The vendor just informed the project manager that an item will not be delivered as scheduled due to a manufacturing error. This will impact the delivery timeline of the
project as there are dependencies to the completion of this item delivery.
What action should the project manager take?
Agroup of specialists with years of experience is temporarily joining a project team. The project manager has been eager for their help in the production of a key
deliverable.
How should the project manager effectively lead these experienced team members?
Acompany merged with a larger company and new project management standards are enforced across the enterprise. The project sponsor is concerned that the
team is not meeting the expectations of the new leaders. The project is at risk of cancellation.
What should the project manager do?
A project is approaching the closure phase. The project manager realizes that the team has consumed more hours than what was budgeted because some nonfunctional security requirements were not considered during project initiation.
What should the project manager do to avoid this issue in the future?
During a review session, the team reports that the daily coordination meetings have been unproductive. The team asks the scrum master to implement a standard
format for the daily coordination meetings.
What should the scrum master do?
A project manager is leading a project for a new type of engine. When the project is in the design phase, the customer requests several new software requirements.
The development team, which is mainly focused on hardware design, is struggling to respond to the requests.
Which two actions should the project manager take? (Choose 2)
Before an application update can be released, the operations team must agree on readiness. This is a listed requirement in the project management plan. Prior to the
next release, the operations team leader requests a meeting so that the operations team can be ready for acceptance and support.
Which two actions should the project manager take? (Choose 2)
During a daily coordination meeting, the team reports that due to considerable challenges with the infrastructure, the planned tasks are now blocked and cannot move
forward. What should the project manager do?
During a project kickoff meeting, two key stakeholders are arguing about the project scope and the acceptance of the deliverable. What should the project manager focus on to address the argument?
A digital health development team is tasked with designing a new product, which is a pioneering effort for the organization and one of the few available in a
‘competitive market. The planning and auditing processes have been notably time-consuming. The development team has reported limited rework and minimal
customer complaints; however, the current budget significantly exceeds the typical project baselines for previous product development initiatives within the
organization. The project manager is currently analyzing the total cost of quality for the project.
What should the project manager do?
In the last project status meeting, a team member reported some tasks with conflicting priorities. Now, other team members are delayed in their tasks due to the
dependencies.
What should the project manager do to address this situation?
The project manager is preparing for the kickoff meeting of a project that follows a ‘plan the work and work the plan’ style. Upon studying the project charter, the
project manager realizes that the project objectives will have to undergo frequent changes throughout the project.
What should the project manager to do?
After a client requested multiple changes to the project scope during a sprint, the sprint goal was no longer valid.
What should the Scrum Master do?
The client believes that a newly assigned team does not fit well and prefers the previous team, whom the client already knows. What should the project manager do?
A project manager is leading a project focused on developing a machine learning platform. Midway through the project, the project manager learns of a new
regulatory policy that will significantly change the way data is stored, processed, and manipulated.
What should the project manager do?
A project team is in the process of selecting a module for the upcoming iteration. They have identified three potential modules as candidates. Despite several rounds
of review, the team remains undecided on which module to select.
What should the project manager do?
The project manager calculates the current cost performance index (CP!) and determines that it is > 1 compared with actual value added. What should the project
manager do first?

According to the Alpha project’s risk management report, which risks should the project manager prioritize?
(Refer to Alpha Project — Risk Management Report exhibit.)
A project to replace a legacy process is in the initiation phase. The project manager needs to send requests for proposals to potential vendors. The business case contains the project’s high-level goals, and all potential vendors have previously delivered similar projects.
What should the project manager do to ensure that activities and tools from the legacy process are retained when necessary?
A project manager is leading a global project involving third-party contractors, internal stakeholders, and regulators. During a project board meeting, stakeholders are
informed of a regional compliance issue that could delay a critical milestone. One stakeholder demands immediate resolution, while another stakeholder thinks it is
not a priority.
What should the project manager do?
A project manager is leading an iterative project to develop a very innovative product. However, a group of stakeholders are hesitant because the high complexity of the product involves many business rules.
What should the project manager do?
A team member has identified a low project risk with a low chance of occurrence.
What should the project manager do?
A project to launch a new financial product is on its fifth out of eight iterations. During the iteration review, a financial stakeholder announces a competitor is launching
a similar product soon. As a result, the stakeholder asks the team to increase velocity.
What should the project manager do?
A project team is working across different time zones and all team members are unable to attend the daily coordination meetings at the same time. The tasks are split
across teams working independently in different regions; however, there are task dependencies between the two teams.
What should the team lead do?
During the execution phase of a complex project, a key government stakeholder was replaced by a new representative from the same agency. During a project
meeting, the new stakeholder expressed complaints about not being informed of recent on-site changes. The stakeholder also said they would not have approved
these changes.
What should the project manager do first?
A project manager is leading a construction project for a retail store. The project manager is using a Gantt chart to present the workflow. One part of the project
includes custom software development to manage the store ' s lighting system, which uses solar energy.
How should the project manager accommodate software development in the project?
A developer has been assigned to complete a project task. At the end of a project meeting, the developer expresses concern about their lack of experience in the technology being used, compromising the project schedule.
What should the project manager do?
‘An organization undergoes a major budget revisal. The project manager gathers the stakeholders to discuss the situation as some projects are stil in-progress and may be impacted.
What two actions should the project manager take? (Choose 2)
During project execution, the development team creates work groups to develop project deliverables. When reporting progress to the project manager, the team
struggles to provide a complete picture of overall progress.
What should the project manager do first?
A project manager is leading a project for a pharmaceutical company. Due to changes in the international market, the project has to be terminated. The project
manager is following company procedures to document the reasons for early termination.
What should the project manager do?
A project is delayed because of an unknown risk impacting the budget. The project manager requests the project management office review the recommendation for a
budget increase.
What should the project manager have done to avoid going over budget?
The project manager could not get the estimated initial budget for an infrastructure project, leaving the team uncertain about which part of the project should be
‘started. What should the project manager do?
A city infrastructure project aims to construct a bridge to enhance traffic flow and alleviate congestion. The project is under tight deadlines due to upcoming major events in the city. The team is employing a hybrid approach by incorporating agile practices into a traditionally structured project schedule.
A key stakeholder asks the project manager to expedite the delivery of specific work packages. The project manager determines that this request will affect the project cost.
What should the project manager do?
|
A project team is developing a product with monthly deliverables. The user feedback collected after each iteration affects how the product is developed further.
How should the project manager process the changes?
The project manager of an international marketing campaign is coordinating with global teams and must align activities across several time zones. With such
geographical diversity, what should the project manager do?
A project manager is leading an important development project. A key deliverable has been completed but does not meet the quality standards defined in the quality management plan.
What should the project manager do?
A project manager is engaged in a process improvement project. The business analyst working with the team has been instructed to interact with line production team
members in an efficient manner. Since process duplication would affect their reaction time, line production team members have a significant interest in process
improvement to improve quality.
How should the project manager advise the business analyst to improve interaction with the line production team?
A project team provided estimates for a hybrid project, but in every case those estimates were undervalued. On the current trajectory, the project will not meet its
intended value before it runs out of budget.
What should the project manager do?
During the execution of a healthcare company project about new solutions, a team member finds a recently published article by the market ' s leading expert. The
article introduces drastic changes driven by a new norm for future healthcare products.
What should the project manager do?
During a project status meeting, two project stakeholders disagree about what should be included in the next deliverable. One of the stakeholders would like the team to include a finalized version of the new component in the release. Using the finalized version will impact the project timeline. The second stakeholder would like the team to include a beta version of the new component to allow the client to provide feedback before the component is finalized.
What should the project manager do next?
A project manager joined an ongoing project to replace another manager. After one iteration, the project manager noticed that team morale is low. Team members are
reluctant to speak at first, but tell the new project manager about a history of conflicts.
What should the project manager do next?
A project manager has recently conducted a kickoff meeting for a project aimed at updating a product for a client in the insurance services sector. The product owner
has given notice of their departure from the company in two months, prompting the client to express concerns about the change in personnel.
What should the project manager do?
A project manager notices that every time a new member joins the team, they spend too much time learning business terminology. This trend has impacted system
integrations and creates delays on a few tasks that other teams depend on.
What should the project manager do?
Health Records Modernization at Hospital Case Study
A project manager led a health records modernization project at a hospital with a project budget of $US5 million and an 18-month timeline. The project involved multiple stakeholder groups including medical, administrative, and IT staff; board members; patients; insurance companies; external vendors; regulatory bodies; and union representatives.
Stakeholder management was complex and a major undertaking for the project manager, but it was critical to achieve a positive project outcome. When the project started, the project manager conducted stakeholder analysis, using the information to create both a power/interest and an influence/impact matrix. The analysis showed that while the hospital board members and regulatory bodies had high power but moderate interest, the medical staff (doctors and nurses) had both high influence and high impact on the project. Administrative staff showed high interest but lower power, while patients and insurance companies had moderate interest and varying levels of influence. Based on the analysis, the project manager created a stakeholder engagement strategy that documented expectations, communication preferences, and influence levels in a stakeholder register. The project manager also made a RACI (responsible, accountable, consulted, informed) chart to show roles and responsibilities; and created communication channels and frequency for each stakeholder group, an issue escalation system, and a feedback system for continuous stakeholder input.
To execute the modernization process of health records, the project manager realized that medical staff members would need to change their daily workflows. To facilitate change management for these stakeholders, the project manager created a clinical advisory committee, appointed department-specific “champions,” created focus groups for requirements gathering, started a training program, and developed key performance indicators (KPIs) to measure satisfaction.
During project execution, several challenges emerged. The doctors expressed concerns about the system’s impact on patient care, the nurses’ union raised workload concerns, the IT department faced resource constraints, the insurance companies requested additional features, and the administrative staff worried about data security. The project manager responded to these challenges by increasing the frequency of stakeholder meetings, implementing a change management program, creating a beta system for stakeholder testing, developing contingency plans for various stakeholder scenarios, and establishing an issue resolution process.
Despite these mitigation efforts, the medical staff required additional training, leading to a change request for a 2-month extension and a 10% budget increase. The board of directors approved this to help ensure high adoption and satisfaction rates among staff members. The project helped establish new good practices in future programs for stakeholder management in the organization’s project management office (PMO). The documented lessons learned became a reference for future projects of similar scope and complexity.
A project to modernize a hospital’s records has a large and diverse stakeholder population. As stakeholders request changes, the project manager is aware that some will cause a negative impact to the project timeline and finances.
What should the project manager do?
(Refer to the Health Records Modernization at Hospital Case Study exhibit.)
During a team ' s weekly status meeting, team members have minor disagreements about how to perform work and some defer to the team lead while others speak
confidently. The project manager realizes that team members have different expectations of the team ' s dynamics and operating model.
What should the project manager do?
An organization, which has no previous experience with adaptive approaches, is seeking to adopt agile practices to improve the speed of value delivery to its internal business units. An agile expert has been engaged to assist the project manager in facilitating this transformation.
What should the project manager do?
The project manager is utilizing a hybrid management approach for a creative project. The organization is undergoing a change aimed at improving cross-functional
collaboration, which may impact the project scope.
What should the project manager do first?
A project manager is developing a project schedule in which only the high-level scope is defined; the detailed work breakdown structure (WBS) is to be developed at
the beginning of each project phase. Project teams are focusing on short-term objectives and can only detail the scope for work they are currently performing. Despite
this, the project sponsor asks for a master project schedule.
What two actions should the project manager take in this situation? (Choose 2)
A project manager leads an agile project. While the team is working on their daily assigned tasks, one team member proposed to change the priority of a task due to
its importance and dependency on other tasks.
What should the project manager do?
A project manager was assigned to lead a construction project where a hybrid approach is recommended. A team with high levels of knowledge and experience is
required.
What should the project manager do next?
There are considerable differences in experience levels among project team members working on a project. Multiple stakeholders are requesting that deliverables
relevant to them be assigned to the most experienced team members, which is not feasible.
What should the project manager do?
Midway through a product launch, a major supplier announces a three-week shutdown due to a warehouse fire. This supplier provides hardware that is critical to integration testing.
What should the project manager do?
Akey stakeholder has been mostly silent until now. To optimize resources, the stakeholder wants to move one team member to another project but the project
manager does not agree.
What should the project manager do?