A solution designer in an agile team often passes the design information to team members without any documentation, This has resulted in misunderstandings within the team.
What should the agile leader do?
A project manager is building a team that will be comprised of subject matter experts (SMEs) from two different divisions of the same company.
The project team will be virtual and will include members from different countries around the world.
What should the project manager do to ensure effective team building occurs?
A project, which has its execution phase planned m an iterative way has the following metrics for the first three iterations
One of the requirements for the project states that m order to get payment authorized fcx the project neither the SPI nor the CPl can be less than 0 95 What should the project manager do in iteration 4 to ensure the project is in compliance with the requirement?
The product backlog has been completed and prioritized. and the first sprint has begun A team member advised that during the daily standup there is a delay in having an external vendor contract signed.
What is the project manager's priority in this situation?
A global program is being kicked off, and various distributed teams are Involved in delivering the initiative. Besides planning and executing the scope for the initiative, team interactions must be considered.
How should the project teams interact in their meetings?
A project manager assigned to an engineering construction project is receiving questions from the site engineers. Several questions are related to carrying out activities to meet timelines that compromise the work crew's safety. When reviewing these questions, the project manager realizes that the engineers do not (eel empowered to make decisions.
How should the project manager address this?
A sales team working on an IT deployment project approached the project manager on several occasions and complained about nonpayment of their overtime pay. The project manager realized that other team members are receiving their overtime pay
What should the project manager do next?
A project manager is leading an integration project for a retail company. The project
demands a lot of time from the stakeholders to make important business decisions. The
project is critical and must be completed on time and within budget.
What should the project manager do to ensure that key stakeholders are available for this
project?
A team is having a hard time completing work due to unclear requirements. They have not been able to complete an iteration successfully in several months.
In order to help the team, what should the project leader do?
A project manager was recently assigned to a new project that is about to start. The
organization has already signed a fixed-cost contract with the customer detailing the scope and final delivery date, but the project manager has identified several internal constraints and conditions that will certainly prevent the project from being completed in the number of iterations initially planned.
What should the project manager do next?
A technical lead has complained to the project manager about a team member's performance. The team member has repeatedly missed tasks that have put sprint commitments at, What should the project manager do?
project manager for a defense software application has a culturally and gender-diverse team with a short project time line Considering the project will be stressful what skill should the project manager use to monitor the team's performance?
A servant leader is about to start a confidential agile research project. A high risk has been identified related to a team member disclosing details of the project with external people.
What should the servant leader do to address this risk?
A product team is comprised of consultants and staff members Most of the team members agree on risks and the defined risk actions. One consultant discovers a new risk and communicates it directly to management.
What should the project manager do?
A project manager has been assigned to lead a major project in a government organization. There are no policies and procedures for project management since there is no project management office (PMO) The managers involved are unaware of their responsibilities for the project
What should the project manager do?
A project requires the installation of a call center to support operations. It is estimated that the call center will need 100 people working on
weekdays from 8:00 a.m. to 5:00 p.m. and weekends from 8:00 a.m. to 12:00 p.m.
What should the project manager do?
A project manager is reviewing the requirements of a large program. Which requirements should the project team prioritize to avoid getting fines?
A project manager is managing a project that is going to deliver a new risk platform. This platform will enable data-driven and new risk market models to ensure compliance with new regulations. The regulatory requirements for the models are released continuously and are not fully fixed yet. The project manager is reviewing the risk register and added a few new
Hems
Match the risks on the left lo the correct category on the right.
A bank has decided to initiate a project to transition from serving small businesses and entrepreneurs to mid- and large-scale businesses The country's economy is struggling, and some stakeholders cannot agree on this transformation need
What should the project manager do'?
During a meeting with a customer, it was determined that participants of the meeting
had different draft versions of an important design document. What should the project
manager do first to ensure that this does not happen again?
A CEO has requested that the project manager provide a budget estimate for a long-term project that will be executed over the span of 4 years What should the project manager do?
A protect manager is working with the team lo deliver a project in a company that uses different delivery methods. The project manager is concerned about the communication channels currently suggested by the project management office (PMO) because some information is taking too much time to reach the team members causing negative consequences for delivery
How should the project manager avoid this situation in the future?
The change control board (CCB) has approved a change request to add a new
component within a product. The operations manager discovers the change after its approval
and complains that the implementation of the change will cause significant disruption to the
production line.
What should the project manager do first?
A company initiated a departmental transformation project improving the processes for the organization using a predictive approach, This is a critical project for the organization and, in the middle of the project, the project manager noticed that one of the deliverables cannot be produced due to a missing technical skill.
What should the project manager have done to avoid this?
On a recently completed prefect a project manager noticed that some of the subcontractors approached the client directly with questions. These subcontractors had a previous direct reporting relationship with the client. The project manager is now in the initial stage of a new project with the same subcontractors and client.
How should the project manager set up communications?
Toward the end of a protect the project manager did not receive approval from a key stakeholder because the necessary deliverables were not functioning as expected. What should the project manager do next?
A project manager is executing a project where an external vendor will provide some deliverables Alter awarding the contract to the vendor the project manager is informed that the vendor is running behind schedule on a separate project Finding another vendor will exceed the budget
What should the project manager update first?
A project manager has recently joined a small company. The company's chief
operating officer (COO) asked the team to skip some steps in the process in order to work
more quickly. The project manager wants to ensure that these steps are not skipped in the
future.
What should the project manager do?
In a hybrid project a stakeholder requests some feature modifications directly to one of the team members. When investigating further the project manager finds this to be a common practice m the business, which is different from what is stated in the project management plan
What should the project manager do?
A hybrid project is experiencing several issues with both the agile delivery of the
product as well as the predictive development of a marketing strategy. What should the project manager do to receive feedback from stakeholders located in different time zones?
An international client contacted a software development company to build out a
software product, and an agile project manager was assigned. At one of the review meetings,
the client complains that a feature mentioned at the initial debriefing was not implemented.
What should the project manager do?
A system migration project is in its closing stage. The project manager is being pressured to close the project The project manager communicated to all stakeholders; however, the last department to migrate indicated that they have not received the notification
What should the project manager do?
A project team has transitioned to full-time remote working. The project manager
started noticing that some team members have not been completing their assigned tasks by
the planned dates despite reminders during weekly team meetings. This has the potential for
delaying the project delivery.
How should the project manager resolve this situation?
A project manager is in the process of creating a strengths-based team and is
organizing a series of workshops to identify and document the strengths of each project team
member. During this session, there are multiple team members who are not actively
participating. These meetings are becoming futile due to a lack of participation.
What should the project manager do?
In the planning phase, a project manager receives identified risks from the sponsors
and subject matter experts (SMEs) and wants to develop a risk response strategy for them.
What should the project manager do first?
A project manager is working on a complex project and is unsure about planning, executing, monitoring and controlling the project. Match the phrase on the left with the correct statement on the right.
A project manager has heard about the large volume of emails the team receives each day which prevents them from doing project work. One team member has stated that they would like to be able to access project-related information when needed
To what type of communication is the team member referring?
A project manager is working with a team that is new to agile. One of the more
influential stakeholders struggles with the nature of agile. The project manager knows that this
stakeholder is needed as an advocate and wants to do everything possible to make the
stakeholder comfortable with the project.
What should the project manager include in the status report to illustrate the project's
performance?
During a network upgrade for a company, the client informs the project manager that a government representative notified the client about a separate project that will affect the network upgrade. Any change in the upgrade will impact the project's cost and schedule.
What should the project manager do first?
During project completion, a project manager receives a request from the customer for a reduced cost of goods. The customer's request will affect the sales department's budget and forecast.
In order to reach a consensus and have a successful project completion, what should the
project manager do first?
A project team member has lost enthusiasm and is experiencing low morale for a
project they were once excited about. What should the project manager do?
One of the team members is consistently absent in team meetings, but always completes their assigned tasks on time. Other team members think this member should attend the meetings.
What should the project manager do?
A project manager is leading a hybrid project. The self-organizing teams are
continually late in delivering their demos, resulting in low morale. The steering committee is
familiar with the reporting and planning associated with a predictive approach and is
concerned about the project because it is unclear if the expected value will be delivered.
What should the project manager do?
A company has assigned a project manager to the initial task of determining the resources required for a new project What should the project manager consult?
A project manager has been working with the same group of stakeholders for 3 years using a predictive approach. The stakeholders have invested in many projects and are familiar with the approach Recently the organization has strongly encouraged all project managers to adopt an agile approach. This was announced 2 weeks before the project manager planned to kick off a large complex project with the same group of stakeholders.
What should the project manager do?
A project team has been together for a long time and has been led by three different
project managers. Lately, the performance of one of the team members has been declining
and has affected the project delivery.
What should the current project manager do to ensure that team performance is improved and
sustained?
A project manager is leading a progress review meeting when some stakeholders who are new to the project express concerns about not having access to previously shared deliverables. What should the project manager do?
A project manager receives a serious complaint from a functional manager about a
team member. What should the project manager do?
A team is given an agile project to build a conceptual product for a new customer.
While planning, the project manager is trying to determine the best way to show value to the
customer, as the technical requirements are not very detailed.
What should the project manager do to help the client understand the value delivered during
project execution?
A project has been running for 2 months and now requires approval for a supplier to
begin some execution tasks. The project team has evaluated several suppliers and selected
their top two preferred suppliers. The project sponsor requested that another supplier who has
lower costs be added to the list. However, the project manager is aware that this supplier
does not always fulfill the project requirements.
What should the project manager do?
A project manager is establishing a project management office (PMO) for a
company-wide program to implement a software based on artificial intelligence (AI). As part of the PMO tasks, some stakeholders need help understanding how to deal with difficult situations.
Which activity should the project manager use to help train the stakeholders?
A project is on its sixth iteration out of seven. Select the two points where the team is
performing better than expected. (Choose two.)
During the project quality control process, the project manager realizes that the quality management plan does not include how the final user will perceive the benefits of the new product compared with the actual product. What should the project manager do first?
A customer asks the project manager about opportunities to create business value.
What should the project manager do first in order to provide the customer with an appropriate
response?
A project manager is assigned midway through a project. The team members are in
different locations across the country and they are unable to meet in-person often. During a status review meeting, one of the stakeholders highlighted that they were unaware of the status for the project deliverables.
What should the project manager do first?
A company's board of directors announced that a major layoff will occur at the end of the month. When evaluating the impact the protect manager found that 25°© of the project team members are part of the layoff
What should the project manager do first?
During the execution of a construction project, the project sponsor asks to make
changes to the floor plan by adding a minimal storage room. The sponsor insists on making
this last-minute change, but they would like to avoid delays to the project.
Which document should the project manager refer to first?
A project manager has experience working with a specific provider that has been
requested for an upcoming project. This provider often fails to meet deliverable dates; however, it is the only company with the specific experience required for the project.
What should the project manager do during the planning phase?
A company has decided to investigate the feasibility of a new product. The project manager is in charge of validating the customer requirements. What should the project manager do to gam customer feedback?
A project is in the execution phase During a few planning sessions the team brought up dependencies and risks based on their knowledge of other project. The project manager also received questions from the company in terms of how and when the team planned to perform acceptance testing and training activities
What should the project manager do next?
During project execution, an important stakeholder threatens to withdraw support
for the project, citing a lack of transparency and accountability in the way the project is being
executed. What should the project manager do to handle this situation?
A project manager notices that a project participant seems frustrated and expresses themselves loudly at status meetings and later discovers that the participant is hearing impaired. Which process should the project manager have used at the start of the protect that would have identified this situation?
A protect manager is managing a project that will handle sensitive data for millions of users The sponsor mentioned that, lo their knowledge, the project does not seem to have any compliance requirements in their country.
What should the project manager do in this situation?
One team member Is complaining about an agreement made during the last meeting. That team member was present at the meeting ana participated in the decisions registered in the meeting minutes.
What should the project manager do next?
A project manager sent the first communication about the project management plan to the team. The next day. two field engineers were asking about their roles and the project schedule.
What should the project manager have done*?
A project team is reviewing solved project issues from the last phase of a project. The lead risk analyst points out that the next phase of the project includes a critical element with some
reserves needed
What should the project manager do to successfully complete the next phase?
An agile leader is working on a complex project that is entering the final phase where solutions from different vendors are being integrated. This is the most critical delivery stage for the project
How should the agile leader ensure successful delivery?
A project manager is involved with a project to remodel a long-used product. There are no proper records for the original design and execution of the original product. The stakeholders doubt that the remodel can be accomplished without this information and are hesitant to provide support for the project.
What should the project manager do?
A project manager is instructed by the project sponsor to draft the project charter. The project sponsor asks the project manager to involve a particular stakeholder m order to provide necessary resources However, the stakeholder is refusing to get involved because the stakeholder thinks mat there is no benefit m using the project deliverable
What should the project manager do to resolve this?
During project execution a project team member resigned and a new junior member joined the team To smooth the transition the project manager assigned a senior project team member to transfer knowledge and support the junior team member The project manager subsequently received feedback from the senior team member saying that the junior member submitted a poor-quality deliverable and should be removed from the team However the project manager checked that deliverable and found it met quality requirements
Which technique should the project manager use to resolve this issue?
A project selection committee is shortlisting projects for the coming year. Which selection criteria should the project manager recommend?
A subcontractor informs the project manager that they are unable to supply a key
component to the project. What should the project manager do?
A new manufacturing line project is planned to be delivered in iterations tor the equipment installation phase. During one of the iterations the vendor communicates to the project manager that they will not be able to deliver some of the equipment at the agreed dates.
What should the project manager do next?
During a project kick-off meeting the project manager tells team members that they can attend a weekly progress meeting either from home or the office. Which intangible stakeholder engagement quality is the project manager embracing to manage relationships?
An organization is adopting an agile mindset. On the first agile project, the project
manager faced an issue because the team was unable to make decisions on time.
What should the project manager do to address the problem?
A project manager is using a hybrid approach to comply with a regulatory requirement. The planning and closing phases will use a predictive approach, and the execution phase will use an iterative approach. During the second sprint review, the project sponsor requested a change in priority tor some of the product backlog items
What should the project manager do as a servant leader?
A contract has fust been awarded for an automation project that was supported by the local community. The project manager was warned by the elected officials that the project cannot proceed.
Why did this action occur?
A customer interacts directly with a Scrum team and continually requests changes in
priorities. This causes confusion among the team members and they complain to the project
manager.
What should the project manager do?
A project manager is assigned to an automotive product development project in me middle of the pilot phase. According to the test lab. a durability test was completed with good results 6 weeks ago but there were no reports left behind by the test engineer who left the organization the previous month.
What should the previous project manager have done to prevent this issue?
A key project team member has exhibited high interest in a project. The input from
this person has been very useful, and the project is steadily progressing. Suddenly, this individual's participation decreases, and activities that they were responsible for are not being completed within the planned period.
What should the project manager do?
A project team is facing challenges understanding how to deliver a project's scope.
A senior subject matter expert (SME) from the organization's global office is in town for 1 week.
What should the project manager do to benefit from the SME's presence?
A team member is openly criticized by others during a standup meeting for failing to
complete yesterday's tasks. What should the agile coach do first to address the situation?
During a project gate review meeting, it is identified that one of the project
deliverables will require corrective actions to meet the project quality requirements. What
should the project manager do first?
A project manager who Is new to an organization is given data that include information related to both project team members and stakeholders. Among other items, this information includes each stakeholder's current role, previous and current projects in which they participated, and their level of organizational influence.
In what type of analysis should the project manager use this information?
A supplier informs the project manager that producing the quantity of a key component for the project will require an additional month. The project manager has to meet an important
milestone in a week.
What should the project manager do next?
An agile leader notices that one team member consistently fails to complete the deliverables on time The agile leader suspects that this team member does not have the proper training.
What should the agile leader do?
The sponsor approaches the project manager with new features they want added to
the project. The project is 95% complete, but the sponsor insists that continued support for the
project relies on the addition of the new features.
What should the project manager do?
The customer wants to show their stakeholders a tangible outcome faster. This requires advancing a milestone.
Which two things should the project manager do? (Choose two)
A large company is transitioning its projects to an agile approach After the transition executive management requests the information that was previously available in old reports and dashboards Many of the old reports and dashboards are no longer relevant after the shift to agile practices.
What should the project manager do in this situation?
A hybrid project manager has taken over a large-scale software development project m a highly regulated environment. During a handover session the outgoing project manager explains that they devised their own status reports which is different from the project management office's (PMO's) status report style. The project stakeholders are extremely particular about the information they receive in updates and do not believe the PMO's status reports have sufficient enough information
How should the new project manager proceed*?
A project manager submits a version of the software that the project team created. During the review meeting, a team member informs the project manager of a recent regulation that requires a dual verification process in the software. However, the product sponsor strongly insists there should be no updates to the software.
What should the project manager do?
A new sales software development project is underway The customer is still finalizing the requirements for the system when a new CEO is introduced. The new CEO is expected to make changes to the organization, which most likely will impact development. However, the most important criterion for the project is that the software must provide correct sales results. No intermediate results are required.
Which project approach should the project manager take?
A project manager who works for a company involved in several industries is asked
to lead a software development project for a government agency. The company attempted to
execute similar projects for other industries before but was unsuccessful.
What should the project manager do to ensure project success?
A project manager has been assigned to a project that is in progress. The project
manager is looking for information regarding why the project is being completed.
What should the project manager do first?
A project manager is leading a software development project. Recently, team members have complained that during the last few dally standup meetings, a key stakeholder frequently interrupts, requests explanations, and proposes unplanned changes. This issue is frustrating the project team and slowing down me work.
What should the project manager do?
A company made several changes recently, which resulted in a positive change in
the company culture. A project manager was just assigned to report to a new project
supervisor whose leadership style is about getting things done quickly regardless of employee
and operational impacts. Some employees are complaining about this.
What should the project manager do?
An agile project manager is evaluating the method that will be used to display the
value of the work performed to date. Which method will they select to display to the project stakeholder?
A project manager for an iterative project received feedback from an on-site team member that the virtual team was not meeting the deliverables on time. The project manager gathered details on what the status report should contain m order to track deliverables
What is the remedial action the project manager should take?
Due to a recent company merger, a project manager from company B has been
assigned to a team that is comprised of team members from company A. At the start of the
project, conflicts arise due to a lack of clarity on processes and the project manager's
relationship with company B.
What should the project manager do to resolve this conflict?
An information technology (IT) team is responsible for the validation and release of a product developed by the agile development team Due to other priorities for the IT team the releases are delayed
What action should the project manager take?
A developer who has almost completed a required product feature for a prototype
leaves the company in the middle of an iteration. What should the project manager do?
A project manager is working on a project with multiple workstreams. One of the
workstreams missed its deadline multiple times.
Who should the project manager speak to about this situation to ensure it does not happen
again?
A project manager is leading an automation project. The project team is colocated
and includes people from both the technical and business units. The project manager
discovers that personal differences and work styles are affecting the project negatively.
How should the project manager address this?
While working on a poorly defined internal project, a project manager receives
multiple change requests from senior management. What should the project manager do first?
Organizational downsizing has resulted in the key subject matter expert (SME) resource leaving a multiyear project. What should the project manager do?
A project manager is assigned to lead a design for a new version of an existing
product with the technology and operations teams. The project manager organizes a joint
requirements session to determine the most practical ideas. The project manager was advised
that the session may become chaotic.
What should the project manager do to ensure the session is interactive, productive, and
efficient?
A project manager is leading a major water pipeline project and realizes midway into
the project that the project completion date is not achievable. Local farmers who rely on the
water for irrigation may be affected due to the delay. The project manager is afraid of their
displeasure and reaction, which will affect the project.
How should the project manager plan the communication to the stakeholders?
A project manager is working on a highly complex project. During the execution of
the project, the local government changed certain environmental regulations, which could
potentially delay the project.
What immediate action should the project manager take?
A team is working on a hybrid project. Due to different interpretations of the project requirements, the deliverables are not aligned to the expectations. What steps should the project manager have taken to prevent this?
During the setup of an agile project, the product owner expressed clear interest in
having features released during product development over having the product completed in
one year. What should the project manager do?
An organization's management system is being upgraded by an agile team. Although the project was scoped thoroughly, the functional requirements were handed over to the project team and there is no subject matter expert (SME) available to work on the project continuously. The project manager is concerned that the team's progress will be hindered by their lack of knowledge.
Which two project events will assist the project manager to ascertain if this is the case? (Choose two)
During project execution of a new IT solution, the testing of one feature was unsuccessful. The go-live milestone is now impacted due to this delay. Extensive analyses were performed, and there is no way to resolve the defects before the go-live date.
What should the project manager do next?
A project requires testing of the final product to be done at another department's
testing facility, which is known for having low availability. This situation could potentially
impact the project schedule.
What should the project manager do next?
An agile team was hired to work on a public service project. The team received a
list of vague ideas about the business and now needs to understand, develop, and prioritize a
list of functionalities.
Who will be responsible for this task?
Ai the start of a project, the sponsor declares that demonstrating benefits from the product will be extremely important. The project sponsor calls a meeting with the project manager and the project leadership team to discuss the best approach because the project has a high degree of uncertainty and many changes are expected.
What should the project manager propose?
During the planning for a long project, the project manager recognized that several
members of the team are new to their roles. How should the project manager incorporate this
into planning?
A project team identified a low-cost software product available for purchase that would drastically reduce the scope of development. The development manager has confirmed that this tool would fulfill the business need.
What should the project manager do?
A team has just adopted an agile approach. During daily standup meetings, the team expressed concerns about task delays. The project leader worked with the product
owner to get clarity on the features. The project leader asked the team to fast-track all product features to ensure delivery. Sprints are being completed but with either fewer
features or low quality.
What should the project leader have done to ensure success?
There is a problem with a project because some features are not in compliance with
regulations. Some stakeholders do not believe compliance is a priority, while others disagree.
What should the project manager do?
A project manager is assigned to an ongoing complex project. The team is delivering value each iteration However, the deliverables are internal and the customers are unaware of the deliverables.
Which action should the project manager take?
A project manager is using a hybrid approach for a project. The project team created and reviewed the risk tog with the stakeholders at the beginning of the project However midway through the project, the project team and stakeholders became misaligned with the risks and mitigation strategies
When should the risks be reviewed to ensure alignment between the project team and the stakeholders'?
A project manager is leading a diverse global team. The team members disagree about the requirements for a recently approved change request. The conflict among the team members has resulted in low morale and decreased performance.
What should the project manager do?
A project manager is asked to implement a hybrid approach that will replace a predictive approach on an upcoming project How should the project manager adjust their responsibilities accordingly?
Vendor A submitted a bid for US$500,000. There is a 65% probability that the
vendor will deliver behind schedule with a cost overrun of US$ 100,000. The vendor will come
in ahead of schedule for a savings of US$50,000.
What should the project manager determine as the value of the vendor's bid?
A project is in the start-up phase of the project life cycle. The project team consists of 20 people from five different countries. The project team is scheduled to have quarterly face-to-face meetings. However, due to unforeseen circumstances, no face-to-face meetings can occur. The project manager is concerned that the team may not be able to fulfill their individual roles without face-to-face meetings.
What should the project manager do in this situation?
During execution of a complex project, the project manager encounters numerous change requests from various teams. These changes may result in the project not meeting its objectives.
How should the project manager ensure that these changes are managed effectively?
Due to scope changes, some of the risks identified during the initiation phase have materialized into issues. What should the project manager do next?
A project manager is leading a complicated project that requires integrating several components from different suppliers. During execution, the project team indicates that some components are not being delivered to the site on time, affecting the project schedule.
What should the project manager do to address this concern?
The project sponsor reports that a key stakeholder is complaining about performance differences in the metrics reported by the project manager,
which gives the impression that the project is out of control. The project manager has been providing the project's status according to the agreedupon communications management plan. This key stakeholder, however, seldom attends the status report meetings.
What should the project manager do first to address this situation?
As part of planning activities for a new project, the project manager must develop a budget that encompasses the full project scope. What should the project manager do to build the project budget?
Anew engineer was assigned to a project. Although the engineer has adequate skills for the job, they always wait for authorization from the
project manager before acting.
What should the project manager do?
A project team member wants to select specific challenging tasks in the subsequent iteration. How can the project lead help the team member in the next iteration?
A project manager is leading the construction of a branch office building for a national bank. The project manager is informed that the regulatory authority has closed the bank.
In closing this project midway, which activities should the project manager execute first?
A project to develop an enterprise resource system for a university is in the planning phase. The project has internal stakeholders such as operational departments, students, and academic staff, as well as global stakeholders who receive the information from the university on a regular basis. All the stakeholders have very different expectations and needs from the system.
What should the project manager do to ensure effective communication?
A project team is defining the ground rules during their first meeting as a team. During this session, only a few of the team members suggested and approved the ground rules while most remained silent. As a result, the team's ground rules favor those few team members.
What should the project manager do?
During a project meeting, the project manager expressed the importance of delivering reports on time. These individual reports will be
consolidated into a single report. One of the team member's reports was not delivered on time and therefore the report could not be integrated
with the other reports. This demonstrates a lack of teamwork and impacts project success.
What should the project manager do to resolve this issue?
A large matrix organization is adopting a new communications approach. This is necessary because their projects often require the resourcing of expert knowledge in the form of specialists from various departments and divisions.
What should the project manager do to set up effective communications?
A project manager was recently assigned to rescue a high-priority project for an Olympic facility. The project is behind schedule, with a heavy contractual penalty. The former project manager had numerous conflicts with the project team members and a few stakeholders.
What should the project manager do first?
A project manager and project team are developing a strategic approach to engage the internal and external stakeholders. Which approach should be followed?
A flagship project is sponsored by the CEO and has a critical go-live date. The project's product requires a regulatory review and approval before it can go live. The CEO instructed to allow only 2 weeks for regulatory approval in the schedule; however, the director for the regulatory liaison indicated 6 weeks was a more realistic timeline.
What should the project manager do?
An experienced project manager has been assigned to a hybrid project that requires an extensive amount of information to be updated. Which tool should the project manager use along with the team?
A project manager is managing the opening of a new office overseas. At the beginning of the project, possible delays due to legal permits are raised by one stakeholder. Subject matter experts (SMEs)
reassessed the concern and suggested assigning more time for this permit, and the change control board (CCB) agrees.
Which document should the project manager update first to document this change?
A customer requests additional changes 1 day before the planned change date. How should the project manager respond to the change request?
A project has completed design activities ahead of schedule. Suddenly, the project manager is informed by a vendor that a deliverable may not meet the agreed delivery time frame due to a resource shortage. The internal team asked if they should continue to deliver as per the schedule.
What should the project manager do?
A project manager is leading a project that needs to be deployed quickly to the market. An influential stakeholder does not believe that the project management processes bring business value.
What can the project manager do to gain the support of the stakeholder?
A project manager is preparing to start a new project in which the team members are distributed geographically across different countries. The project manager is using the communications management plan to engage the team members and find a communication method that suits everyone.
How should the project manager continually evaluate the effectiveness of the virtual team's engagement?
During a sprint retrospective, the project manager notices that one of the team members does not achieve the sprint objectives on a regular basis. This team member is an experienced resource.
How should the project manager properly address this situation?
A project manager is leading a project in a heavily regulated industry. Match the considerations on the left with the correct compliance plan categories on the right.
As the project progresses, the learns not performing at acceptable levels and in accordance with the key performance indicators (KPls) that were set at the beginning of the
project. How should the project manager resolve this?
During the execution of a construction project, one of the neighboring businesses is complaining that the current building height does not agree with the initial project plans. What should the project manager do first?
A project manager notices that an extroverted project team member appears to be increasingly controlling the direction of the entire team. The other team members are not complaining but seem to be more passive.
What should the project manager do?
Developers spend most of the sprint writing code for user stories, leaving little time for testing. As a result, user stories cannot be tested in time and the stories remain unfinished by the end of the iteration, resulting in poor metrics.
What should the scrum master do first in this situation?
A project manager is working on a global project and realizes that one team member is not performing as expected. The project manager meets with the team member to find out what is causing this low performance. The project manager discovers the team member is experiencing conflict and feels uncomfortable with the team. The team member then asks to be moved to another project.
What should the project manager do?
Halfway through project execution, stakeholders ask for equipment that was expected to be procured. The project manager explains that the equipment was purchased, but differs from what the stakeholders are currently asking for. This is because the initial requirements were changed during a previous meeting.
What should the project manager have done to avoid this situation?
In an agile environment, a project is running iteration four out of six. A team member leaves the company with no replacement.
What should the project manager do?
Update the issue log and refer to the resource management plan to address the situation.
Ask the team for extra work to fulfill the project commitment.
Reduce the scope of the project and inform stakeholders.
A project is implementing an agile strategy, and a minimum viable product (MVP) was agreed upon. After the first iteration review, the customer explained that the first deliverable is not of great value.
What should the project manager have done differently?
A project manager is assigned to a new project that will launch the digital version of a current product. Even though the product is well known, the vision for its digital version
is not clear to the stakeholders.
What should the project manager do to increase value delivery?
A project manager is assigned to a critical software development project. The team is using a hybrid approach and has divided development into four sprints. At the end of
sprint three, the project manager discovers that the earned value (EV) is US$500,000 and the planned value (PV) is US$550,000.
What should the project manager do?
An agile team is geographically separated across multiple continents, and the project manager is in the process of identifying the tools to manage the communication among the virtual teams. Drag the appropriate tool on the left to each project task on the right.
A project is approaching the closing phase. While preparing for the final steps, the quality system is updated in accordance with new international quality standards, resulting in new deliverable/approval procedures.
Which action should the project manager take?
An agile team has been assigned to a project that mandates the implementation of changes to key government products. The team has been given 6 months to fulfill this mandate.
What should the team lead do next?
A startup company has just appointed a CEO that has no prior project experience. The CEO wants to execute projects with their own resources
and has appointed a project manager.
What should the project manager recommend that the CEO do first?
A team is finishing the third release to present to the stakeholder as part of a demonstration. The company that subcontracts the developers has communicated that there is a cash flow problem and the company will not be able to provide the same resources for the next iterations.
What should the project manager do next?
A project manager is working on a project to develop a new watch at a matrix organization.
Which two key items should the project manager include in their feedback to external stakeholders? (Choose 2)
During planning, a virtual project team agreed to the project reporting structure and established a meeting cadence that fits multiple time zones. One month into execution, the project manager notices that certain members are disengaged during project meetings.
What should the project manager do to resolve this issue?
A project manager receives a suggestion from a team member for improving the product attributes without impacting the schedule or cost. This will add value to the project
and the customer.
What should the project manager do?
A project manager has just been assigned a major, ongoing project. The project team is not working in harmony and their performance is decreasing. Some team members are autocratic in their approach whereas others are in avoidance mode.
How should the project manager proceed?
A project lead with a strong technical background oversees a project using agile delivery. The product owner asked the project lead to assist with ensuring the benefits of functionality that are built in the sprint are tracked.
What should the project lead advise?
A senior project manager has included a junior project manager as part of the project team. During a coaching session, the junior project manager
asks the senior project manager how to be efficient and reduce rework.
How should the senior project manager respond?
A project manager has just been appointed to a project that has two major deliverables. Both deliverables have the same level of priority and are to be delivered at the same time. The members of the team are complaining about the lack of information regarding which deliverable needs to be finished first.
What should the project manager do?
An experienced project manager is in a meeting with project key stakeholders when they are informed that a senior manager with extensive experience on similar projects will join the project steering committee. The project kick-off meeting is scheduled for the following week.
What should the project manager do next?
A project manager is part of an organization that is assessing the use of agile delivery approaches. A new project management office (PMO) manager who had a bad experience with a Scrum approach recommended that the project board replace Scrum with a predictive approach.
What should the project manager do?
A project manager noticed that the functional manager is not cooperating with staff assignment schedules and is always finding excuses not fo release the requested staff.
What should the project manager do first?
A project manager is leading a project that has a dependency on the client's vendor management system for critical requirements. The vendor
management team will not derive any benefits from the project. However, the project requires support from the vendor management head.
What should the project manager do next?
After sending an on-site meeting invitation to seven people for the kick-off meeting of a project, a key stakeholder declines because they will be at another location for the rest of the month.
What should the project manager do?
After the first iteration, a scrum master notices that some of the team members are struggling with testing their developed product. What should the scrum master do next?
A company is working on a project to develop an integration of their existing systems. There are known issues in production.
What should the project manager do?
A project team member, who is inexperienced in system development work is not performing well. Currently, there are no other staff members
available who are qualified to complete the work.
What should the project manager do?
During a progress review meeting, the project sponsor requests a complete revamp of the product roadmap to meet the strategic objectives based on market conditions. This change will result in a completely new product.
What should the project manager do first?
A project team has been working together for about 2 years. One of the team members has consistently shown high performance and stood out among their peers during the execution of the project.
How should the project manager recognize high performance?
A project manager encounters a governance issue during the project execution phase. One of the team members complains about receiving assignments from multiple people and states they are not able to work effectively.
What should the project manager establish first in the project governance structure?
A project manager is leading an engineering project. The project manager must obtain some certifications before mass production, which is scheduled in 3 months. The certification process will require at least 6 months.
What should the project manager do next?
A project manager is leading a hybrid project and is collaborating with the client to develop the project contract.
Some delays have been experienced due to unforeseen technical difficulties and new dependencies. However, the project manager is optimistic about recovering the delays in the upcoming sprints. A key stakeholder asked the project manager if the contract deadlines can be met.
What should the project manager do first?
A project team is not motivated and is producing the bare minimum. The team has no interest in keeping pace with the aggressive project schedule.
What should the project manager do first to get the team energized and performing efficiently?
The scope of a construction project that is being planned by a multinational company requires that services are procured via contract from an external provider. When considering communication channels, what should the project manager do to help maximize delivery success with this provider?
A project manager is working with a team that is demotivated and tired, as the project has been changing direction due to budget cuts from the sponsor.
What should the project manager do first?
During the execution phase of a project, a new department has been created in the company. The manager of this department has requested to
be involved in the regular project communications and reporting cycles.
What should the project manager do?
An information technology project manager works at an insurance company and is assigned to an infrastructure upgrade project. During the execution phase, a stakeholder approaches the project manager and informs them that a deliverable is not meeting the quality requirements.
What should the project manager do first?
A project manager is working in a regulated industry. The minimum viable product (MVP) for the launch has been defined. The project manager learns that the regulatory body requires a prototype for inspection before the product can be launched; however, the prototype is not part of the MVP definition.
What should the project manager do next?
A project management office (PMO) is currently stretched for project control resources. Specifically, the cost control resources are short of the staff required for this activity level. A new project is about to start soon.
What should the project lead do to obtain the needed resources?
In a hybrid project, the project manager has identified a few stakeholders. According to the stakeholder matrix, the head of development has a high rating of power/influence and a high likelihood of conflict.
Which action should the project manager avoid?
A project manager is leading a project with a team that is comprised of both experienced and inexperienced team members. What should the project manager do to ensure an effective project team?
At the end of a project, the project manager was asked to provide a performance rating of the project team members. What should the project manager mainly make reference to?
A project manager is assigned to a regulatory project for their country. The deadline for delivering results in compliance with the new laws is very tight, and the project team members have not yet been assigned. One of the project manager's peers informs the project manager that a project with the same scope for a different country was completed 1 year ago.
What should the project manager do first?
Project stakeholders have provided a team with requirements that will take at least one year to complete. The project sponsor advised that they need to see some return on investment (ROI) soon.
What should the project manager do?
A project manager is facilitating an iteration retrospective. The iteration did not go well and the committed functionality was not delivered to users. The project involves a vendor team for the build and an internal quality assurance (QA) team. In the past, there were tensions between the vendor and the internal team.
What should the project manager do?
A project manager has just received communication from an operational functional manager to complete an additional scope item for a project that was formally closed a few weeks ago. The scope looks relatively small and simple to handle as part of the daily operations activity.
How should the project manager deal with this request?
Travel restrictions are suddenly imposed during a project's execution. The team members reside in different geographic locations.
What should the project manager do next to address this issue?
A newly hired project team lead was assigned a project using a hybrid delivery approach. As the project onboards a lot of new team members, the lead feels overwhelmed with the effort of explaining the project delivery process to each new team member.
What should the project lead do?
A project manager has been assigned to lead a software project to generate savings at an important financial institution. Initially, the duration of the project was 13 months,
but due to various issues during execution, the project was extended to 16 months. By month 11, the expected savings were exceeded but not all of the functionalities
planned for that date were fulfilled.
How should the project manager inform the stakeholders of the project's progress?
An organization is using a hybrid delivery approach for a business project. The product owner, the person who was also managing the project, was promoted to a more senior role. A new project lead has joined the project.
Which artifact should the project lead use to ensure that the project benefits have been identified?
A project team needs to create artifacts for an upcoming steering committee.
What should the project manager do first?
A team needs to implement a mandatory compliance regulation in a product, which is required for its release. While nearing the product release, when completeness was
being verified, it was found that the compliance part was not implemented in the project.
What should the project manager do next?
A project manager notices during project meetings that some team members repeatedly threaten to resign when they do not agree with something. Which phase of conflict escalation is the project in?
Two experienced team members in a hybrid project are having a conflict about a technical solution. The project manager has already spoken individually to the two team members without successfully resolving the conflict.
What should the project manager do next?
At the beginning of a project, a project manager is asked to provide human resources (HR) with an evaluation of every team member's performance. This evaluation will be delivered at the end of the project.
How should the project manager approach this request?
Presented with flowcharts of the organization's operations, stakeholders are unfamiliar with several recorded processes, and others note that some recorded processes were discontinued. The project sponsor notices that the chart is several years old and wants an updated version immediately.
What should the project manager do?
A project manager is assigned to a research project. The project team has been selected and has worked together on other projects. Based on the project documentation, team members seem to be working at their own pace and have had little interaction with the project manager.
What should the project manager do to have a high-performing team?
After meeting with stakeholders, a project manager working at a computer gaming company is creating a project management plan for the company's newest offering. The project manager learns that the company's main competitor is scheduled to release a similar offering leveraging the newest technology. The project manager fears that the competitor's offering is better in multiple ways compared to the project manager's project.
What should the project manager do?
A new employee has joined the management team and wants to get a quick overview of all the agile team's projects. What should the agile team lead recommend to the employee as a first step to gain this understanding?
An organization is about to start a multiphased project. Due to strict regulations, some of the phases must be completely planned in advance.
However, other phases allow for more flexibility and experimentation on scope and schedule. The sponsor wants to pursue the project objectives
as planned, but also wants to accommodate new information and changes as the project progresses.
Which project management approach should the project manager select for this project?
A project manager is assigned to deliver a development project with subcontracted resources from a sister company. What should the project manager do to ensure a smooth inclusion of the new subcontracted resources?
A project manager is performing the scrum master role for a project team of developers. At the daily standup, a couple of developers complain about the noise from a neighboring team, the performance of their laptops, and the difficulty in booking meeting rooms.
What should the project manager do?
A state-of-the-art product was delivered at the end of a project life cycle. However, the customer claims the product was not designed to specifications.
What should the project manager have done to avoid this issue?
A project manager is planning a project to build a research center with the installation of scientific equipment. Since the research topic is new and unfamiliar, the equipment required might change during project execution.
How should the project manager plan this project?
A project is comprised of team members who are not engaged and committed to project success. What should the project manager do to address this situation?
Early on during a sprint in an agile project, the project team begins deliberating two different approaches to implement a feature. The project manager is concerned that the team is spending too much time discussing this feature, because the team needs to cover other features in the sprint as well.
How should the project manager approach the situation?
A project manager is reviewing a draft of the project charter with key stakeholders. During the meeting, a conflict occurs between the sponsor and the product owner.
How should the project manager deal with the situation?
A project manager is implementing a project similar to a previous one that required strict adherence to occupational health and safety (OHS). Both projects are for the same client whose business environment is highly regulated. However, this time the client does not appear to be concerned about OHS requirements.
What should the project manager do first?
Before kicking off a high-priority and complex project, what should the project manager do to ensure all project stakeholders are aware of their role scope as it relates to project activities?
A project team's performance is being impacted by impeding internal procedures that are affecting the progress of activities and team autonomy. What should the project
manager do first to address this situation?
A project team is in the planning stage and has prepared a list of activities and completed sequencing the activities. During a review, the team noted that there is a
dependency missing between:
+ Test the product
+ Release to customer
According to the quality management plan, the product must be tested before being released.
How should the project manager enter this dependency?
A project is late due to a large number of scope changes. This was raised as a risk in the risk register during the initiation phase. The team is afraid that they will be blamed in case of failure and recommends that the project manager ask for an extension.
What should the project manager do first?
A project manager is leading a global team that they have worked with in the past and has a high level of trust with them. The team is located in different countries and time zones and will need decisions in a timely manner.
In order to ensure that the project runs smoothly across the team, how should the project manager approach delegation?
A major issue about conflicting priorities has been highlighted by the project team with regard to a few stakeholder requirements. What should the project manager do?
A vendor project manager and team are implementing a software solution across the organization. A customer stakeholder who was not present during the sales process is demanding that the team implement requirements that are out of scope without adding additional cost to the project.
What should the project manager do next?
During an agile project a project manager lost one of the resources, and at the same lime, uncovered new requirements, which were added to the backlog What should the project manager do next?
During the last iteration of a hybrid project, one of the key members of the team wants to leave the project. What should the project manager do to address this concern?
During the daily standup meeting that is assessing progress against the current sprint, a team member reports some delays due to a component
managed by an external vendor. How should the project manager address the team member's concern?
An agile project manager has started working in a company that builds shopping centers. The project manager wants to implement some agile
practices, which are relevant to the project.
What should the project manager do in order to gain buy-in from the different stakeholders?
A project manager manages multiple information technology (IT) projects in a matrix organization. The project manager schedules a meeting with one of the functional
managers to coordinate testing support for two software development projects. Unfortunately, the functional manager is not able to attend the meeting and informs the project manager that there may not be any resources available to test the software.
What should the project manager do?
During the third iteration of a project, the product owner requests another mandatory feature. This also happened in the previous two sprints, which resulted in failure and caused frustration within the team.
What should the project manager do next?
A multimillion-dollar project has started and is in the execution phase. A local regulatory authority has just announced changes to the requirements that will need to be implemented in 6 months, prior to completing the project execution phase.
What should the project manager do next?
A key customer stakeholder asks the project team to include new tasks in the backlog and begin analyzing new requests. The customer expects results as soon as possible and pressures the team to attend noncritical meetings. The team is frustrated by this situation.
How should the project manager approach this situation?
An agile project team received an assignment to develop an industrial system that interfaces with robots. The project team does not have any previous experience
performing this type of work. Team members are interested in acquiring such expertise but it may result in a project delay.
How should this situation be handled?
At a recent steering committee meeting, the project sponsor asked the project team to add a major feature to the final product. After consulting
with the project team, it is determined that the change will cause significant impacts to the original project delivery date and budget.
What should the project manager do to assess the priorities and meet the new objective?
A project manager is working for an organization in country A and has been tasked with opening the first brick-and-mortar store in country B. The sponsor has identified the city for the store and wants to minimize any potential issues with the local government.
Which action should the project manager take to address the sponsor's request?
A project team member is struggling to deliver an assigned task. In a team meeting, the project manager determines that there are other members
on the team who have more experience with similar tasks.
What should the project manager do?
An agile team wants to maximize the work delivered for the upcoming project that involves considerable product complexity. What should the
project manager do to help improve the team's collaboration approach?
A team is using an agile approach to maintain the project backlog. A new project obstacle was identified as a blocker and added to the backlog list. The team is facing challenges to remove this obstacle
What should the project manager do next?
A company has undertaken a large transformation project in preparation for the changing economy. During the planning of the transformation project, the key resource from human resources (HR) refuses to approve the proposed project plan.
What should the project manager do to gain an understanding of the cause for the resource's refusal?
A proof of concept for a proposed solution was conducted during the project implementation, and it was determined that the current technology cannot support it. What should the project manager do next?
A software delivery project began having technical impediments. The issue may cause a delay of the deliverables. The technical service team has been working on the issue, but the issue is unresolved even after 1 week of maintenance.
What should the senior project manager do now?
In an agile project that is about 45% complete, most team members are siloed and lack an understanding of each other's work. What would have
most likely caused this communication breakdown?
A project team was hired to perform on-site duties, but there were unexpected circumstances that required the entire team to work remotely Some team members returned to their hometowns and they are now requesting reimbursement for operational expenditures
What should the project manager do?
A project is designed to provide local community members with health facilities that will support improved sanitation practices. What should the project manager do to
ensure the community members are up to date on project progress?
An insurance company is planning to make a big change to its core application. The project manager realizes there is resistance to change from the sales agents since they
are accustomed to taking orders manually and entering them in the system at the end of the day. With the new change, they will use point-of-sale devices to take orders online.
What should the project manager do to get commitment from the sales agents?
A project manager just finished a meeting to identify the main stakeholders of the project. What should the project manager do next?
A project manager is managing an internal project with a tight budget and schedule. While executing the project, the project manager realizes that
some stakeholders are working against the success targets of the project.
What should the project manager do to ensure successful project delivery? (Choose two)
A learn member has a sudden emergency that may last for several days. There are no other team members who can cover their tasks and job duties. What should the project manager do to address this concern?
The investment committee is the authority for the approval of funding required for a business improvement project. The investment committee approved funding to complete
the preliminary feasibility study. The project is on an expedited schedule, and the project manager requires interim funding to continue with the preliminary feasibility
activities that must commence immediately.
How should the project manager get these funds approved?
An organization is transitioning to an agile approach. At the project's first sprint review, the product owner did not accept the result of the sprint and has some concerns.
What should the project manager do?
A project manager is working in a company that has several global offices. During resource planning for a new project, the project manager realizes that the company requires projects to include team members from different continents.
What should the project manager do to ensure a successful project execution?
A key stakeholder has recently started in a company and has been assigned to a hybrid project. Although very experienced in their domain, the stakeholder has only been exposed to predictive project approaches.
What should the project manager do?
A customer complains that the user stories released so far contain too much jargon and do not reflect the expectations of the product. What should the project manager do
next?
A technical team for a project is managed by the lead who was recently promoted to this role. Inside the team, a mature and experienced engineer is constantly questioning the actions of the team lead and is currently ignoring part of the team lead's decisions. The team lead asks the project manager for help.
What should the project manager do?
A concerned project team member complains to the project manager that another team member is being disruptive and argumentative during team meetings. The project manager received some information that the team member recently overcame a difficult personal situation.
What should the project manager do to address the concem9
A project manager has been authorized to begin a project and realizes that an effective high-performing team is needed to finish the project successfully. What should the project manager do next?
A project manager is working directly with a vice president who is also the project sponsor. The project is an organizational transformation for a company that primarily works on predictive projects. The project manager has been asked to use a hybrid approach to deliver before a defined date by using sprints.
What should the project manager do first?
During the execution of a project to develop a prototype, the customer asks the project manager to stop the prototype line and purge a specific
component based on recent reliability tests that have deemed the component to be deficient. The project manager checked the quality
management plan and there is no reference to this component.
What should the project manager do next?
A project manager is assigned to a project related to taxes, which will be managed using an agile approach. By reviewing lessons learned from a
previous project, the project manager discovers that a key stakeholder is an expert on taxes and is willing to help.
How should the project manager leverage this information?
A team needs to follow defined cybersecurity compliance that is mandatory for a customer project. What should the project manager do to monitor compliance in the
project?
A project manager has just taken over a project that is in the requirements gathering phase. A stakeholder indicates that they have not received any progress updates even
though reports have been sent on a weekly basis.
What should the project manager do to ensure all stakeholders are receiving proper information about the project?
An IT company's office is closed abruptly due to a new government restriction. All employees are now working remotely. Project team A has a
critical project delivery due in 2 weeks. The project manager, apprehensive about this sudden change, instantly emails the customer explaining
that the project delivery will be delayed. The customer is unhappy with this and has escalated the issue to senior management.
What should the project manager have done differently?
A geographically distributed project team working on an iterative project adopts a new mode of communication following changes in health protocols. The colocated team members are finding themselves challenged with understanding verbal communication and collaboration methods.
What should the project manager do?
A project manager in one country is reporting to a lead project manager for a new software development project in another country. The lead project manager constantly
requests updates from the project manager, often demanding information via multiple communication channels if the project manager does not respond within a few minutes
of a request. Both of them are equal in seniority and both report to the same functional manager.
How should the project manager proceed?
A project manager is managing a large project. A stakeholder has just discovered a new risk that has not been identified in earlier stages.
What should the project manager do?
A project manager is managing a new development program to automate some technical functions. During project kickoff, the project manager
expresses the need for a technical architect to support the project for a moderate amount of time. The project sponsor informs the project
manager about an existing technical architect who possesses valuable knowledge but is already assigned at the portfolio level.
What engagement model should the project manager use for the technical architect role to ensure project success?
A company is running a project to eliminate a sales channel that has been unprofitable for the past 3 years. A key stakeholder from another area, who has legacy ties to that sales channel, objects to the project.
What should the project manager do in this situation?
A project's business case was just approved and the project manager is creating the benefits management plan. It is unclear how the benefits from the project align with the organization's vision.
What should the project manager do first to verify alignment?
While managing a project using a hybrid approach, the project manager realizes that there is a high level of rework due to quality issues. Because
of that, each feature is taking longer than initially estimated.
What should the project manager do to address the issue?
During the execution phase of a healthcare IT project, the project manager finds one stakeholder is very difficult to communicate with and obtain
feedback from on project deliverables. What should the project manager do?
A project sponsor is concerned that the scope is not being met correctly and has questioned several team members about this individually. When the project sponsor approached the project manager, the project manager realized that the issue was that the project sponsor understood the scope in a different manner than the project team.
What should the project manager do to address this issue?
A project manager is made aware that there are defects in the parts provided by a supplier, which are causing delays in the testing phase. The supplier claims that all parts have been delivered as per the contract. If the defects are not fixed by the supplier within one week, the product release will be impacted.
What should the project manager do?
An agile team completes a deliverable that is to be certified by another expert team. The second team does not take the deliverable for many months.
What should the servant leader do?
A project manager is leading three projects in a program focused on starting product commercialization. Once the three projects fareket, the project manager stops attending the recurring team meetings. The program manager asks the project manager to continue attending these meetings to maintain those team touchpoints.
This request does not match the project manager's expectation, since a program manager is overseeing the remaining work
How should the project manager approach the situation?
A project manager works in an organization that embraces using different project approaches. The project manager's current project uses a
predictive approach with clear requirements. A few months following the kickoff, the project manager notices that the virtual development teams
are not communicating enough, and coordination is becoming an issue. The teams are not aligned on the tasks being done or the current
impediments.
What should the project manager do?
Within a project, senior management is requesting project information so they can analyze the data to make project decisions. What information
should the project manager provide so that senior management can get a broader view of the project?
In a project, one core team member tends to do all the work and ensures all tasks are completed. This core team member is soon leaving the project, which may make the project vulnerable.
What should the project manager do?
An agile project to provide a material information system has started. During the kick-off meeting, the team realizes that the stakeholders require a solution in 2 months, but it will take at least 4 months to deliver the entire project.
Who should the project manager contact to help the team accelerate the delivery?
An iteration is almost finished, but the team is struggling to complete the stories that require more time. What should the project manager do first?
During the execution phase of a project, a project manager notices that the project team is not motivated and performance is decreasing. The decision is made to invest in financial rewards for all of the Key team members. After the rewards are distributed, the team is still underperforming.
What should the project manager have done to avoid this situation?
A project manager identifies a risk that has a high probability of occurring. How should the project manager manage this risk?
In an organization with good work-life balance, one team was continuously overloaded, thereby delivering the product ft quality. What should the project
manager do?
A company's project management office (PMO) has started to implement iterative tools. The project manager is starting a new project and has
identified an opportunity to use the new tools. There is disagreement among stakeholders about the use of the adaptive tool.
What should the project manager do first?
A project manager has established daily standup meetings with the team during the execution phase of the project. The project manager has been successful in removing 75% of the
obstacles reported, but the timeline continues to deviate further each day with no signs of improvement.
What should the project manager have done to avoid this issue?
During a project's initiation phase a lessons learned sharing session was held with the team from another project Low construction productivity was discussed as a potential delay to project completion
What should the project manager do next?
A project manager is facilitating a project steering committee meeting where the prioritization of work items in the backlog is being discussed. The
engineering executive wants to prioritize features based on level of effort, completing the smallest items first. The quality executive wants to
complete the most complex tasks first to have adequate time to ensure a quality product is delivered. The compliance officer wants to complete
items with associated regulatory components as they are essential items.
How should the project manager prioritize the work items?
A project manager is working with a colocated agile project team that has worked together long enough to be in the performing phase of team development. An unforeseen event has caused the team to be dispersed and they are now unable to colocate.
What should the project manager do to keep the team performing as effectively as possible?
A project is about to start. The project manager has found that the client does not have an appropriate knowledge management system and does
not have a requirement for it.
What should the project manager do?
A telecommunications project consists of departments spread across several countries with different cultures. The project team rarely meets in person, and each team member works independently using online reporting tools.
What should the project manager do to ensure team members are committed to project success?
A project manager wants to ensure that the project acceptance criteria are met for all project deliverables. What should the project manager do to accomplish this?
A project manager who is new to a matrix organization has just been assigned to an internal software development project that is intended to
reduce conflicts in the company’s internal tracking system. With over 1,000 people in the company who will benefit from the software, the project
manager wants to ensure everyone is aware of the great progress the team is making. The project manager meets with the project team to decide
upon the most effective way to communicate progress.
What should the project manager do?
A project manager is assigned to a project that is in the execution phase that has different types of stakeholders. Some of the stakeholders are very interested in the project, whereas other do not show the same level of interest.
What should the project manager do to assure the project finishes correctly?
An organization is transitioning to agile. The project manager is discussing how to manage risks with the development team in light of the transition for a particular project.
The team estimates the risk level as low.
What should the project manager do?
A project manager in an automotive company is scheduling activities for a complex project Some of the project requirements are fixed and some are flexible Match the items on the left with the methodology on the right that the project manager is using.
After an executive-level reorganization, the new project sponsor is not keen on continuing with the project. What should the project manager do?
During the project planning phase, a project manager is informed that they cannot start one activity before another department implements the
required IT system. What should the project manager do?
The first task a project manager needs to complete on a new project is improving stakeholder engagement. How should the project manager complete the power/interest grid based on the following scenario:
• The marketing director is the key stakeholder. as the project will create a new product for the company.
• The finance director is providing funding and does not have much time to follow the tracking of the project.
• The sales representatives assigned to the team provided some negative feedback on the requirements
• The human resources (HR) intern assigned to the team was satisfied with the new product interlace.
A product owner has returned from a meeting with a few key stakeholders, who expressed interest in learning more about the project progress. The product owner is
seeking the project manager's recommendation on how to approach this request.
What should the project manager do to help the product owner?
During a system demo, a project stakeholder rejects the features completed from the most recent user stories. According to the stakeholder, the product does not meet the
quality standards required by regulations.
What should the project manager have done to avoid this?
A project manager receives an email from a customer saying that they do not want to keep working with one of the project team members. The customer does not provide
any reasons for this sentiment. The project manager is concerned because this project team member is highly skilled and experienced and is key in one of the main project deliverables.
What should the project manager do to ease the situation?
A project manager is working on a project to build a manufacturing complex. The project will run in three different phases: engineering, procurement, and construction. The
procurement phase is in the initiation stage. The project sponsor wants to pursue the project phases as they have been planned, but also wants to accommodate and adjust to new data, input from the customer, and changes during the various phases as the project progresses.
How should the project manager approach this project?
A healthcare organization hired a new compliance specialist to ensure that the healthcare compliance needs are met. The feedback about the new compliance specialist
from the team was average.
What should the project manager do to help the new compliance specialist improve?
A project team is working on a product that is planned for multiple iterations. They are delivering incremental value.
When should the value be demonstrated?
A new team member is assigned to a team that consistently delivers each iteration. The new team member is does not understand many of the processes followed and begins to negatively impact the schedule.
What should the project manager do?
A project manager holds meetings every Monday to review the team members' progress. The project sponsor is insisting on daily updates to ensure improved delivery on products developed by all of the teams, including this one. Some learn members indicate they are on a very light time line and would attend me Monday meeting, but not the daily update meetings.
What should the project manager do to ensure all team members participate in daily meetings?
A team member shares with their functional manager some negative details about the performance of another team member that was discussed during the retrospective. The project manager finds out about this discussion
What two actions should the project manager take? (Choose two)
A project manager has received an updated earned value analysis report The following are the key findings from the report
•Budget at completion = USS1 million
•Earned value = US$0 7 million
•Actual cost = US$0 75 million
•Cost performance index = 0 933
Based on this information, what should the project manager conclude about project performance'?
A project manager is managing a hybrid project After attending an iteration review, a stakeholder tells the project manager that they are very busy and asks why these reviews are held so frequently.
How should the project manager respond'?
A project sponsor commonly asks the project manager to skip project retrospectives due to time constraints However the project manager persists in running this critical ceremony by reducing the time for preparation and for discussion
What are two issues that these actions by the project manager could cause? (Choose two)
During a retrospective meeting a project manager hears that stakeholders have been constantly complaining at iteration demos about product features not being delivered as requested. What advice should the project manager give to the Product owner to ensure that product features are always delivered as requested?
A new team member is added to a self-organizing team. The new team member is reluctant to speak and take part in team discussions or decisions.
Which two actions should the team take to engage this new team member? (Choose two)
At the end of a meeting a functional manager takes the project manager aside to raise some concerns on behalf of a project team member who is unclear about their role and responsibilities for the project What should the project manager do in this situation?
A project manager for a government organization often deals with stakeholder engagement issues Drag the interpersonal skill the project manager should use on t he left to the correct situation on the right
A new agile team is forming and the project manager notices that the team is struggling in many areas The team is experiencing both the inability to meet iteration commitments and team member conflicts
What should the project manager do next?
The project manager of an agile project has been asked to reduce the budget by 30% Since this is a small project team, the budget is primarily allocated to resources
What strategy should the project manager use in order to keep delivering value in a restricted environment?
For the purposes of quality assurance a quality audit was conducted on the processes being used in the project execution plan. One of the nonconformance issues raised by the auditor was that attendance lists for the project risk review meetings were not available
Why is an attendance list important?
During the review of a project's list of deliverables, one of the stakeholders expressed concern that one of the requirements will not be addressed. What should the project manager do?
A new project manager is planning an information security project for a company that resides in different countries. What is the first step the project manager should take to gather customer requirements?
During a project’s third iteration, two of the existing team members were replaced As the project entered the next iteration, the team velocity dropped and the performance started to slip.
What should the project manager do?
To estimate the costs of a new project that is similar to a project that was implemented last year, the project manager meets with a group of experts from the previous project The group uses a three-point estimating technique The project manager submits the estimated budget to the project sponsor for approval The project sponsor, who is new to the company, is concerned because the budget exceeded their expectations
What should the project manager do?
An agile project is in its sixth iteration out of 10 After the iteration review, the team receives feedback from the stakeholders that could result in a change in the product What two actions should the project manager take? (Choose two)
During initiation of a new product improvement project, a project manager finds historical data showing that a similar project resulted in customers complaining of an even worse user experience compared to the previous product version
How can the project manager prevent this outcome in the new project?
In a software development project, the product owner and development team agree on a sprint backlog The highest priority in the backlog is to build a payment module The team worked on the module during the first half of the sprint, but now two developers want to spend the rest of the sprint focusing on refactoring another feature that might create issues in the future.
What should the project manager do?
During an inspection, the production phase was stopped because the inspector claimed that regulatory labels were missing. What should the project manager do?
A project manager invites the company CEO, sponsor, team members, and an external client representative to a meeting to review the project management plan. The project manager starts to present the budget but the CEO suddenly asks to end the meeting
What should the project manager have done to avoid this situation?
A project manager is assigned to a project within a program. The high-level requirements of the project are known, but the priorities of some of the requirements are uncertain as they are interdependent on some other pipeline projects within the program.
How should the project manager prepare for the next steps of the project?
A new project has been kicked off following a planning session. The project is under direct oversight of an executive in the organization After a review meeting, the project manager overhears an executive request a dashboard from one of the team members to show the overall project status
What should the project manager do?
A project manager is managing a hybrid project. After attending an iteration review, a stakeholder tells the project manager that they are very busy and asks why these reviews are held so frequently Record the issue in the issue log and escalate the conflict to the project sponsor for assistance.
How should the project manager respond’
An agile project manager would like to convert the requirements document into epics, capabilities, features and stories In how many iterations should the project manager estimate the story duration?
During the execution of a project, the finance team identified that they were not involved in building the business case for the project and will not approve the estimated return on investment (ROI). What should the project manager do?
A project manager is assigned to a global project where, during the planning process, team members from different regions are not agreeing to collaborate with each other What should the project manager do?
An external project manager is managing the construction of new corporate offices for a large company The project management plan states that it is necessary to contract a highly trained external resource to revise and validate an important project component The client has rejected hiring the external resource because of the high cost even though it is within the project budget.
What should the project manager do to resolve this issue?
During the execution phase of a healthcare IT project, stakeholders made a change request regarding user requirements There is no remaining budget available to cover that change request.
What should the project manager do next?
During the implementation phase of a project, a new regulation affects the project, and a critical status meeting discussing the scope changes is required. The project manager discovers that a key stakeholder cannot attend the scheduled meeting
What should the project manager do?
During the daily meetings with the team the project manager notices that a new team member is not making the expected progress on an assigned task What should the project manager do?
During project execution, a project manager is informed that most of the project team members have enrolled in the newly implemented work-from-home company policy. How should the project manager reflect this change in the project?
A Scrum team has committed to delivering a specific capability in their first release Multiple operational issues have prevented the developer from delivering key capabilities. The technical lead has also given notice that they are resigning from the company
What should the project manager have the Scrum team do to recover from these issues?
An integrated project involves the interaction of both hardware and software and the sponsor has approved the schedule management plan The project team evaluated the product's feasibility of functionality and accelerated testing What should the project manager do as a servant leader?
A project manager has a team of shared resources from other projects who are working on a client project Three days before the project is due. The team informs the project manager that the project will be delayed because a component was not delivered on time Competing priorities of the shared resources are delaying delivery of the component
What should the project manager have done to prevent this delay from happening?
A retail chain is evaluating a project to replace payment systems across all its stores in multiple locations The project does not pass the financial threshold but is also expected to increase market share, improve customer services and retain more customers The project is planned as a phased implementation building on learning from the retrospectives during each phase
How should the business increase the value of the project?
An organization is embarking on the deployment of a new digital solution that will revolutionize purchasing services The project manager has created all the necessary plans and activities to ensure a successful integration and solution launch There is a risk of a partner’s system being unavailable which could impact the project negatively
What key activity is needed to ensure the project's success?
A project manager is struggling to figure out the performance of the project teams in an agile environment for the same scope of work, team A has calculated 100 story points and team B has calculated 125 story points
Which team is performing better?
The client will not agree to closure, claiming that the project team has not performed the code inspections mandated in the development contract. The project team has performed the code inspections, however the records are not complete What should the project manager do?
How should the project manager develop the project management plan to ensure that the project continually delivers the expected benefits?
A product owner presented the backlog to the team, and the team raised concerns over implementing some of the features due to various impediments What should the project manager suggest that the product owner do next?
A team has been working on a project for several months,, but the completion date is unclear because the scope is changing frequently as new knowledge is gained. Some deliverables have already been completed, but when new stakeholders join the team, they complain that project outcomes are not meeting business goals.
How can the project manager prevent this situation from happening in the future?
A stakeholder on a project has a reputation for being easily angered and unreasonably difficult on projects The project manager would like to minimize the impact of the stakeholder’s behavior on the development team.
What training should the project manager choose for their team to help with this situation?
A technical subject matter expert (SME) identifies an occurrence that should be captured in the project's lessons learned The SME asks the project manager to write, document and include it in the lessons learned register
What should the project manager do?
The project manager is experiencing delays with two critical tasks that are to be executed by two different teams The project manager realizes that the functional managers of these two teams have an unsolved conflict and they are not communicating properly.
What should the project manager do?
A project manager created a contingency plan associated with a risk. The risk was realized, but the client insists on using a new workaround instead The requested workaround will introduce delays and require additional budget
What should the project manager do?
A company recently used desktop research for a feasibility study, which showed that the project is behind schedule The project team also has concerns about the impact of scope changes on the project schedule
What should the project manager do to keep the project on schedule while still meeting project objectives'?
A learn has been working for two months and has consistently missed planned user stories How should the project manager address this issue?
A large multi-year project requires highly skilled staff for successful deployment The management team and the project sponsor have analyzed the resource requirements and agreed to have permanent staff hired for the project to avoid potential budget overrun However there is a risk of staff turnover during the course of the project, which may have an impact on the delivery
Which two actions should the project manager take to mitigate this risk? (Choose two)
A project manager is m the middle of a project when one of the key project team members needs to take an unexpected and prolonged leave of absence The project is ahead of schedule and running under budget
Which two actions should the project manager take initially to resolve this problem? (Choose two)
During the execution of a project the project manager notices that only one team member has one of the technical skills needed to build the product The project manager is afraid this might have a future impact on the quality and schedule because most of the upcoming activities will require at least three people with this specific skill.
What two actions should the project manager take to prevent the team from being unqualified? (Choose two)
During the last sprint review the product owner stated that the product does not deliver any value The project manager believes that the product meets all the provided specifications
The team is confused by the product owner's statement
What should the project manager do when using a hybrid approach?
A team has been struggling with various issues during the course of an iteration. The project lead facilitates a discussion of the issues and the team forms new team agreements. During the next iteration, some of the same issues appear again
What should the project lead do next?
During a retrospective review, many project team members say they are not completing tasks during the iterations because of interruptions and requests for help from other teams As a team facilitator, what should the project manager do to avoid this?
A large project is affecting the neighborhood in which it is located The neighbors are not satisfied with the project and their resistance to the project may affect the project deadline
What two actions should the project manager take'? (Choose two)
After reviewing the project management plan with key stakeholders, the project manager was told that an 18-month release plan was unacceptable and the product should launch in six months. Based on the new timeline, what should the project manager do?
An agile team is geographically separated across multiple continents, and the project manager of identifying the tools to manage the communication among the virtual teams Drag the appropriate tool on the left to each project task on the right
A project manager is assigned to a project in a company that is transitioning to agile Not all stakeholders believe in the project, and some stakeholders would like the entire project defined and planned out early in the project However the project sponsor needs a quick win to ensure the continuation of the project.
What approach should the project manager use?
Some members of a project team are frustrated by a new team member who previously worked in a Scrum setting This new team member approaches members of the project team on a daily basis in what appears to be an attempt to engage in individual standup meetings
What should the project manager do?
From previous lessons learned working with a client, a project manager notes that the client's turn-around times on documents sent for approval were very slow and well outside of the agreed timelines At the initial kick-off meeting with the same client, how should the project manager approach this issue for the new project?
A project manager of a large company needs to categorize the stakeholders' involvement at the beginning of a project initiated by the board of directors. The sales and delivery teams are internal teams.
Drag each stakeholder scenario on the left to the correct engagement level on the right.
A project manager is assigned to a new marketing campaign The sponsor gives the project manager an approved project management plan for review and explains the scope, business requirements, deliverables and stakeholders The project manager asks to see the project charter to gain a better understanding of the project. The sponsor says the project is small and simple so there is no need for a project charter.
What should the project manager do?
The team has reported the following impediments at the daily standup meeting Drag each impediment on the left to the action that the project manager needs to take on the right
A project manager has been managing a project for several months when an issue that had not been registered as a risk appeared. This issue may have a big impact on the project.
What should the project manager do?
Drag the organizational characteristics on the left to the correct scenario on the right
At the end of a project with multiple suppliers, the project manager is reviewing the closing process and finds that an unexpected financial balance is remaining What will help the project manager understand why this has occurred?
A project is in the knowledge transfer phase, and a few subject matter experts (SMEs) went to the client site for knowledge transfer The SMEs captured various process deviations without sharing with the project team
How can the project manager ensure knowledge transfer across the team?
During the planning stage of a project the project manager realizes that a standard stakeholder engagement approach will not suffice One of the client representatives, who is not a key decision maker, is extremely opinionated This client representative could become a roadblock to progress due to their perceived level of authority during meetings
How should the project manager handle this moving forward?
A team member misses a project meeting without it being approved and has been penalized as defined in the ground rules. This team member, as well as other team members, insist that it is the first time they have seen this rule regarding the project and they do not agree with the penalty
What should the project manager have done to avoid this situation?
A project manager is leading a large-scale project that involves 70 stakeholders The project manager has heard various comments and expectations from the customers, some of which are contradictory Consequently, some requirements are not clear.
What should the project manager do to build consensus regarding the requirements?
During the implementation phase of a construction project the customer asked a key subcontractor to deliver a work package ahead of time The subcontractor was not prepared for it and asked the project manager for additional budget What should the project manager do first?
A key project stakeholder showed interest in the beginning of a complex agile project but has become less involved as the sprint has progressed due to additional responsibilities A few sprints later, the key stakeholder rejected a feature deliverable The team is reworking the rejected deliverable for the next sprint
What should the project manager have done to avoid this situation?
In a newly formed project team one experienced team member is overwhelmed by the complexity of the tasks and is not happy with the project team. What should the project manager do?
A project manager has been using predictive methodology for more than 10 years and is switching to an agile project. The team members have not previously worked together. After two sprints of work, the team has not achieved any outcome and there is a lot of pressure to get work done
What kind of leadership style should the project manager use at this stage?
A verbal announcement is made that the new team member joining the Scrum team has limited mobility The scrum master is aware that some team members are unsure how the dynamics of the team will change
What should the scrum master do?
A technical manager newly appointed by the client, visits the project site to verify the project deliverables The technical manager feels that the project manager has not been providing enough information
What should the project manager do first to resolve this situation?
A project manager has been appointed to a multimillion-dollar project The project is considered to be high risk since no similar projects have been undertaken before and there is no historical data Some external stakeholders are reluctant to provide support
What approach should the project manager take?
A project manager is tracking a project, but a key stakeholder will not accept the project's key performance indicator (KPI) results Which tool or technique should the project manager use?
After reviewing the project management plan with key stakeholders, the project manager was told that an 18-month release plan was unacceptable and the product should launch in six months. Based on the new timeline, what should the project manager do?
A project manager is approaching the end of a project, and several tasks are now practically complete and ready for handover to the client How should the project manager proceed?
Two functional managers disagree on key features of one deliverable during the planning of a project The project manager discovers that each manager included requirements that contradict each other The functional managers do not want to meet with each other to find a solution This situation has been escalated to the sponsor who requests a meeting with them
What strategy should the project manager use to resolve this conflict in the meeting?
The change control board (CCB) rejects a change request submitted by a subject matter expert (SME) The SME refuses to accept this rejection and does not want to continue the project without the change
What should the project manager have done to avoid this situation?
A team is working on implementing a communications system when the client says that they are considering closing the project. The project manager schedules an urgent meeting with the client to understand why the project is at risk Which two tools or techniques can the project manager use to influence the client’s decision to keep the project active? (Choose two)
One of the main inputs required for a deliverable is missing due to a miscommunication between the vendor and project manager Because of the missed deliverable, the critical path of the project is extended
What should the project manager do next?
One of a project manager’s team members is continuously improving This team member has been a role model and mentor to others in the organization
How should the project manager acknowledge this team member’s commitment?
A company is using a predictive approach for the development of a particular component as defined in the scope management plan Due to regularly changing regulatory requirements, the development team has requested to utilize agile approaches
What should the project manager do about the development team's request"?
Due to a company merger and acquisition process, the main stakeholder of a critical project has been changed This new stakeholder complains that they were unaware of a delay on the project of which the rest of the stakeholders were aware. All the communications about the project are shared via email at the start of every week.
How should the project manager address this situation?
Which three of the following scenarios are impediments to which a scrum master should pay attention? (Choose three)
A project manager who is new to an organization observes that an approaching deadline is likely to be missed because there have been some delays on the project due to a lack of resources. What should the project manager do next?
During project execution, the project manager notices that the work performance reports have deteriorated drastically in less than two weeks The project team in country A is complaining about delays resulting from holidays occurring in country B that have impacted their project team
How should the project manager handle this situation?
A new team member has joined an agile project, replacing a team member who recently left The project team needs the new team member to speed up their ability to contribute effectively to the project
What should the project manager do to help in this situation?
Some of the mote experienced members of a project team have complained about the project manager The senior project team members feel that the project manager is micromanaging them and preventing them from completing their work.
What should the project manager do when made aware of these issues?
A project manager is managing a project which has a very complex and long execution period Although the project is mostly predictive, the team was able to break the design and execution into smaller packages using a hybrid framework The business wants to keep track of the value delivered by this framework application but there is no defined set of measurable items for the framework.
What should the project manager do first?
A project team is experiencing delays in completing a task that turned out to be more complex than initially estimated. This is a critical task that could impact current iteration goals
What two options will help the team initially address this obstacle? (Choose two)
A project manager is leading a meeting with key stakeholders, the project sponsor and the product owner to define the features that will be released after the next iteration. The purpose of the meeting is to review the product backlog prioritization, considering that during the past iteration some deliverables were not completed.
Which two items should be taken into account first to review and update the product backlog priorities during the meeting? (Choose two)
A key stakeholder for a construction project has been spending a lot of time at the site and interrupting the team's efforts What should the project manager do in this situation?
A project manager has been managing a highly complex project. The project manager has ensured that all of the required tasks have been completed. During a recent external audit. The project manager was informed of a heavy penalty being levied on the project for the latest module that was implemented
What should the project manager have done to ensure that there were no liabilities arising from the recent implementation?
An agile team member received certification on a new tool: however, this learn member is complaining that the rest of the team is not using the tool due to lack of knowledge How should the servant leader apply emotional intelligence to leverage this situation to benefit the project?
At a meeting to receive approval for the project management plan, a project manager realizes that there is so much detail in the presentation that many of the stakeholders are not actively engaged in the process. The stakeholders are agreeing to the scope, goals, and timelines without giving them substantial thought.
How should the project manager proceed?
A project manager has been selected to deliver one of an organization's key flagship solutions Critical success factors include agility, market adaptation, and a quick response to market offerings
What is one of the key activities that the project manager should undertake to ensure company success?
A project manager is in rapid development mode on a joint application development module The company wants delivery to occur in two weeks The module needs to be integrated with other modules on a similar timeline, but release management has a three-week backlog
What should the project manager do?
An intern is replacing a critical resource midway through a sprint To help the intern get up to speed, the project manager assigns a senior engineer in the team as the intern's mentor Two months later, the project goes into critical status, delaying the release milestone by a month.
What should the project manager have done to avoid this scenario?
The team architect resigned from the company. The new architect points out a
design flaw during a planning meeting that may potentially impact the final quality.
What should the project manager do first?
A project needs to purchase a specific piece of equipment, as stated in the
project documents and approved by the project sponsor. The procurement division is
questioning the need to buy the specific brand of equipment and has suggested buying a cheaper alternative instead.
What should the project manager have done earlier in the project to ensure the purchase of the specific equipment?
The project manager of a large construction project discovers that the blueprints received from the client appear incomplete. What should the project manager do first?
An organization uses a hybrid approach to project management. A project manager has been assigned to an external project, project A, where two of the three modules in the project require machine learning skills. The only machine learning expert in the project manager's organization is engaged in an internal project, project B, that is about to end.
What should the project manager do?
A project manager is managing multiple teams. One team member complains to the project manager about the favoritism shown by a team lead to another team member and cites multiple instances.
Risk Response Strategies Analyze if someone else could contribute Record the observations and move ahead Check for options to exclude the stakeholder
What should the project manager do to resolve the team member's concerns?
Due to a recent budget reduction, two team members were released from an agile
team. The customer is still expecting early results for the project.
Which two actions should the project manager take to align customer expectations? (Choose
two)
A project manager for an agile project wants to have a highly engaged team. How should the project manager achieve this objective?
A large company has agreed on a business case for an environmental project. The
project will cause some major changes in their operations, such as reduction in paper use,
which will obviously affect all of the users.
What is the first thing the appointed project manager should do?
An events company is planning their annual event for a retirement fund. The organization has run the event planning using agile approaches for the last 3 years. During the initiation phase, while assessing possible risks and improvements for the event, the project manager uses previous event feedback to assist in developing the risk register.
Which ceremony should be used in developing this register?
A company Is helping their client launch an Innovative product. During the sprint review, the product owner identifies that the product does not include key features that were previously prioritized as part of the product backlog.
What should the project manager do next?
During a regular review, the project manager of an agile project realizes that a key stakeholder is missing critical information about some features being developed. In order to improve communications and reduce the risk of deploying the wrong features, what should the project manager do?
A large organization decided to adopt an agile methodology based on the trends
seen in the industry. The organization invested a large amount of money in adopting it, but
after a few months, the implementation failed.
What should the project manager have done differently to avoid the implementation failure?
A project manager finds that team members In an agile project are involved in several different projects due to budget constraints. What should the project manager do?
An agile project team discovers that they are unable to implement a feature completely in the first iteration The team believes it may not be able to complete the tasks in the second iteration. The feature is a critical component that the customer has prioritized.
What should the team do?
A contractor delivering construction services to a company is using agile principles
to manage the project tasks. Engineers are producing frequent design changes due to new legislation. There is a risk the contractor may lose money due to resources waiting on design
changes or performing rework.
What should the project manager do to minimize the cost?
A project manager has just been assigned to a team that is developing a new design product. The work breakdown structure (VW/BS) has been created and the activities have been assigned to the team members. The project manager finds that there are activities that could be completed sooner by other team members. If the current assignments are left as is, the project could be delayed 2 weeks.
What should the project manager do in this situation?
The project management office (PMO) assigns a project manager who specializes in hybrid approaches to a predictive project that is off track from both the cost and schedule perspectives. The project runs into further delays as the project manager is ramping up on the project. The stakeholders and ask senior management to replace the project manager.
How should the project manager approach this situation?
local company is developing a new product and. for the first time, using a remote
team for the programming tasks of features. The design for the product comes from the local team. During the third sprint review, the product owner has concerns about the project's
outcomes. The remote development team is complaining that they do not clearly understand the requirements conveyed in the daily standup meetings.
How should the project manager address this situation?
Two team members were recently released from a project because the customer reduced the budget. However, the agile team is still receiving the same, if not more, work requirements as before.
How should the agile project leader resolve this situation?
An agile project team is building a new product. The stakeholders require ongoing
illustration of project business value.
How should the project manager proceed?
In a construction project for a new building, the project manager decides to apply agile principles for the building foundation phase While evaluating the project schedule with the team, the project manager believes that the estimates are inaccurate. How should the project manager address this issue?
A team has been consistently delivering outcomes. However, based on their current performance, it was discovered that their velocity has decreased by 30%.
What should the project manager do to ensure the velocity is under control?
A project manager for a building construction project is planning to go on vacation
midway through the project execution phase. What should the project manager do first to
ensure the team is empowered and deadlines are met?
A project manager is assigned to a strategic communication project that involves
subject matter experts (SMEs), interns, and new recruits. The project manager discovers
that the project is not gaining much traction due to knowledge gaps from the interns. The
budget for training is exhausted and the project needs to be delivered without delay.
Which two actions should the project manager take? (Choose two)
A project started 12 months ago and is currently on iteration 12 of 14. The team
has performed well and completed all deliverables on time. However, some team members
are starting to complain about the length of the project, creating a risk for lack of
performance at this critical stage.
What should the project manager do as a servant leader to mitigate this risk?
Experienced team members assigned to a critical project are also supporting several other projects and this is delaying the critical project. If this critical project is not
delivered, the company could receive a fine from the government. What should the project manager do?
Close to the end of a project, a customer claims that some deliverables have not
been met and starts initiating change requests. What should the project manager do next?
On a project to create the perfect paper airplane, the development of the airplane Is performed In iterations. The artwork to go on the wings and tail is done using a predictive approach. One of the stakeholders provides a requirement that conflicts with the product owner's requirements.
Who is responsible for analyzing the new requirement and making the final decision?
While developing a new product, a key stakeholder expresses concern about
insufficient information on product feature requirements. The product team disagrees and
mentions that detailed requirements have been provided.
What should the project manager do to handle this situation?
An important email from a project sponsor states that a backlog item should be immediately prioritized. What should the project manager
do with many tasks still open on the Kanban board?
A team has been working together for several months and has successfully
delivered work. A new team member has joined the team but is having difficulty
contributing.
What should the project manager do to help the new team member integrate effectively?
A project manager prepared the base budget model to deliver a highly
customizable software solution. The solution will be delivered in multiple countries with
significantly different cultures and will be staged over phases.
What should the project manager do next?
A project is behind schedule and over budget, resulting in a problem for the next deliverable. The project manager informs the stakeholders, who are very concerned about the project. What should the project manager do to alleviate the stakeholders' concerns?
For an agile pilot project, the sponsor arranged an early product demonstration for the customer. During the meeting, the customer realizes that a new feature will significantly improve the product
After collecting the new requirements, what should the project manager do?
A company that is introducing a new product into the market by the end of the year requires a storage and distribution facility to be built. During the monthly stakeholder meeting, it is discovered that the location for implementation is a government-owned area
What should the project manager do first?
A software system is being built for a company. Once the system is in production, the team would like to collect usage data to evaluate the delivered value.
Which evaluation practice should the project lead use to obtain accurate usage data?
The portfolio management office wants to cut costs by suspending some ongoing
projects that do not directly support the organizational strategy. The project manager has invested too many resources into one of the projects to be suspended, but the portfolio
management office has not backed down on their plan.
What should the project manager do to continue the project?
Early in a project, a team member failed to effectively communicate the reason for their absence from three team meetings. How should the project manager handle this situation?
During the execution phase, the project manager discovered that the deliverables
are not meeting the quality specifications requested by the main stakeholder. This has
caused the schedule performance index (SPI) to deteriorate from 0.98 to 0.72 and the cost
performance index (CPI) from 1.5 to 1.1.
What action should the project manager take to mitigate the issue of the deliverables being
rejected during the next iteration?
A project manager receives a call from the customer's account manager requesting support for a critical operational issue. Although the issue is unrelated to the project, the customer believes that one of the project team members has the technical expertise to recommend a solution.
What should the project manager do first?
A project team's performance has declined for the last three iterations Some of the team members are disappointed, and raise their concerns during the retrospective meeting What should the project manager do?
A project manager scheduled a session to identify risks on the current project. Most of the stakeholders did not attend the meeting, although they previously confirmed their attendance.
How should the project manager proceed in order to complete the risk register?
Since the beginning of a project, the product owner keeps asking during ceremonies about the budget spent for each product iteration The product owner seems much more interested in the cost rather than the product itself.
What should the project manager have done earlier to change the product owner's behavior''
A project manager is in the middle of an agile project comprised of 100 user stories broken down into five iterations Each user story is worth USS50 The actual expenditure is US$2,000 and 50 user stories have been delivered.
Which statement is true''
A project manager for a large project's agile team is developing new workflows to meet changing business needs. As the second sprint is running, the product owner and agile team begin to receive more details that impact the scope change of running items. The agile team
requests a change in the sprint goals and sprint backlog items.
What should the project manager do?
A project manager is assigned to a new project. Many of the project deliverables need to be outsourced.
What should the project manager use to document the project deliverables?
The project manager has finished all the tasks of the project and immediately starts on a new project. A few months after beginning the new project, the accounting manager asks for confirmation of previous projects because the budget is still open with no further cash flows.
What should the project manager have done?
A project is delayed due to an undelivered component, which was caused by a conflict between the procurement lead and the contracts manager. The project manager
schedules a meeting with the two stakeholders to resolve the issue.
What role does the project manager play in this situation?
A project manager is meeting with the project sponsor regarding a new project.
The project manager tells the sponsor that, as part of the communications management
plan, a weekly email will be sent with the status of the project, so the sponsor can be
informed of the progress. The sponsor indicates that the email is not necessary because
they will ask for a status update whenever it is needed.
What should the project manager do next?
A project manager is working on the budget for a long-term project. The project manager creates a work breakdown structure (WBS) and estimates the cost for each work package based on past projects.
What else does the project manager need to do before determining the budget baseline?
In a global project, the project manager has to plan and manage communication between the team members and stakeholders in order to ensure the project will remain on track and achieve its goals.
What should the project manager do?
A project manager is leading a product development project that requires high involvement from several stakeholders. What should the project manager do to ensure this involvement?
A project manager notices that the team lacks a subject matter expert (SME) in a specific area. This expertise will be required for many future projects.
What should the project manager do?
A project manager is transferred to another country to perform a project within their organization. What should the project manager do first to ensure collaboration within the team for a successful delivery?
An organization uses a predictive approach but is open to using some agile practices. The project manager was asked to recommend an agile practice to provide business value throughout the project.
What should the project manager recommend?
As part of a temporary assignment, a project manager is leading a business project During a daily status meeting, it is discovered that the project manager's former department has not completed a task This is delaying the current iteration.
What should the project manager do?
At the daily project meeting, team members are complaining about receiving emails from their functional managers to support other nonproject-related tasks. This is having a negative impact on the team's productivity.
What should the project manager do next?
A project manager is assigned to a new project. The project management office
(PMO) and the project manager agree that this is the right opportunity to include daily
standup meetings. The project team has never used such tools, and a few members are
challenging the decision.
What should the project manager do in this situation?
A company is planning a digitization project. Which action should the project
manager take first when defining the project scope?
During a project review meeting, several project team members expressed that they did not have an understanding of the benefits of certain features for the project What should the project manager do next?
A supplier was supposed to mobilize a government-issued, licensed piece of
equipment two days ago, but did not. The procurement manager was informed that the
supplier failed to check the validity of the license, which expired last week. The supplier had
already submitted an application to the authorities, but it generally takes one to three weeks to process the application, which will affect the critical path.
Which action should the project manager take?
A project manager is working on a major construction project. Part of the
agreed-upon plan was to use a cloud-based system with a server that runs on high-speed
internet service since most of the team members work virtually. The company needs to
reduce operating costs as much as possible and management insists that the project will
now use a system running on a conventional dial-up service.
What should the project manager do next?
In a functional organization, a product analyst is assigned to a short-duration application development effort The analyst expresses concerns about the task and asks the project manager to provide the support of a peer with expertise in this domain
What should the project manager do?
In the middle of an iteration a team member suggests a new method of doing things The method provides no value to the end customer, however it may help the team to work more efficiently The change may require several days of work to implement
How should the project manager respond to the suggestion?
In an agile project, the project manager notices that one team member rarely reports blockers during daily check-ins. Additionally, the team member is too shy to participate in team activities and prefers to provide status updates individually to the project manager.
How should the project manager rectify this situation?
A team member is hosting an event and invites several colleagues through their work calendars Another team member, who was not invited to the event, is noticeably distracted during several standup meetings
What should the project manager do?
A project manager brings in a new team member from an agile environment to work in a predictive environment The project manager expects to leverage the new team member's agile experience with the existing team members.
What should the project manager do to integrate the new team member effectively?
A project manager is assigned to a hybrid project involving multiple sectors. The sectors collaborated in the joint venture delivery facility.
The chief executive officer (CEQ) from each participating sector is a sponsor of the project. Each sector nominated project representatives, who in turn appointed a product owner who was the most experienced in delivering such projects.
Match the stakeholders on the left with the appropriate frequency for updates.
A project team is using one of the visual management tools to identify dependencies. It was identified that domain knowledge from one team needs to be shared with
another team to ensure the continuity of deliverables.
What should the project manager do?
In the past, the project manager and the project team performed well using
predictive methodology. However, the organization recently decided to adopt agile
approaches, and the project sponsor wants to use an agile approach in an upcoming project.
Before initiating the project, what should the project manager do?
A project manager is leading a council's project that aims to ensure full compliance with health, ecological, and environmental standards.
At the same time, the project's goal is to remain fully adherent to the council's values, policies, and procedures.
How should the project manager ensure project success?
A project manager decided to incorporate the latest technological advancement with the client's devices at no additional cost to the project.
Upon completion and submission of the project deliverables, the client rejected the devices, despite having the latest features.
What should the project manager have done?
An agile project has just started, and the backlog is being prioritized. The
customer wants to prioritize business value over identified risks.
How should the customer’s request be managed?
A team is assembled for a new project that will be using a predictive approach through requirements gathering and an agile approach for development and testing Not everyone on the team has experience working in agile. The schedule has started slipping due to the unclear structure of the agile development approach.
What should the project manager have done to avoid this situation?
A key team member shared confidential information about another team member with management, a practice that is against ethical standards. During a team meeting, some of the team members requested that the key team member be removed from the team.
What should the project manager do next?
A company is moving its headquarters to another city. The project manager responsible for the assignment has been using a predictive approach during the transition. However, the information systems will be migrated using an agile approach. The project manager needs to decide which kind of control to sign with the vendor responsible for migrating the systems.
How should the project manager address this situation?
A new relevant project stakeholder suggested a change to some of the project parameters midway through execution What should the project manager do next?
A project manager has just taken over a project that is halfway through its schedule. In a brief meeting with the client’s key project team, the project manager receives several requests from a specific client team member who was not at the project team meeting. The requests for information seem to be for trivial information that was previously submitted in project documents.
What should the project manager do first?
A project manager is appointed for the deployment of a new solution. The solution will be integrated into the environment by a third-party vendor. This vendor just announced a delay in delivering a key component, which will impact the project schedule.
What should the project manager do?
During the execution phase of a project a new project manager is assigned to replace the previous project manager As the project manager starts managing the project, they discover that team performance is significantly decreasing, which is impacting the project's key performance indicators (KPIs). This team has delivered good performance on similar projects in the past
What should the project manager do next to improve this situation?
A new team member on a self-organizing team is finding it difficult to deliver due to the new technology being used in the project. What should the project manager do in this situation?
A project manager has noticed that the performance of a new team member has increased dramatically over the past few months The project manager has been measuring this team member's performance through the cost performance index (CPl) and schedule performance index (SPl) of work packages. The project manager has also assigned new. unrelated work packages to this team member The project manager wants to formally record the team member's success in the project documentation
What should the project manager do?
An organization is transitioning to an agile environment. The project manager finds that most of the team members are not familiar with an agile environment.
What should the project manager do to address this concern?
A new project manager is assigned to a project in the execution stage. A few key stakeholders inform the new project manager that the project has some serious issues.
What should the newly assigned project manager do first to understand the issues?
The vendor for a new IT data center project failed to follow the required cabling standards as stated in the requirements specification. The infrastructure manager and vendor were involved in an argument about the issue.
What should the project manager do to resolve and prevent additional arguments?
A project manager Is transitioning from a predictive We cycle project to a new agile project How should the project manager manage and control the scope for the new project?
A business stakeholder for a project is reluctant to accept an agile approach due to a previous bad experience, and is pushing for a predictive approach. What strategy should the project manager use to persuade the stakeholder to use an agile approach?
A project manager has two projects that are being executed at the same time. The duration of the critical project must be reduced, but the project manager does not have enough resources to achieve this goal. In addition, the schedule does not have activities that can be overlapped.
What should the project manager do?
A newly hired team member just joined the project team and reports directly to the
project manager. In the first week, this new member tells the project manager that there is a
task priority conflict with hard, dependent tasks on the critical path.
What should the project manager do to handle the conflict?
A project manager works for a large manufacturing company with diversified domains. The project team often participates in change requests Recently, the change control board (CCB) deferred some requests and the project manager wants to communicate these requests to the stakeholders
What document should the project manager use to communicate these requests?
A key agile project team member takes a leave of absence in the middle of an iteration and will not return to work for a while What should the project manager do next regarding the feature on which the team member was working?
An agile team is working on a project that will be launched in six countries. Each country has specific requirements in addition to the base offering. The estimates indicate it will take six months to develop the base offering and an additional month to finalize each country’s unique requirements. The expected revenue for the product is the same for each country.
Which release strategy should the project manager recommend?
A project manager has been assigned to a long-term project. The project manager came across a government debate over a new law that may affect the project.
What are the first two actions the project manager should perform? (Choose two)
In an attempt to streamline project communications, a project manager established a shared portal for all stakeholders to get project information. The sponsor complained about this system and says that it is ineffective.
What should the project manager have done to prevent this situation from occurring?
A team is working on a project using a hybrid approach, and they are facing a lot of obstacles and blockers from some stakeholders. What should the project manager do to improve project performance?
An agile senior project team member suddenly resigns from the organization. Following this departure, the remaining team members are having difficulty accessing information and are unable to complete a deliverable.
What should the project manager have done to avoid this situation?
A project manager is assigned to a technical research project. The project team has
already been assigned, and the main subject matter expert (SME) sends the project
manager a list of the technical skills required for the execution of this project.
What should the project manager do next?
In a multinational project, stakeholders are in different time zones. The project
manager has regular project update meetings with the stakeholders. However, a group of stakeholders who has never attended project update meetings is complaining to the
project sponsor that they know very little about the project.
What should the project manager do?
After a project learn has been working on a project for several months, the project Is cancelled The project sponsor Is putting pressure on the project manager to perform closeout duties as fast as possible so that the project team can move on to other work. The project sponsor has instructed the team not to waste time archiving the project artifacts for the cancelled project.
How should the project manager handle this situation?
A project manager just completed the planning phase when a new stakeholder was assigned to the project. The deliverables were discussed with the customer, but the new stakeholder is still concerned about the benefits of two of the deliverables.
What should the project manager do next to address this stakeholder’s concerns?
An IT project manager for a project that is 50% complete teams that a critical team member plans to relocate to another country soon. The team member is needed for the remainder of the project.
How should the project manager improve team dynamics?
Halfway through a project, the project sponsor is replaced by another peer who was not previously engaged in the project. The new project sponsor has rejected most of the project artifacts, and the team did not get the latest increment approved on the current iteration. Stakeholders are not feeling confident about the project outcome.
What should the project manager have done to prevent this situation?
A project manager is part of a distributed team. The project team is using a product backlog, but due to an excessive workload, the backlog items are not very detailed. In the retrospective, a couple of new team members are raising the issue of knowledge transfer inside the team.
What should the project manager do?
During the implementation phase of a project, functional managers are adding new requirements, which may impact cost and schedule baselines. The project manager
notices that some of the team members are communicating with their managers directly to fulfill their requests. This will lead the project to go beyond the agreed baselines.
How should the project manager handle this situation?
A project manager notices that the project team is unlikely to complete the development of a system on time before the testing start date, which was based on the technical
complexity of the project. What should the project manager do before communicating with the client during the regular project progress meeting?
A project manager is working on a project with three virtual teams. Team A is in a different time zone than teams B and C. The project was going
well, but recently team A has started feeling left out. Information reaches team A late or is sometimes missed, and teams B and C give preference
to each other's problems over team A. The project manager has already set project guidelines, but realizes they need to be improved.
Which two things should the project manager do to help the teams collaborate better? (Choose two)
A project manager is assigned to a multiyear enterprise resource planning (ERP) solution project. During planning, the business sponsor emphasizes the importance of demonstrating value along the way, while maintaining the integrity of the final product.
How should the project manager establish the delivery model for this project?
A project manager is leading the development of a mobile banking application using a hybrid approach. The team has been holding daily standup meetings each workday
morning. Due to an unexpected issue, 50% of the team has to work from home. The bank's management directed the team not to have in-person daily standups. Various team members are complaining about this, stating that there is a lack of information sharing among the team
What should the project manager do?
A project manager is assigned to an agile project that has an aggressive time line and a fixed budget. Currently, the majority of the items are in the backlog and only a few are in process or completed.
What should the project manager do?
A project manager has been assigned to a new digital product line, which the company hopes will boost their revenue. The product is complex and requires customer feedback to continually refine the product. The project is being handled by a cross-functional agile team.
What should the project manager do to ensure value is delivered quickly?
A project manager is leading a multiyear project that involves internal and external stakeholders. As the project manager begins to gather requirements, additional business stakeholders express interest in being involved.
Which three actions should the project manager take to ensure proper stakeholder involvement? (Choose three)
One of the team members is always late to the daily standup meeting. What should the project manager do?
A project team is globally distributed with team members living and working in different time zones. The project manager is trying to get the team
to collaborate effectively.
Which three actions should the project manager take to accomplish this goal? (Choose three)
During project planning, a development team is assigned an agreed-upon work package to determine the appropriate pattern for integrating a new service with a legacy system. The lead developer has requested a meeting with the project manager and Is looking for direction as to which technology to select.
How should the project manager help guide the lead developer?
A project manager is leading a project that will be delivered using a Scrum framework. The organization has an innovative project management office (PMO) that fully supports agile and also has a very friendly procurement team. A new vendor needs to be engaged to provide more developers for a new reporting platform.
What should the project manager do?
A project team has finished participating in an iterative product increment planning session. After the planning session, the team returns with a list of features to deliver.
How should the project manager ensure the product increments deliver the anticipated requirements?
A customer wants to launch a new product in the market and an agile team is set up to work on this project for 9 months After 1 month the customer feels that it would be better to release the product 2 months earlier than the planned date. The task is now assigned to the most talented resource in the organization to this project tor an early finish.
Which risk management strategy has been adopted in this scenario?
A supplier, who was tasked with providing an important component for a project, is unable to deliver the materials due to a large-scale labor problem. What document should the project manager use to update the details and communicate to relevant stakeholders?
A project manager has been assigned to handle a company’s newest product. The product is in the conceptual stages and no one is sure about the success or marketability of the product. Management wants to deliver the product in 3 months.
What should the project manager do next?
A new product is designed for a certain market. This product needs to adhere to the health and safety regulations for that region. What should the project manager do to ensure that the product complies with the regulations?
A project manager Is leading an agile software development project with strict deadlines The client complained that the last deployment did not meet the acceptance criteria The development team lead is arguing that the deployment met all specifications and has provided evidence of the client's specifications
What should the project manager do?
A new member was included on a project team in an ongoing software project. This team member was the only available resource but does not have the proper experience to accomplish the activities.
What should the project manager do to ensure this team member's lack of experience does not negatively impact the project?
Anew systems project requires feedback from the accounting manager at the beginning of solution discussions and before meeting with other functional managers. The project manager knows the accounting manager will not be available until a few days before the deadline for the solution
document.
What should the project manager do to avoid a delay in the project?
A project manager is part of a team that is launching a series of features to comply with a new regulation. The team has only 6 weeks to release the features to the legacy applications. During the standup meeting, a software engineer indicated that the development of an important feature is
on hold until the assigned designer completes a specific task. This delay is a serious road block to meeting the release date.
What should the project manager do?
An agile coach and technical writer for a globally distributed agile team are In a country with a 9-hour time zone difference from the agile team. The agile coach and project lead disagree on the timing for the daily standup. The project lead thinks the standup should be at 10:00 am local time, but
the agile coach and technical writer feel that is an inconvenient time for them.
How does the project lead ensure adherence to agile practices?
A project manager works at an organization that intends to use an agile delivery approach, The product owner asks the project manager what the benefit of agile delivery is from a project evaluation perspective?
How should the project manager reply to the product owner?
A project manager has considered a detailed and expensive training plan for a new technology for all team members. The training is needed several months into the execution phase of a project Surprisingly. many problems still appear that are related to the team members' lack of competence and the training costs are now negatively impacting the budget baseline
What should the project manager do next?
An agile team completes a deliverable that is to be certified by another expert team The second team does not take the deliverable for many months What should the servant leader do?
A project management office (PMO) has been trying to implement an adaptive approach for the project management framework. The project manager has been asked to use adaptive tools in the next project. Awareness of adaptive tools is very low in the company, and many stakeholders are concerned about moving to a hybrid approach.
What should the project manager do?
A project manager is working on a project to modernize the information technology of a bank, The project manager is facing challenges with the project sponsor regarding how to proceed with implementation of a key piece of technology.
How should the project manager resolve this conflict?
A project manager works for a large global company. The project manager is leading a project where the expected business value is to improve the company's image and reputation. During the project's closing phase, the project manager realizes that there is still a negative perception about the company's brand.
What should the project manager have done to prevent this?
A new project team has formed and the project manager notices that some of the team members do not feel comfortable being part of the project team As a result members of the team are working individually and not as a team
What should the project manager do to resolve this?
A project manager has been authorized to begin a project and realizes that an effective high-performing team is needed to finish the project successfully What should the project manager do next?
A project manager for a digital transformation project has already received the business needs for the project. When gathering requirements, the project manager discovers that not all of the requirements can be delivered with the available resources, but that some of the requirements will be
enough to add business value.
With the project on a fixed budget, what should the project manager do next?
An agile team has completed 9 out of 10 stones tor the sprint. During the retrospective a few team members pointed out that they finished a of their stories However one team member tailed to finish a story
What should the agile leader do1?
As a result of the first iteration review, the stakeholders' feedback indicated that they saw more technical features than business ones What should the project manager do?
A project team member is providing updates to assigned work and reports a task as complete, As the project progresses, it is observed that the task is not fully complete.
What should the project manager do moving forward?
A new solution is being deployed in countries A B and C. This solution will allow the countries to propose new services to their customers Country A has asked for a change in the solution m order to comply with its own customer market
What should the project manager in charge of the deployment in country A do?
A lead project manager for an agile project needs to prioritize requirements define the scope of the initial product and deliver the approved scope in a series of multiple versions. What should the project manager do next?
A third-party supplier demands payment for the services provided for a project. The agreement was that payment would be made after the organization receives payment from the client. The third-party supplier lacks the capital to meet their payroll and has informed the project manager that if they do not receive payment quickly, they will withdraw team members from the project.
What should the project manager do?
An agile project is in the seventh iteration with multiple changes being accommodated from the project start due such as regulatory changes technological innovations market competition and other changes What should the project manager do to manage these continuous changes coming into the project?
During a project meeting, the project manager asks risk owners to present issues that may affect the backlog. During their presentation, the project manager realizes that some risk owners did not implement the already agreed-upon risk responses.
What should the project manager do to reduce exposure?
As a result of updated external regulations a project manager has been asked to upgrade the operation system tor a call center The project manager is beginning to meet with and segment the stakeholders involved
How should the project manager categorize the call center staff? Click on the correct section of the power/interest grid.
A project manager is consolidating information tor all the workstreams within a data center and IT service transition project To ensure the project delivers value quickly the project manager will assess a large number of consolidated project schedules
Which two actions should the project manager take with regard to schedule analysis? (Choose two)
The project management office (PMO) has recently adopted some agile practices. During an iteration a key stakeholder in the business is concerned with the benefits management plan in the project document repository and mentions that some benefits have not been updated.
What should the project manager do first?
One of the project manager's important assignments is to formally revise project compliance as it pertains to user data protection regulations. What should the project manager
do to monitor compliance?
A project manager received the project charter for a new product. The project is expected to have two main deliveries: the hardware part that has detailed specifications already defined, including a sample machine, and the user interface software that has only a basic specification and a
requirement for a user experience design approach.
Which project management approach should the project manager use?
A high-tech borehole protect was initiated with the goal of providing water for a rural community of 1500 villagers located in an arid region. The project was completed with a cost performance index (CPi) of 1 09 and a schedule performance index (SPl) of 0.93 Six months after its completion it is determined that the villagers could not access water
What caused this situation to occur?
A project is approaching its project closure phase, and the project manager receives
an email from a key stakeholder who complains that the project documentation and artifacts have not been updated. The project manager assigns a project specialist to support the project management office's (PMO) effort to update the project documentation and artifacts.
Which three actions should the project manager ask the project specialist to take? (Choose
three)
A new project manager is assigned to an ongoing agile innovation project that started 2 weeks ago. After reviewing the project, the new project manager discovered that the previous project manager was planning to use a predictive approach. The previous project manager planned to present the first major deliverable to the client when the project was completely finished in 8 months.
What should the new project manager do?
A project manager needs the team to define the steps and identify the risks of migrating data to a new system.
What type of leadership should the project manager use to accomplish this?
A project manager has been assigned to a high-visibility project that has been identified as having medium complexity, based on previous similar projects. The project needs
to be delivered to the customer as a ready-to-use product .
Based on this scenario, what should the project manager focus on throughout the project life cycle?
Early prototypes developed in a project show an unacceptably high detect rate. The quality management plan calls for a cause-and-effect analysis to address quality problems as they arise.
What is the protect manager's first step in addressing the problem?
A project manager has been asked for performance feedback regarding one of the team members The project manager would like to gather additional input from the project team because there are no metrics in place for evaluating employee performance.
What should the project manager do next?
A company is transitioning their projects to utilize hybrid project management approaches While putting together their project team, the project manager discovers the requirements from the customer are unclear and also realizes that the team members are lacking critical technical stalls needed for project success. However the customer will not accept any changes to the requirements
What should the project manager do to resolve this issue?
During the final iteration of the execution phase, the project has a cost performance
index (CP!) of 0.9 and a schedule performance index (SPI) of 1.0.
How should the project manager avoid a budget shortfall?
we architects are unable to agree on how to approach certain components of the development that will be included In the upcoming sprint. After a one-on-one discussion, the architects have decided to each own a particular module of the system, and the team supports the decision.
What should the project manager do?
A project manager has recently joined an organization and notices that the engineering manager shouts at the project manager during project meetings Also the procurement manager will not return calls and the accountant always insists the project manager clears approved budget line items with them personally before expensing
Which three corrective actions should the project manager perform? (Choose three)
In experienced project manager has never managed an agile project until now. Due to the uncertainty of the project, the project manager is struggling with the definition of the project scope and is taking a long time trying to define it.
What should the project manager do?
A senior developer working on a large artificial intelligence (Al) project has worked hard and shown excellent results. The project manager is very happy with the developer's contribution and thinks that the developer deserves a reward.
What should the project manager do?
In a geographically distributed project team, the project team members continue to email status reports and update schedules after their weekly meeting discussions. However, the team is having difficulty tracking the changes and progress made.
What should the project manager do?
A project manager is working on a project that will transform the organization's operating model. The project manager reviewed the budget allocation for various phases and was informed that upper management will not approve any additional funds.
Knowing that there are no additional funds available, how should the project manager proceed?
A project manager is a part of the project management office (PMO) and Is tasked with finding a reputable vendor to provide on-site support for their project. The project sponsor stresses the urgency of the need and suggests using a vendor they know to provide the support.
What should the project manager do given the urgency?
A large and complex program in an agile environment has experienced an increase in
escalations from the client side. The rates and responsibilities are unclear, and the client does not have any direction regarding the escalation process.
What should be done to resolve this issue?
A project is being delayed due to a large amount of rework caused by a quality problem that is impacting the critical path. What should the project manager do?
It is late at night on a weekend when a team member calls the project manager on the telephone. The team member Is crying about the pressures of an upcoming deadline.
What should the project manager do?
A project manager is leading a project to modemize the information technology of a bank. The project manager needs to determine how the project stakeholders should communicate, and has discussed the various options with the project team.
What should the project manager do to communicate with the stakeholders?
A project is assigned to two different project teams to develop product features. One team uses a predictive approach and the other team uses an agile approach to complete the work. Senior management is concerned about the success of the project.
What should the project manager do?
A client comes to the company asking to copy a project that was executed 2 years ago
in the same city, with the expectation that the new project will have the same cost and duration.
While finalizing the project management plan, the project manager realizes that the baseline
costs are much higher than the original project.
What could the project manager have done to avoid this?
A new project manager has been assigned to a project that is in its second phase The product created in the first phase was transferred to operations During a meeting, the project sponsor complained that some of the reports contain conflicting data on the product value
What should the new project manager do next?
During a project planning phase, the project manager realizes that project performance win be measured based on budget deviation and revenue, but without consideration for the overall project schedule What should the project manager do?
During the execution phase of a large project there is an extremely high number of change requests Because of this the project manager realizes that there is a greater risk for rejection of the deliverables
How should the project manager mitigate this risk without compromising the completion date?
A project learn member is having difficulty delivering assigned tasks for a project that is at risk of being delayed. The main issue is that the team member does not understand a new system that was recently implemented.
What should the project manager do?
A healthcare company requires all new employees to attend mandatory computer-based training courses, Because some of the employees work with highly sensitive patient data, the training covers various aspects of data security. In spite of this training, data breaches continue to occur in
one of the project teams.
What should the project manager do?
A customer is meeting with an agile team at regular intervals and keeps changing priorities for the team members. What should the project manager do to remove this impediment?
A company is launching a new product and decides to transition from a predictive to an agile approach. During the third sprint the project manager notices that the team is not working as a cohesive unit
Which two rules are appropriate tor the project manager to instill in the team? (Choose two)
An established project team with a good track record has been working on a project for one year The project manager trusts the team and the work they produce. Which term describes the project manager's management approach?
A project manager is assigned to a project that has a tight schedule. Due to recent market changes the marketing team has identified that a few features that were initially in the scope are no longer required
What should the project manager do?
A construction services company has influence within the local community with the potential to derail a project site establishment. Their build was unsuccessful but they continue to communicate with the hope that their influence will persuade the project manager to reconsider their offer.
What is the appropriate course of action for the project manager to pursue?
A project manager is working toward a deadline to prepare a client report. The project manager prepared a meeting agenda but not a single meeting has gone according to plan True, meetings always end in arguments and no action items come out of it. The project manager is very frustrated and seeks help from the project sponsor
What should the project manager have created to prevent this situation1?
A project team member is struggling to understand a specific requirement. How should a servant leader address this issue?
An agile team is conducting a sprint retrospective and wants to focus on the practices that allowed them to recover after a bad start Please click on the area of the burndown chart that the team should focus on.
A compliance strategy was created during the planning phase of a project During execution, the project manager left the organization and another project manager was assigned to the team
What should the project manager do first to ensure the project is compliant?
A self-organizing team brings an internal problem to the project manager. What should the project manager do as a servant leader?