentive mechanism

Buy Now
Questions 24

During the planning stage of a project the project manager realizes that a standard stakeholder engagement approach will not suffice. One of the client representatives, who

is not a key decision maker, is extremely opinionated. This client representative could become a roadblock to progress due to their perceived level of authority during

meetings.

How should the project manager handle this moving forward?

Options:

A.

Update the project schedule to cater to this particular stakeholder.

B.

Allocate time to gain buy-in from the stakeholder prior to key decision meetings.

C.

Ask that only key decision makers attend the project meetings. O

D.

Update the risk register to consider the possible project impacts.

Buy Now
Questions 25

A project sponsor has requested that the project manager reprioritize the team's tasks to include a feature that is not part of the minimum viable product (MVP) for the project. Although the project sponsor isvery keen on the feature, adding it has the potential of causing team burnout and/or delaying the release.

How should the project manager address this situation?

Options:

A.

Ensure the feature's tasks are included in the iteration backlog, explain to the sponsor the consequences of the request, and ask the team to deliver the feature in the current iteration.

B.

Ensure the feature has been included in the product backlog, then hold a meeting with the team and sponsor to determine how to deliver the feature within the current iteration.

C.

Ensure the feature is included in the iteration backlog, ask the team to work on the current tasks first, and include the new tasks after those tasks are completed.

D.

Ensure the feature has been included in the product backlog, explain to the sponsor the consequences of the request, and ask the team to include the features tasks in the next iteration.

Buy Now
Questions 26

A project manager at a large corporation has been assigned to oversee a customer experience project. Within the project,customer satisfaction is a bigissue and there are many unresolved customer queries on a daily basis. The project manager has been informed that the customer service team isoverwhelmed with these unresolved queries.

Which two actions should the project manager take to correct this problem? (Choose 2)

Options:

A.

Ask senior management to replace the customer service manager with a more qualified one.

B.

Contact the customers in batches and inform them that the issues are being worked on currently.

C.

Deploy solutions that will track, prioritize, and resolve queries as soon as possible.

D.

Request that the customer service team prioritizes work on queries that are received this week.

E.

Confirm the issues truly exist by conducting a survey and other analyses that may detect the real issue.

Buy Now
Questions 27

A project manager has recently been asked to take over an existing project. The project manager would like to determine how the project has been progressing by tracking features that are in progress,

completed, or scheduled to be worked on.

Which of the following can help the project manager assess the state of the project?

Options:

A.

Pareto diagram

B.

Burnup chart

C.

Burndown chart

D.

Cumulative flow diagram

Buy Now
Questions 28

An organization is about to start a multiphased project. Due to strict regulations, some of the phases must be completely planned in advance. However, other phases allowfor more flexibility and experimentation on scope and schedule. The sponsor wants to pursue the project objectives as planned, butalso wants to accommodate newinformation and changes as the project progresses.

Which project management approach should the project manager select for this project?

Options:

A.

Hybrid

B.

Agile

C.

Phased

D.

Incremental

Buy Now
Questions 29

A project team member complained to the project manager that they are not sure if they are working on the latest requirements document because it was emailed to them about one week ago. They mentioned that, in the past, they worked on a document for more than 20 hours only to find out later that another team member had already updated that same document but did not send them the latest revisions.

What should the project manager do to avoid this situation in the future?

Options:

A.

Implement a project management information system (PMIS).

B.

Encourage better team communication by positioning team members closer together.

C.

Update the communications management plan to ensure correct delivery of the latest version.

D.

Restrict team members from sending the requirements documents via email.

Buy Now
Questions 30

An agile project team discovers that they are unable to implement a feature completely in the first iteration. The team believes it may not be able to complete the tasks in the

second iteration. The feature is a critical component that the customer has prioritized.

What should the team do?

Options:

A.

Reduce the scope of the feature to fit into one iteration and deliver it to the customer.

B.

Go back to the customer and explain that they cannot implement the feature completely in one iteration.

C.

Split the feature into smaller subfeatures, implement them, and then deliver them incrementally in multiple iterations.

D.

Ask the customer to simplify the feature so that it can be implemented in one iteration.

Buy Now
Questions 31

A project team is conducting sprint planning. Based on the estimated effort, only 95% of the items included in the sprint may be delivered. The product owner asks theproject manager for advice on how to prioritize the backlog items.

What should be used to prioritize the backlog items?

Options:

A.

Risk to delivery

B.

Technical complexity

C.

Estimation accuracy

D.

Business value

Buy Now
Questions 32

A project manager was recently assigned to a banking IT project. The project team has been developing products using a predictive approach for more than 10 years, butmanagement wants the team to change to an agile approach. The project manager met with the team to introduce the agile approach.Most of the team memberscomplained about changing approaches because the performance of this team has always been above average among the IT teams in the bank.

Which two actions should the project manager take? (Choose 2)

Options:

A.

Interview the most resistant team members to persuade them to try to accept an agile approach.

B.

Meet with management to explain the team's resistance to the agile approach and request that they formally ask the team to implement agile.

C.

Ask the team to identify the product backlog and create a kanban board for the team to manage and follow the approach.

D.

Brainstorm with the team to understand the specifics of the team's project and to identity possible alternative approaches for the team.

E.

Conduct training sessions with the team so that the team can understand what the agile approach and mindset are.

Buy Now
Questions 33

The product team is progressing with a prototyping approach to deliver a multiyear business initiative. A few user stories are taking longer to be delivered.

What should the project manager do?

Options:

A.

Inform stakeholders about the delay during project updates.

B.

Determine cross-dependencies and plan a spike in the next sprint.

C.

Discover the gaps in the communications management plan and address them accordingly.

D.

Determine the risks and identify a resolution during the retrospective meeting.

Buy Now
Questions 34

A project manager implementing a hybrid project is dealing with multiple stakeholders in a rapidly changing business environment. How should the project manager ensure that the needs of stakeholders are consistently met?

Options:

A.

Use iterative life cycles involving stakeholders to enable the team to improve the product end result through successive prototypes.

B.

Identify all the critical stakeholders during project initiation.

C.

Assign one team member to one stakeholder to ensure that the responsible team member is conversant with the needs of the stakeholder.

D.

Add more iterative techniques to improve stakeholder learning.

Buy Now
Questions 35

A project manager is assigned to a major construction project. The project is critical to the city's population, and especially to the local government official who committed to

delivering the project on time as an election promise. A new project sponsor has been assigned and wants to include aspects that the previous project sponsor did not

support,

What should the project manager do next?

Options:

A.

Inform the new project sponsor that the new aspects will not be included in this project.

B.

Meet with the new project sponsor to review the current project scope and the requested changes.

C.

Invite the project sponsor to a briefing with the project team to demonstrate progress and seek further support to meet project-committed deliverables.

D.

Rebaseline the project as there is now a new project sponsor, which is presenting an opportunity to review and recalibrate the project objectives.

Buy Now
Questions 36

At a project status meeting, different activities were agreed upon for the following weeks. At the end of the first week, the project team

realizes that the activities were executed in the wrong way because each team member had a different understanding. These

misunderstandings have caused a delay in the project.

Which of the following actions should the project manager take to avoid this situation in the future?

Options:

A.

Conduct reviews prior to performing activities.

B.

Use a common communication terminology.

C.

Monitor the team's performance metrics.

D.

Document the agreement in the meeting minutes.

Buy Now
Questions 37

A project manager is assigned to a project with a long time line and complex scope. The client requires a high-level, long-termplan as well as something thatwill work immediately, adding features to the product as the project progresses.

How should the project manager plan and deliver this project?

Options:

A.

Plan the project with a predictive approach and a work breakdown structure (WBS) following the plan and deliver value at the end of the project.

B.

Select an agile approach and manage the project according to best practices to ensure value is delivered to the client.

C.

Agree on a minimum viable product (MVP) first to be delivered immediately with the client and then release the restof the scope at the end of theproject.

D.

Plan the project with a predictive approach with a work breakdown structure (WBS) and then execute it using an agile approach to deliver valueincrementally.

Buy Now
Questions 38

A company has decided to initiate a project to eliminate a sales channel that has been unprofitable for the past 3 years. Some members of the project team are pessimisticabout the project.

What should the project manager do in this situation?

Options:

A.

Provide team members with specific and clear instructions on the project objectives and tasks.

B.

Communicate the project's impact and plans to engage the project team throughout the project.

C.

Escalate the team's concerns and ask the project sponsor to change the team's composition.

D.

Engage the functional managers to describe the project's impact to the team members directly.

Buy Now
Questions 39

A project manager is leading a global project with resources spread out in different locations. The stakeholders have different interpretations of therequirements. The project manager is concerned about scope creep.

Which action should the project manager take to control the scope?

Options:

A.

Accept only those changes that are approved by the change control board (CCB) prior to being implemented.

B.

Accept only those changes to requirements that provide additional value to the project.

C.

Ensure that all key stakeholders agree to the project deliverables and there will be no need for changes.

D.

Reject all changes that will increase the budget or increase the time line of the project.

Buy Now
Questions 40

Two members of a new project team disagree on the best approach to solve a problem. The conflict has been going on for 1 week. The two

members are tense around each other and are taking everything personally.

What should the project manager do?

Options:

A.

Send both team members to the human resources (HR) department for an acceptable resolution.

B.

Understand each team member's argument and select the one that results in less risk to the project.

C.

Help the team members to resolve the conflict in a way that results in the best team performance.

D.

Offer a compromise that is acceptable to both team members, even if it may not be the best solution.

Buy Now
Questions 41

A project manager has been approached by the project sponsor about adding fo the project scope. How should the project manager accommodate this request?

Options:

A.

Disregard the request since the project scope is finalized.

B.

Create a change request for the change control board (CCB) to review.

C.

Update the project team about the change request.

D.

Adjust the project schedule to accommodate the new project scope requests.

Buy Now
Questions 42

A project interfaces with other projects that are in the same portfolio but are being developed in international locations. One ofthe international projects hassuggested a tactical change that needs to be implemented in this project.

What should the project manager do next?

Options:

A.

Reject the change request since it may negatively impact the project's performance.

B.

Implement the change request as soon as possible to avoid accumulating new scope.

C.

Keep the focus on the priority items while the change goes through the change control process.

D.

Use the team's connections with international colleagues to get early warnings on future changes.

Buy Now
Questions 43

The client will not agree to closure, claiming that the project team has not performed the code inspections mandated in the development contract. The project team has

performed the code inspections, however the records are not complete.

What should the project manager do?

Options:

A.

Hold a meeting with the project team, project sponsor, and the client to agree to the further work required to close the project and add to lessons learned.

B.

Close the project and hand over the deliverables to the client.

C.

Hold a lessons learned workshop with the project team and project sponsor to avoid contractual compliance issues arising in future projects.

D.

Seek expert legal advice on the interpretation of the clauses in the contract.

Buy Now
Questions 44

A project for developing software for a retail company's procurement system is in the initiation phase. The project sponsor has expressed concern that the forecasted project implementation date coincides withthe company's financial budget planning period.

Which two actions should the project manager take next to address this concern? (Choose two)

Options:

A.

Facilitate a risk workshop with all stakeholders in attendance to identify and assess all risks to the project.

B.

Change the project implementation date so that the concern is alleviated and no longer applicable.

C.

Communicate to the project sponsor that the implementation date is low risk and will not impact the project.

D.

Advise the sponsor that it is not feasible to determine if the end date will be met as the project is in the initiation phase.

E.

Log the concern as a risk in the project risk register and assess the impact and severity of the risk.

Buy Now
Questions 45

While managing a project, the project manager has just noticed that the last several monthly invoices have been challenged by the client when they were clearly defined.

The actual invoice payments received have also been late and were outside of the contracted payment schedule. Recent invoices have only been partially paid.

What should the project manager do?

Options:

A.

Review past projects for payment-related lessons learned.

B.

Conduct a meeting with the project team to update the procurement management plan.

C.

Add nonpayment to the issue log and keep tracking payments.

D.

Hold a meeting with the client to address the issue.

Buy Now
Questions 46

A company is initiating a project to enhance one of its existing products. All of its products are developed internally.

What should the project manager do?

Options:

A.

Ensure the stakeholder engagement plan is accurate and properly documented.

B.

Create a lessons learned document for the initiation phase.

C.

Identify the risk of implementing the new solution and evaluate the impact on the project.

D.

Review the lessons learned from the previous project

Buy Now
Questions 47

A project manager is working on a project for a startup company. The company launched cloud-based agile project management and DevOps training modules via the learning platform to support multiple self-paced and virtual learning formats. In a recent sprint, the quality assurance team failed to thoroughly inspect the modules before deployment, resulting in a poor customer experience.

Which of the following issues is the project manager facing?

Options:

A.

Nonconformance issue

B.

Unmet planned-to-done ratio

C.

Undetected error

D.

Escaped defect

Buy Now
Questions 48

A hybrid project has just deployed, and the project manager is planning project closure with lessons learned workshops. A key stakeholder informs the project manager that

having the Scrum team in the workshops is a waste of time because the project was delivered successfully.

What should the project manager do?

Options:

A.

Ask the scrum master to attend the workshops.

B.

Ask the Scrum team members to share retrospectives.

C.

Invite the Scrum team members as mandatory participants.

D.

Invite the Scrum team members as optional participants

Buy Now
Questions 49

During an agile team retrospective, a project team member mentions that the code quality is degrading, which might result in future rework that could becomeunmanageable with time. What should the project manager do?

Options:

A.

Compare the cost of improving quality against the cost of failure and adjust the budget.

B.

Help the team create the definition of done (DoD) to improve delivery quality. 0 2 Add testing items to the backlog to assess quality periodically. oO

C.

Expand the team in order to improve the quality of the project.

Buy Now
Questions 50

By the end of the first sprint, a project lead notices that one of the team members is not performing very well. Which form of communication should the

project lead use to handle the situation?

Options:

A.

Informal written communication, such as a friendly reminder

B.

Formal verbal communication, such as a conversation at the end of the sprint retrospective

C.

Formal written communication, such as an email with a copy sent to the manager

D.

Informal verbal communication, such as a conversation

Buy Now
Questions 51

An information technology (IT) team is responsible for the validation and release of a product developed by the agile development team. Due to other priorities for the IT team, the releases are delayed.

What action should the project manager take?

Options:

A.

Work with the IT team to prioritize the validation and release of the new features.

B.

Escalate the issue from the IT team to management and get the validation prioritized.

C.

Request the IT team to immediately release the product and then validate the features.

D.

Deliver the features when the IT team is able to validate them.

Buy Now
Questions 52

A project manager is working on a major construction project. Part of the agreed-upon plan was to use a cloud-based system with a server that runs on high-speed internet

service since most of the team members work virtually. The company needs to reduce operating costs as much as possible and management insists that the project will now

use a system running on a conventional dial-up service.

What should the project manager do next?

Options:

A.

Meet with management about their decision and ask them to get another project manager.

B.

Agree with management and continue working the project management plan.

C.

Replace some of the team members that work virtually to help the company save money.

D.

Evaluate the impact of this decision and communicate with management.

Buy Now
Questions 53

A project manager has been selected to deliver one of an organization's key flagship solutions. Critical success factors include agility, market adaptation,and a quick response to market offerings.

What is one of the key activities that the project manager should undertake to ensure company success?

Options:

A.

Request more funding from the project sponsor to hire additional skilled resources and to incorporate additional quality in the project deliveryapproach and outcome.

B.

Conduct periodical reviews of the project plans, objectives, and deliverables to ensure all relevant data are captured to continue making informedproject decisions.

C.

Create a business case after performing a market review, and then submit it to the sponsor to modify the project deliverable to meet the newly definedobjectives.

D.

Review the project objectives with the project sponsor to agree on more realistic and achievable project plans and deliverables.

Buy Now
Questions 54

During project execution, a project manager discovers that the budget at completion has shifted significantly and is higher than expected.

What should the project manager do?

Options:

A.

Adjust the original budget estimates with the current cost variance.

B.

Perform a root cause analysis of the project performance.

C.

Review the activity duration to reforecast the project completion date.

D.

Negotiate the project changes and adjust stakeholder expectations.

Buy Now
Questions 55

A project manager has just been assigned to a team that is developing a new design product. The work breakdown structure (WBS) has been created and the activities have been assigned to the team members. The project manager finds that there are activities that could be completed sooner by other team members. If the current assignments are left as is, the project could be delayed 2 weeks.

What should the project manager do in this situation?

Options:

A.

Maintain the task assignments as planned and compress the other tasks to keep the project on schedule.

B.

Ask the team members to work overtime to finish the tasks on time according to the schedule.

C.

Keep the task assignments unchanged since the project management plan has been approved.

D.

Review the work allocation and reassign some tasks to shorten the critical path.

Buy Now
Questions 56

A project manager has been assigned to a global project involving regulatory bodies, government agencies, internal company leaders, the

project team, and end users. What should the project manager do to engage them all effectively?

Options:

A.

Analyze the stakeholders.

B.

Check lessons learned from past projects.

C.

Gather business requirements.

D.

Remove any bias that exists on the team.

Buy Now
Questions 57

In a project, one core team member tends to do all the work and ensures all tasks are completed. This core team member is soon leaving the project, which may make the

project vulnerable.

What should the project manager do?

Options:

A.

Ask human resources (HR) to counsel the team member to balance the workload.

B.

Assess a mechanism for knowledge transfer among the team members.

C.

Ensure the activities of this team member are distributed across the project team.

D.

Motivate the team member to stay by providing them with incentives.

Buy Now
Questions 58

A project team is working hard to reach a milestone. The team morale is low because of the extended hours worked to meet the deadline.

Adding to this tension is the fact that the team works remotely, and there has been little time to build relationships or get to know team members beyond the tasks that everyone performs.

What should the project manager do to address the remote team's morale?

Options:

A.

Plan a party to celebrate everyone's accomplishments after reaching the milestone.

B.

Evaluate the challenges and capture them with the team as part of the lessons learned.

C.

Offer opportunities for coworkers to interact beyond tasks, and model this behavior to create a safe space.

D.

Invite the team to a work retreat to allow the team to build relationships in person and reach the milestone as planned.

Buy Now
Questions 59

A company initiated a project to introduce a new product to the market. The product must undergo the industry's regulatory process prior to approval and launch. However, the company sees a great demand

for this product and wants it to launch as soon as possible.

What should the project manager do to realize this opportunity?

Options:

A.

Hire a third party who is an expert on the industry's regulations to work out the details.

B.

Escalate the issue to the company's CEO who has experience with the regulations.

C.

Communicate with the industry's regulatory authority to grant the company an exception.

D.

Comply with the regulatory requirements and work to compress the project schedule.

Buy Now
Questions 60

A project manager is leading an agile project in an organization that has not executed this type of project before. In order to ensure the project is following the compliance requirements, what should the project manager do?

Options:

A.

Use the risk register to document all of the compliance vulnerabilities generated by the project so that all decisions are well documented and approved by stakeholders.

B.

Meet with the project management office (PMO)/compliance entity to work on process tailoring to ensure that the agile deliverables support the compliance requirements of the organization.

C.

Follow the organization's process and deliverables for predictive projects, even if they compromise the agility and performance of the project.

D.

Coach upper management on agile practices, explaining that an agile project is concerned with value delivery, and negotiate a way out of the compliance requirements.

Buy Now
Questions 61

An agile project started 6 months ago. Since the beginning of the project, there have been disagreements among team members regarding daily meetings since some of the team members are not available at the same time. The project manager is convinced an agile team should be self-organizing, and that meeting times should be worked out by the team.

What should the project manager do?

Options:

A.

Establish a project schedule.

B.

Assign a team leader.

C.

Recognize the team's contributions.

D.

Establish a team charter.

Buy Now
Questions 62

The marketing team is transitioning to using hybrid approaches for their projects. The marketing director is not knowledgeable about hybrid

methodologies, and the project manager needs the director's support as the marketing director is a key stakeholder.

What should the project manager do to obtain the support?

Options:

A.

Mentor the marketing director on hybrid approaches.

B.

Ask the marketing director to participate in daily meetings.

C.

Train the marketing team and keep the director informed.

D.

Ask the marketing team members to coach the director.

Buy Now
Questions 63

A company is transitioning from a predictive to an agile approach. During the last two sprint reviews, the product owner complained about the development team, indicating that the

increments do not meet the acceptance criteria defined in the user stories. The development team complained about the product owner, who is defining sprint backlog items, because

the backlog items cannot be delivered during the 2-week sprints agreed to at the beginning of the project.

How should the project manager resolve this situation in their new role as servant leader?

Options:

A.

Extend the sprints to 3 weeks to allow the work requested by the product owner to be completed.

B.

Request that the team use the next sprint to complete all technical debt remaining from the previous sprints.

C.

Encourage the whole team to be empowered and accountable for the decisions made according to their roles.

D.

Review the organizational process assets (OPAs) to find similar situations and review the resolution actions taken.

Buy Now
Questions 64

Ateam is not delivering the committed work. Cards are not moving on the kanban board, and the burndown chart shows that the sprint progress is slow.

What should the agile project manager do?

Options:

A.

Change the work in progress (WIP) limit to reflect the team's capacity.

B.

Discuss the performance with senior leadership.

C.

Meet with the project team members who are slow in delivering tasks.

D.

Consider the use of alternative performance metrics.

Buy Now
Questions 65

After the merger of two large companies, a project manager is assigned to a project. The company hires a consultant to ensure best practices are being used in information security. During an iteration, the consultant requests changes to a software component, claiming that it is not meeting market requirements.

What should the project manager do?

Options:

A.

Cancel the iteration and add the requested changes.

B.

Continue the iteration and add the requested changes.

C.

Continue the iteration and review the change with the customer.

D.

Cancel the iteration and meet with the product owner.

Buy Now
Questions 66

A project manager prepared a project benefits management plan. Which of the following should be included in this document?

Options:

A.

Target benefits, benefits owner, lessons learned

B.

Project requirements, target benefits, issue log, metrics

C.

Target benefits, strategic alignment, time frame for realizing benefits

D.

Strategic alignment, benefits owner, risk register

Buy Now
Questions 67

A project team is having difficulties understanding technical details regarding requirements. The information was not initially provided by the customer, butthe information is critical in the current iteration for clarification on how tasks need to be accomplished.

How should the project manager approach this situation?

Options:

A.

Educate the customer and have them participate in daily standup meetings. ®

B.

Request that the customer reviews and clarifies feature definitions for the current sprint.

C.

Send a burndown chart of the current sprint to the customer and seek clarifications.

D.

Schedule weekly meetings and product reviews with the customer to clarify requirements.

Buy Now
Questions 68

At the end of a project with multiple suppliers, the project manager is reviewing the closing process and finds that an unexpected financial balance is remaining. What will

help the project manager understand why this has occurred?

Options:

A.

Project audit

B.

Procurement audit

C.

Lessons learned

D.

Organizational process assets (OPAs)

Buy Now
Questions 69

A project manager has recently moved to an organization to lead a key project. The project manager notices that team performance is

below the target, and the tasks assigned are not delivered on time. Team commitment is also not as appropriate as it should be.

What should the project manager do?

Options:

A.

Apply an agile approach to help improve team performance.

B.

Schedule a meeting and communicate the performance concern to the team.

C.

Study and determine the appropriate leadership style suitable for the team.

D.

Hirea project team leader who can influence the project team members.

Buy Now
Questions 70

A project team began working on a complex project that involves new technology as a product. The team is new to the technology and the proposed approach. Additionally,

the customer is apprehensive about how the product will be received in the market.

What should the project manager do to help the team and the customer?

Options:

A.

Assist the team with identifying the minimum viable product (MVP) to validate assumptions.

B.

Manage the risks associated with the proposed approach.

C.

Work closely with the marketing team on market research and product segments.

D.

Coordinate with the business unit to get detailed requirements.

Buy Now
Questions 71

In a complex development project with many clients and team members, there have been delays in completing the required work. What should the project manager do?

Options:

A.

Empower the team members to do their work.

B.

Inform the project sponsor about this situation.

C.

Work with the team to develop a risk response plan.

D.

Send an email to human resources (HR) about this situation.

Buy Now
Questions 72

A large corporation is transforming itself from a predictive to agile approach. A project team with knowledge of agile practices is experiencing significant conflicts with the

executives regarding the processes to be followed.

How should these conflicts be resolved?

Options:

A.

Request that the executives use agile practices.

B.

Include the executives in team retrospectives.

C.

Train the executives on agile practices.

D.

Negotiate with the executives and agree on a process.

Buy Now
Questions 73

A project is starting its third iteration out of six. During planning, the team realized that all of the requirements were not defined clearlyenough to start working.

What should the project manager do?

Options:

A.

Invite key users to the next daily meeting to get requirement clarification.

B.

Review and replace the unclear requirements with ones that are clear.

C.

Update the issue log and escalate it to the project sponsor.

D.

Meet with the product owner to review the project backlog.

Buy Now
Questions 74

While following up on a deliverable, a team member expresses concern to the project manager about working with another team member. This team member states that the other team member, who is a functional manager, is often defensive and aggressive during meetings.

How should the project manager handle this situation?

Options:

A.

Report the disruptive team member to the human resource (HR) department.

B.

Suggest that the team member ignore the disruptive team member and focus only on the work.

C.

Monitor the situation for a few weeks to determine if the disruptive team member's attitude changes.

D.

Encourage both team members to meet as soon as possible and resolve the problem.

Buy Now
Questions 75

A project team is working to deliver a solution to manage nationwide crisis relief operations. The project team is spending most of its time in

meetings with end users. The meetings have been slowing down project progress.

What should the project manager do to keep the deployment on track while obtaining stakeholder approval?

Options:

A.

Put all of the requirements, priorities, and progress on a visible board, share it with all entities, and decrease the number of meetings.

B.

Ask the project sponsor to attend the meetings on behalf of the team while the team is working on the development.

C.

Inform the stakeholders that a daily meeting will take place at a specific time and ask them to share their feedback during this time.

D.

Stop attending meetings, start development with what was collected so far, and define a date for the first delivery of the solution.

Buy Now
Questions 76

An organization is using a hybrid delivery approach for a complex project. In the iteration review, a senior manager is asking for a complete redesign of the functionality presented.This may require a significantchange in the technical architecture and an additional release.

What should the project lead do first?

Options:

A.

Discuss with the solution architect

B.

Discuss with the development team

C.

Discuss with the product owner

D.

Discuss with the technical lead

Buy Now
Questions 77

A key team member informs the project manager that they have been accepted to a master's degree program. The team member explains that the first semester of the master'sprogram will coincide with thelast phase of the project.

What should the project manager do?

Options:

A.

Ask the team member to inform human resources (HR) about their enrollment in the master's program.

B.

Ask the team member to delegate some of their tasks to another colleague during the last phase of the project.

C.

Suggest the team member postpone their enrollment in the master's program until the project is completed.

D.

Assess the team member's commitment to the master's program and its impact on project performance.

Buy Now
Questions 78

A laboratory is launching a new product, defined to be executed in eight iterations with a fixed release date. At the beginning of the second iteration, the project managerrealizes that a significant regulatory feature is missing in the project backlog.

What should the project manager do?

Options:

A.

Estimate the related cost and ask for a project extension.

B.

Ask the product owner to add the missing feature in the backlog.

C.

Increase the capacity of the team to include the missed feature.

D.

Invite stakeholders to discuss the impact of adding the regulatory feature.

Buy Now
Questions 79

A project manager has taken over an agile project. There have been several issues during product development due to unclear product requirements.

How should the project manager resolve this issue?

Options:

A.

Ask the team to rework the definition of done (DoD) before items can be pulled into the backlog.

B.

Review issues and identify opportunities for improvement that add value to the product.

C.

Gather the project team and product owner to find a solution design.

D.

Assist the team in estimating project tasks such as milestones and story points.

Buy Now
Questions 80

A project manager in an automotive company is scheduling activities for a complex project Some of the project requirements are fixed and some are flexible Match the items on the left with the methodology on the right that the project manager is using.

Options:

Buy Now
Questions 81

A project manager is leading a project in an organization that has a functional structure. The project manager has been informed by the team that the tasks related to the

purchase of services are taking too long, as the purchasing department has other priorities.

What should the project manager do?

Options:

A.

Ask the project team to keep developing other tasks that do not depend on the purchase of services.

B.

Request that the purchasing tasks be outsourced through an existing purchasing vendor.

C.

Meet with the purchasing manager to find the source of the delays and agree on a purchasing schedule.

D.

Modify the project schedule to accommodate the delays in the purchase of services.

Buy Now
Questions 82

A project manager is using an agile approach. During the sprint planning meeting, the product owner flagged a backlog item as high business value and easy to implement.

However, the other team members identified a high dependency between this item and another item that is flagged as low business value and high complexity.

What should the project manager do to support the backlog prioritization?

Options:

A.

Facilitate the discussion until the team reaches an agreement about the two items.

B.

Prioritize the item flagged as a dependency with low business value and high complexity.

C.

Prioritize the item flagged as high business value and low complexity for this sprint.

D.

Support the team to move both items to the next sprint when the team will know more

Buy Now
Questions 83

A project manager is assigned to a project related to taxes, which will be managed using an agile approach. By reviewing lessons learned from a previous project, the

project manager discovers that a key stakeholder is an expert on taxes and is willing to help.

How should the project manager leverage this information?

Options:

A.

Request the functional manager to assign the team from the lessons learned project to the current project to avoid a learning curve.

B.

Recognize the stakeholders skills are important for the project and evaluate the possibility of the stakeholder supporting the project team.

C.

Ask the project team to review the lessons learned and have the team contact the stakeholder directly if there are any questions. @]

D.

Send a request to the project sponsor to hire the stakeholder and have them become part of the project team.

Buy Now
Questions 84

A project manager for an application development firm is meeting with stakeholders prior to the launch of the latest release of the company's most profitable application. The stakeholder mentions the following key points:

• A major corporate rebrand was scheduled to occur with this launch, but the rebrand has been delayed by 3 weeks.

• Development processing improvements will be ready in 4 weeks.

• The company is preselling the updated product with a release date of next week.

Which action should the project manager recommend to the sponsor?

Options:

A.

Have the sales team reach out to customers to communicate that the product release is being delayed.

B.

Suspend the release of the product until the marketing delay has been resolved.

C.

Delay the rebranding and release the product now to address the realized improvements and meet the sales commitments

D.

Postpone the product release until the processing improvement delay has been resolved

Buy Now
Questions 85

One of the team members is always late to the daily standup meeting. What should the project manager do?

Options:

A.

Reinforce the ground rules for standup meetings with the entire team.

B.

Schedule the meeting at the end of the day to accommodate everyone.

C.

Speak with the team member directly to reinforce the ground rules.

D.

Ignore the situation since the team member is accomplishing their deliverables.

Buy Now
Questions 86

A senior project manager is assigned to lead a team of project managers to run a large initiative. Oneof the key stakeholders oftenbypasses the senior project manager and gives instructions to the other project managers directly.

What should the senior project manager do?

Options:

A.

Tell the project managers to document the stakeholder's instructions.

B.

Evaluate the stakeholder analysis to identify the stakeholder's influence.

C.

Review the benefits realization plan with the sponsor and the stakeholder.

D.

Escalate to the project sponsors and the manager of this stakeholder.

Buy Now
Questions 87

A project manager is leading a global team that they have worked with in the past and has a high level of trust with them. The team is located in different countries and time zones and will need decisions in a

timely manner.

In order to ensure that the project runs smoothly across the team, how should the project manager approach delegation?

Options:

A.

Delegate certain authorities and share information to allow fair decision-making.

B.

Delegate most authorities and control the authority by withholding important information.

C.

Delegate most authorities and share information to allow fair decision-making.

D.

Delegate certain authorities and control the authority by withholding important information.

Buy Now
Questions 88

A project requires the procurement of a large amount of equipment that needs to be on-site before any other activity can begin. The procurement department has a lengthy

approval process.

What should the project manager do?

Options:

A.

Ask the project sponsor to expedite the vendor selection process.

B.

Use the existing equipment and replace it later with the new equipment.

C.

Contact the vendor that supplied similar equipment for a previous project.

D.

Work with the procurement team to find alternative options.

Buy Now
Questions 89

A new project has been kicked off following a planning session. The project is under direct oversight of an executive in the organization. After a review meeting, the project manager overhears an executive request a dashboard from one of the team members to show the overall project status.

What should the project manager do?

Options:

A.

Ask the team member to develop a dashboard to fulfill the request.

B.

Tell the team member to route the request through the project manager.

C.

Update the communications management plan to include informal requests.

D.

Update the stakeholder engagement assessment matrix.

Buy Now
Questions 90

A project manager has been hired to lead a governance consulting project that is in the initial phase. The project manager has been assigned to evaluate the supplier search activity. There are many interested

candidates, including former suppliers and suppliers recommended by the sponsor.

What should the project manager do in this situation?

Options:

A.

Evaluate the suppliers based on their experience and skills in similar projects.

B.

Prioritize evaluation of the suppliers recommended by the sponsor.

C.

Evaluate suppliers who have worked successfully with the company before.

D.

Request the contracting area take charge of the supplier evaluation process.

Buy Now
Questions 91

A project sponsor is promoting the use of a new technology that has not yet been approved. The technology guarantees cost savings and a delivery ahead of schedule. However, the operational support atproject completion is uncertain as the service organization expressed an inability to provide support without approval of the new technology.

What should the project manager do to resolve the conflict?

Options:

A.

Acknowledge the lack of approval and focus on a resolution that will benefit the customer.

B.

Maintain and adhere to project plans to ensure the project delivers successful outcomes.

C.

Seek to understand the project stakeholders’ needs in an effort to support the new technology.

D.

Communicate the project's progress to the stakeholders and promote the new technology.

Buy Now
Questions 92

An agile project is approaching its first release date, and the product will be supported by the operations team. To ensure proper support for the product, what should the project manager do?

Options:

A.

Engage an external consultancy to assemble supporting documents and coordinate the knowledge transfer.

B.

Create and prioritize a support manual on the product backlog to ensure adequate knowledge transfer.

C.

Ensure the operations team has representation in the planning and review meetings and that there are support requirements in the backlog.

D.

Propose a workshop with the operations team to outline all requirements of the new software and how to properly support it.

Buy Now
Questions 93

A mid-size capital project has shared resources from the company's contract department. During the execution phase, the project team observed a delay in contracting. After

communicating with the contract department, the project manager found the contract team is prioritizing other contracting jobs because they are not part of the project team.

What should the project manager do first in this situation?

Options:

A.

Report the issue to higher management and seek their direct involvement to complete the job from the contract department.

B.

Communicate with the contract manager to commit a budget for the resources required for project execution.

C.

Arrange several meetings with the contract department and ask them to contract the project as it is critical for project success.

D.

Arrange a meeting with the contract department to build trust and commitment by recognizing their critical support to the project.

Buy Now
Questions 94

A project manager has been managing a project for several months when an issue that had not been registered as a risk appeared. This issue may have a big impact on the

project.

What should the project manager do?

Options:

A.

Hold a meeting with the project team and relevant stakeholders to agree on the best way to manage the issue.

B.

Inform the sponsor that the issue has arisen and that the project's success may be uncertain.

C.

Avoid managing the issue as it was not registered as a risk for the project and there is no planned response to it.

D.

Delay the project until the issue is addressed and no longer presents as a risk to the project.

Buy Now
Questions 95

A project is scheduled to end in 2 weeks. The team is expected to continue working long hours and is showing signs of weariness and fatigue.

What should the project manager do to encourage the team?

Options:

A.

Add new team members to help the project finalization.

B.

Initiate rewards and incentives according to assessment results,

C.

Schedule working lunch meetings until the project is complete.

D.

Schedule training courses to enhance team performance.

Buy Now
Questions 96

In an agile project, the team planned to complete 40 story points in an iteration, but only completed 30 story points. What is the scheduleperformance index (SPI)?

Options:

A.

40/70

B.

30/70

C.

30/40

D.

40/30

Buy Now
Questions 97

A project manager has been assigned to a project that involves building 100 wells for a small community that is urgently in need of access

to water. What should the project manager do next?

Options:

A.

Hire local contractors who are familiar with the environment.

B.

Start project planning and develop the project management plan.

C.

Face the challenge immediately and start sending relief to the town.

D.

Process a change request for additional funding due to project urgency.

Buy Now
Questions 98

A new marketing vice president just joined a software startup and is concerned that the agile model does not provide the needed accountability for their role.What should the responsible project manager do to ensure the vice president is comfortable with the project meeting its agreements?

Options:

A.

Require proper approval of all requirements from the marketing vice president and formally document the agreements.

B.

Leverage the use of the review/demo sessions with the vice president to acknowledge that the agreements were met.

C.

Establish an executive review board where all stakeholders discuss and approve features and requirements.

D.

Foster an environment of open communication where all parties can discuss issues and agree on objectives.

Buy Now
Questions 99

The project team is experiencing schedule delays due to issues arising with suppliers. Some of the tasks are on the critical path.

What should the project manager do in this situation?

Options:

A.

Discuss the critical path issues with the purchasing department.

B.

Escalate the supplier-related issues to the sponsor for resolution.

C.

Review the critical path with the stakeholders to define next steps.

D.

Review the work breakdown structure (WBS) with the suppliers.

Buy Now
Questions 100

A project is being planned to deliver a proof of concept to evaluate technology compatibilities. The business and project stakeholders are having difficulty agreeing on what should be included in the final

product.

What should the project manager do?

Options:

A.

Include all stakeholders in the creation of the project charter.

B.

Determine the root cause of their inability to determine the project scope.

C.

Include the technology suppliers in the creation of the business case.

D.

Determine a clear distinction between business and technology benefits.

Buy Now
Questions 101

A project sponsor wants to develop software that would have 30 features and would be used in 10 different countries. The team feels overwhelmed with the amount of work to be done.

What should the project manager do?

Options:

A.

Support the team to find and execute the minimum viable product (MVP).

B.

Subdivide the team to handle different aspects of the project.

C.

Organize project execution to satisfy the project sponsor's request.

D.

Encourage and motivate the team with project incentives.

Buy Now
Questions 102

Organizational downsizing has resulted in the key subject matter expert (SME) resource leaving a multiyear project. What should the project manager do?

Options:

A.

Update the stakeholder register.

B.

Consult the project sponsor.

C.

Refer to the resource management plan.

D.

Modify the statement of work (SOW).

Buy Now
Questions 103

A company has decided to implement a new archiving system. A data breach occurred during the implementation of the project.

What should the project manager do first?

Options:

A.

Ask the team to fix the system to resolve the issue.

B.

Update the risk register with the risk and proposed impact.

C.

Implement the planned risk response to handle the issue.

D.

Review possible alternative documentation methods with team.

Buy Now
Questions 104

A project manager assigned team members to work in pairs on a large amount of technical reports. At times, the project manager noticed that important information was not shared properly among the team.

This has caused delivery delays and, ultimately, the failure to complete the project.

What is the root cause of this issue?

Options:

A.

Lack of team member training on documentation planning

B.

Team cohesiveness was lost because team members worked in pairs

C.

Improper assignment of tasks to team member pairings

D.

Incorrect communication techniques applied during implementation

Buy Now
Questions 105

During the final stage of the launch for a new design, team members are having a conflict about some features of the design. What should the project manager do?

Options:

A.

Ask the project sponsor to make the decision about the design features.

B.

Call a stakeholder meeting along with team members and seek consensus.

C.

Ask stakeholders to reduce the scope in order to meet project deadlines.

D.

Review the design with the team members and propose a new launch date.

Buy Now
Exam Code: PMP
Exam Name: Project Management Professional (2024 Version)
Last Update: Apr 23, 2024
Questions: 354
$239.6  $599
$179.6  $449
$159.6  $399
buy now PMP